Capital Budgeting Analysis for
Medical Services USA
Purpose of Spreadsheet
Supplemental Material for Short Course 3: Cap
Budgeting Analysis, located on the internet at
www.exinfm.com/training. Prepared by: Matt H
Evans, CPA, CMA, CFM
Illustrate concepts related to capital budgeting analysis of projects. Certain aspects of a capital
project may have not been included in order to help highlight basic concepts, such as
Net Present Value. The spreadsheet is setup to evaluate six different projects and summarize
all projects based on both economic analysis and risk factors assigned.
Note: The Solver feature of Excel is used in an example at the end. Please make sure that you
have installed Solver: Solver add-on feature (Tools => Add-Ins => Solver).
Economic Analysis
Three economic criteria are applied to projects: Net Present Value, Modified Internal Rate of
Return and Discounted Payback Period. If your project(s) have non-periodic payments
(payments are not equal over the life of the project), then you should use these Excel Functions:
=XNPV for Net Present Value by entering specific dates of cash flows
=XIRR for Internal Rate of Return by entering specific dates of cash flows
Cell Indicators
Certain cells are highlighted as follows:
Selected input cells (not all input cells are highlighted since each project is unique)
Cell includes a comment - move mouse and point over cell for comment
Indication of an error in calculation or a red flag that a criteria has not been met
Organization of Spreadsheet
Lead Worksheet
Project A Analysis - Example with Annual Cash Flow Calculations
Project B Analysis - Example with Sunk Costs & Projected Financials
Project C Analysis - Example of Upgrade Investment
Project D Analysis - Example of Project Financing
Project E Analysis - Example of Foreign Investment
Project F Analysis - Example of Monthly Inflows / Outflows
Summary and Example of Using Excel Solver
Answer Report 1 - Output from Using Excel Solver in Summary Example
General Input
The following general inputs have been used on different worksheets:
A
B
C
D
E
F
Diesel Generation System
<= Enter project name
New Clinic in Kansas City
<= Enter project name
Upgrade to DuBois Center
<= Enter project name
Southeastern Upgrades
<= Enter project name
Canadian Partnership
<= Enter project name
Regulatory Compliance NE
<= Enter project name
27.50% <= Marginal Tax Rate *
9.50% <= Weighted Average Cost of Capital
$10,000 <= Threshold investment amount where formal project analysis
is not required - general expenditure item.
* If you expect changes in future tax rates, you may want to consider these changes
in your analysis.
Project Codes (Used to help categorize various capital projects)
Project Classification Codes:
1 Land
2 Buildings
3 Leasehold Improvement
4 Equipment
5 Furniture and Fixtures
6 Vehicles
7 Acquisitions
8 Investments
9 Other
Primary Justification for Project:
A Cost Reduction
B Replacement
C Expansion / Addition
D Service Improvement
E Safety & Compliance
F Operating Necessity
G Other
Priority Code:
1 Carry over project, already in progress, requires additional funding
2 Essential for continued operations, regulatory compliance, etc.
3 Economically desired for revenue growth, cost reductions, etc.
4 General improvement for building or expanding the business
erial for Short Course 3: Capital
s, located on the internet at
raining. Prepared by: Matt H.
CFM
Lead Wks
Project A
Project B
Project C
Project D
Project E
Project F
Summary
ormal project analysis
A
Capital Budgeting Analysis for
Medical Services USA
Diesel Generation System
Project Information
Project Description > New diesel backup system for high volume medical plant
Project Benefits >
Eliminate downtime, improve efficiency, better service
Project Location >
Mobile, AL
Responsible Division >
Southern
Responsible Department >
Plant Engineering
Contact Person Name >
John Pearson, Southern Div Manager
Estimated Project Start Date >
01/01/92
Classification >
4
Justification >
F
Priority >
2
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
2
3
3
1
0
0
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
4
0
0
0
0
0
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
2
4
1
2
0
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
Enhances workforce productivity
0
0
M3
M4
M5
M6
M7
M8
Project meets a critical regulatory, security or specific need
Project fits with company strategy and goals
Probability of project success is very high / low risk
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
0
1
4
0
0
0
27
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Financial Analysis
Proposed Project Expenditure:
* Equipment & Facilities (purchase price)
* Installation Cost
* Labor
* Materials
* Shipping
* Taxes
Other Costs (expensed)
Intial Cash Outlay for Project
Tax Breaks for Investment
Sale of Existing Assets
Tax Benefit on Loss - Sale of Assets
Total Project Investment
Project Analysis Required?
* capitalized costs subject to depreciation using double declining method over 8 years with $ 8,000 salvag
NOTE: Depreciation for tax purposes is considered the same for accounting purposes. If tax depreciation
different than accounting depreciation, deduct tax depreciation in calculating taxes.
Cash Flows associated with Project:
Year 1:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
1
Operating Cash Flow in Year 1
Less Taxes
28,900
6,200
35,000
(4,600)
(1,500)
(45,808)
18,193
(5,003)
Net Income - Year 1
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 1
Year 2:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
2
Operating Cash Flow in Year 2
Less Taxes
Net Income - Year 2
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 2
Year 3:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
3
Operating Cash Flow in Year 3
Less Taxes
Net Income - Year 3
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 3
Year 4:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
Depreciation in Yr
Operating Cash Flow in Year 4
Less Taxes
Net Income - Year 4
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 4
8
4
Year 5:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
5
Operating Cash Flow in Year 5
Less Taxes
Net Income - Year 5
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 5
Year 6:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
6
Operating Cash Flow in Year 6
Less Taxes
Net Income - Year 6
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 6
Year 7:
Reductions in annual operating costs
New revenues from higher output volumes
Eliminate third party vendor service
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
Salvage Value
Useful Life
Depreciation in Yr
Operating Cash Flow in Year 7
Less Taxes
Net Income - Year 7
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 7
(2,400)
183,230
8,000
8
7
Year 8:
Reductions in annual operating costs
New revenues from higher output volumes
Rebuild / Repair Unit Option
Annual service and maintenance
Annual fuel costs
Depreciation:
Cost
183,230
Salvage Value
8,000
Useful Life
8
Depreciation in Yr
8
Operating Cash Flow in Year 8
Less Taxes
Net Income - Year 8
Add Back Non Cash Depreciation
Change to Net Working Capital
Net Cash Flow - Year 8
Terminal Year 9
Salvage Value of Asset
Working Capital Reversed
Terminal Value
(8,153)
44,247
(12,168)
32,079
8,153
(150)
40,082
55,500
11,000
(25,000)
(4,600)
(2,600)
(6,115)
28,185
(7,751)
20,434
6,115
(50)
26,499
5,000
2,500
7,500
At the end of Year 8, a decision will be made to either rebuild the asset or outsource to third party.
Economic Analysis
Summarize Cash Outflows and Inflows for Project:
Cash
Present
Recovery
Year
Flows
Value
Payback
0
(182,080)
(182,080)
1
55,497
49,997
(132,083)
2
57,518
46,683
(85,400)
3
57,213
41,834
(43,566)
4
32,469
21,389
(22,177)
5
34,303
20,357
(1,820)
6
36,334
19,426
17,606 <= payback
7
40,082
8
26,499
9
7,500
Net Present Value
19,306
11,499
2,932
51,342
36,912
48,410
51,342
Required Rate of Return for Project =>
Reinvestment Rate for Project =>
Net Present Value
Modified IRR
Discounted Payback (years)
11.00%
6.00%
$51,342
11.03%
6.1
Economic Assessment
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
Yes
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis
Risk Premium Applied to Project
1.50%
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
1.00 (a)
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
1 (b)
Exponential power to apply to Risk Ranking is 2 - (a)
1 (c)
Risk Factor = (b) raised to the power (c)
1
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
d over 8 years with $ 8,000 salvage value
nting purposes. If tax depreciation is
or outsource to third party.
B
Capital Budgeting Analysis for
Medical Services USA
New Clinic in Kansas City
Project Information
Project Description > New Walk In Clinic - Kansas City
Project Benefits >
Toehold market position, profit center, business expansion
Project Location >
Kansas City
Responsible Division >
Mid West
Responsible Department >
Business Development
Contact Person Name >
Bill Watson, Operations Director
Estimated Project Start Date >
04/01/92
Classification >
2
Justification >
C
Priority >
3
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
Enhances workforce productivity
M3
Project meets a critical regulatory, security or specific need
M4
Project fits with company strategy and goals
M5
Probability of project success is very high / low risk
M6
Other Misc Attribute _____________________________________
M7
M8
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Financial Analysis
Proposed Project Expenditure:
Rework / Upgrade Existing Building
Equipment and Fabrication
Marketing and Promotion of Clinic
Contingency Costs
Market Study / Research
Total Project Investment
Project Analysis Required?
85,000 (1)
45,000 (2)
7,500
3,500
2,500 <= exclude since sunk cost, not rele
141,000
Yes
(1): Depreciated over 30 years using the straight line method with no salvage value.
(2): Depreciated over 12 years using the declining balance method with no salvage value.
Tax depreciation and accounting depreciation are considered the same.
Working Capital Requirements:
Historical analysis of other similar clinics indicates that clinics require:
Cash
Accounts Receivable
Inventories
Total Current Assets
Accounts Payable
Other accruals
Total Current Liab
Net Working Capital
Sales Revenues
Ratio (NWC / Sales)
The above Ratio will be applied to estimate working capital requirements
Opportunity Cost Analysis:
As a result of this project investment, the company expects some negative impact to its
Topeka, Kansas facility as follows:
Year 1
Year 2
Reduction to Sales Revenues
(4,000)
(5,000)
Reductions in overall cost
1,500
2,000
Net Reduction to Income
(2,500)
(3,000)
Five Year Financial Forecast:
Sales Revenues
Year
1
65,000
Year
2
75,000
Cost of Services:
Personnel / Labor
Supplies, Vendors, etc.
Adm Overhead Increases
Opportunity Cost (per above)
Profit before Tax
Taxes
Investment Credits
Net Profit
Depreciation:
Upgrade to Building
Useful Life =>
30
Equipment
12
Operating Cash Flow
Net Working Capital
Planned Critical Cash Outlays
Total Cash Flow
Economic Assessment
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
No
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis
Risk Premium Applied to Project
3.00%
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
Exponential power to apply to Risk Ranking is 2 - (a)
Risk Factor = (b) raised to the power (c)
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
Enter Expected Cash Flows for different outcomes:
Capital Budgeting Analysis for
Medical Services USA
Upgrade to DuBois Center
Project Information
Project Description >
Upgrade DuBois for unused capacity
Project Benefits >
Better use of facility, more income
Project Location >
Iowa
Responsible Division >
Mid West
Responsible Department >
Finance
Contact Person Name >
Cheryl Strickland, Controller
Estimated Project Start Date >
03/15/92
Classification >
4
Justification >
C
Priority >
3
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
Enhances workforce productivity
M3
Project meets a critical regulatory, security or specific need
M4
Project fits with company strategy and goals
M5
Probability of project success is very high / low risk
M6
Other Misc Attribute _____________________________________
M7
M8
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Cost Volume Profile of DuBois Facility
Personnel & Labor
Supplies and Inventory
Variable Adm Overhead
Fixed Overhead Costs
Total Unit Costs per Billable Hour
37.50
2.65
3.60
10.50
54.25
Current Operating Capacity =>
60%
Maximum Capacity per month
15,000 billable hours
Sales growth rates over the next ten years are estimated at 4% per year with increases to costs
estimated at 1.5% per year for each variable component.
Estimated Changes from Upgrade Investment
Upgrade Investment will result in additional 5,000 billable hours per month
New Services from Upgrade Investment are billable to customers at $ 50.00 per hour
Capacity after upgrade =>
14,000
Does upgrade project exceed max?
No
Financial Analysis
Proposed Project Expenditure:
Upgrade Systems & Facilities
Executive Management Time
Training and Promotion
Contingency Costs
Total Investment
Project Analysis Required?
Due to the rapid changes in services provided by this upgrade investment project, no
calculated for the periods beyond year 10.
Economic Analysis
Summarize Cash Outflows and Inflows for Project:
Cash
Present
Year
Flows
Value
0 (1,780,000) (1,780,000)
1
256,875
233,523
2
295,578
244,279
3
334,811
251,548
4
374,625
255,874
5
416,074
258,349
6
459,215
259,215
7
504,105
258,685
8
550,802
256,953
9
599,369
254,191
10
649,868
250,552
Net Present Value
743,170
Required Rate of Return for Project =>
Reinvestment Rate for Project =>
10.00%
4.00%
Net Present Value
Modified IRR
Discounted Payback (years)
$743,170
11.24%
8.07
Economic Assessment
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
Yes
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis
Risk Premium Applied to Project
0.50%
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
Exponential power to apply to Risk Ranking is 2 - (a)
Risk Factor = (b) raised to the power (c)
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
Enter Expected Cash Flows for different outcomes:
Capital Budgeting Analysis for
Medical Services USA
Southeastern Upgrades
Project Information
Project Description >
Upgrade to various Southeastern facilities
Project Benefits >
Better use of facility, more income
Project Location >
Atlanta
Responsible Division >
Southeast
Responsible Department >
Engineering
Contact Person Name >
Bob Ferrell
Estimated Project Start Date >
02/05/92
Classification >
4
Justification >
C
Priority >
3
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
Enhances workforce productivity
M3
M4
M5
M6
M7
M8
Project meets a critical regulatory, security or specific need
Project fits with company strategy and goals
Probability of project success is very high / low risk
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Project Summary
Several facilities in the Southeast area need to upgrade existing scanner equipment to better serve customers
and produce higher quality analysis / treatments. The Atlanta Bank has agreed to finance $ 500,000 towards
the investment at 9% over a five year period. The loan repayment schedule is as follows:
Interest Number of
Rate
Installments
0.09
5
Principal
Payment
(83,546)
(91,065)
(99,261)
(108,195)
(117,932)
Total
Payment
(128,546)
(128,546)
(128,546)
(128,546)
(128,546)
Financial Analysis
Proposed Project Expenditure:
Total Upgrade Acquisition Price
Installation / Training / Other Costs
Total Investment
Financed through Bank
Net Cash Outlay
Project Analysis Required?
After Tax Cost of Borrowing =>
Reinvestment Rate for Project =>
Net Present Value
Modified IRR
Discounted Payback (years)
6.53%
2.50%
$389,865
6.38%
10.87
Economic Assessment (based on Analysis #1)
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
No
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis (based on analysis #1)
Risk Premium Applied to Project
2.25%
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
Exponential power to apply to Risk Ranking is 2 - (a)
Risk Factor = (b) raised to the power (c)
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
1.00
1
1
1
0.65
6
1.35
11
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
Capital Budgeting Analysis for
Medical Services USA
Canadian Partnership
Project Information
Project Description > Expand Toronto Urban Centers
Project Benefits >
Market expansion, new source of revenues, leverage of assets
Project Location >
Toronto
Responsible Division >
Canadian Division
Responsible Department >
Marketing
Contact Person Name >
Allen J. Herbert
Estimated Project Start Date >
04/01/92
Classification >
8
Justification >
C
Priority >
3
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
Enhances workforce productivity
M3
M4
M5
M6
M7
M8
Project meets a critical regulatory, security or specific need
Project fits with company strategy and goals
Probability of project success is very high / low risk
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Project Summary
In order to establish a toehold position in the Toronto area, a joint venture investment will be
made since the current major provider in Toronto needs improved child care services for the
urban areas of Toronto. Medical Services USA will provide personnel and overall management
for urban child care. In return, Medical Services USA will share in the profits 50% / 50%. The Joint
Venture Agreement has a ten year term period.
Financial Analysis (all amounts are expressed in Canadian Dollars)
Convert
to U.S.$ *
Initial Relocation / Setup Costs
$750,000
1.12
$840,000
Ten Year Projected Income Statement
Year
1 **
2
3
4
5
6
7
8
9
10
* convert from Canadian Dollars to U.S. Dollars
** partial year in 1992
Economic Analysis (U.S. Dollars)
Summarize Cash Outflows and Inflows for Project:
Cash
Present
Net
Income
288,000
410,000
434,000
460,000
495,000
518,000
543,000
595,000
634,000
675,000
Required Rate of Return for Project =>
Reinvestment Rate for Project =>
13.50%
3.50%
Net Present Value
Modified IRR
Discounted Payback (years)
$876,491
16.95%
5.30
Economic Assessment
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
Yes
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis
Risk Premium Applied to Project
4.00%
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
Exponential power to apply to Risk Ranking is 2 - (a)
Risk Factor = (b) raised to the power (c)
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
Enter Expected Cash Flows for different outcomes:
Capital Budgeting Analysis for
Medical Services USA
Regulatory Compliance NE
Project Information
Project Description >
Regulatory Compliance in NE
Project Benefits >
Compliance
Project Location >
Northeast Regional Office - Boston, MA
Responsible Division >
Finance
Responsible Department >
Finance
Contact Person Name >
Carl Jackson, V.P. Finance
Estimated Project Start Date >
01/01/92
Classification >
9
Justification >
E
Priority >
2
Preliminary Review
Assign points from 0 to 5 for each of the following project attributes. 0 indicates that the
attribute does not apply to the project. 5 is the highest rating, indicating that the project
strongly meets this project attribute.
Financial Attributes:
F1
Project improves overall profitability of the company
F2
Project lowers cost structure
F3
Project will generate a rate of return
F4
Project improves asset utilization
F5
Other Financial Attribute __________________________________
F6
Other Financial Attribute __________________________________
Operating Attributes:
O1
Improves operating efficiencies
O2
Increases the customer base
O3
Improves overall customer service
O4
Improves competitive position of company
O5
Other Operating Attribute _________________________________
O6
Other Operating Attribute _________________________________
Contingency Attributes:
C1
Project has options that allow for change during life
C2
Project will positively impact company even if value is negative
C3
Project can be abandoned easily with some positive value
C4
Project permits several options to maximize value
C5
Other Cont Attribute _____________________________________
Miscellaneous Attributes:
M1
Expands Human Resource Capital
M2
M3
M4
M5
M6
M7
M8
Enhances workforce productivity
Project meets a critical regulatory, security or specific need
Project fits with company strategy and goals
Probability of project success is very high / low risk
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Other Misc Attribute _____________________________________
Total Preliminary Points
Projects with point totals less than 15 may represent poor investments and require additional
approval before further analysis and processing. Projects with point totals between 15 and 20
require caution and careful analysis. Projects with point totals greater than 20 may proceed
with analysis and submission.
Project Summary
A major regulatory change is expected to change certain services in the Northeastern United States.
In order to meet this new mandate, an investment is required in field personnel, training, and
equipment. Revenues from the new services are also forecasted based on demand in California
which adopted this regulatory change two years ago. The regulatory change is subject to future
modification and therefore, the project is only projected over two years on a month to month basis.
There is no initial investment required for this project.
Economic Analysis (Cash Flows by Month)
Required Rate of Return for Project =>
Net Present Value
Rate of Return (IRR Annual Basis)
Discounted Payback
Immediate
Economic Assessment
Project has positive Net Present Value?
Project has IRR in excess of cost?
Project has a positive payback?
Yes
Yes
Yes
Project must meet at least two of the three Economic Criteria, otherwise special
approval is required.
Risk Analysis
Risk Premium Applied to Project
0.00% (Required for Compliance)
Compare Risk Factor with Government Treasury Bond (lowest risk) to Project Risk Factor:
Risk Ranking = 1 for lowest possible risk up to 10 for highest possible risk
Probability of Accurate and Reliable Information - Gov't T Bond
Risk Ranking assigned to Gov't Treasury Bond ( 1 to 10)
Exponential power to apply to Risk Ranking is 2 - (a)
Risk Factor = (b) raised to the power (c)
Probability of Accurate and Reliable Information for Project
Risk Ranking assigned to project (1 to 10)
Exponential power to apply to Project
Risk Factor for Project
Assign probabilities to three possible outcomes for project:
P Pesimistic outlook, declining growth, slower volumes, etc.
N Normal expected outlook as applied in analysis
O Optomistic outlook, better than expected growth
Total should equal
100.00%
Enter Expected Cash Flows for different outcomes:
Capital Budgeting Analysis for
Medical Services USA
Summarize Economic and Risk Analysis for All Projects
Project
Ref
A
B
C
D
E
F
Project Name
Diesel Generation System
New Clinic in Kansas City
Upgrade to DuBois Center
Southeastern Upgrades
Expand Toronto Urban Centers
Regulatory Compliance in NE
* Provide additional narrative information on "strategic" reasons for making this investment since the return is less th
Using Solver for Program Constraints
Financial Modeling Textbooks provide useful examples of how Excel Solver can be used to solve for capital budgeti
set of constraints. The following example will illustrate how we could apply Solver for finding the right set of projects
Example:
Objective: Maximize Net Present Value of Projects
Contraints: Year 1: Only $ 200,000 can be spent on all capital projects
Year 2: Only $ 150,000 can be spent on all capital projects
Year 3: Only $ 120,000 can be spent on all capital projects
Year 4: Only $ 100,000 can be spent on all capital projects
Year 5: Only $ 75,000 can be spent on all capital projects
Five Projects require investments over five years and have the following Net Present Values:
Select?
Project 0 = No
Ref
1 = Yes
A
B
C
D
E
1
0
1
1
0
Project Name
Annual Marketing Program
IT Infrastructure Development
Executive Leadership
HR Capital Improvement
Product Research
Total (SumProduct)
Maximum Allowed Budget
< - - - - - Five Year Capital Budgets for Each Project - Year 1
Year 2
Year 3
45,000
55,000
25,000
35,000
50,000
99,051
200,000
40,000
60,000
20,000
30,000
45,000
85,282
150,000
We will enter the following constraints into Solver:
$ 45,000 A + $ 55,000 B + $ 25,000 C + $ 35,000 D + $ 50,000 E .LE. $ 200,000
$ 40,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 45,000 E .LE. $ 150,000
$ 38,000 A + $ 60,000 B + $ 20,000 C + $ 30,000 D + $ 42,000 E .LE. $ 120,000
38,000
60,000
20,000
30,000
42,000
83,672
120,000
$ 35,000 A + $ 58,000 B + $ 18,000 C + $ 28,000 D + $ 40,000 E .LE. $ 100,000
$ 35,000 A + $ 55,000 B + $ 17,000 C + $ 27,000 D + $ 40,000 E .LE. $ 75,000
Each of the above constraints recognizes that we can spend no more than what is budgeted each year. We also
have the equation we are trying to solve for:
Maximize NPV = $ 650,000 A + $ 820,000 B + $ 540,000 C + $ 701,000 D + $ 490,000 E
We will also use as our variables "0" for No and "1" for Yes as to which projects we should select given the above
constraints and equation. The "maximum" NPV will show up in our "set" cell which is cell D43.
Now go to the main toolbar, select Tools -> Solver and enter the following:
1. Target Cell is D43
2. Equal to: Select the Max button since we are solving for maximum values.
3. By Changing Cells: Select the range B38:B42 as our variables.
4. Subject to Constraints: Add two contraints as follows:
B38:B42 .EQ. Binary
EQ or = (equal)
E43:I43 .LE. E44:I44
LE or <= (less than or equal to)
5. Click on Solve. The Find Solution dialog box may pop up. Click on Answer. Solver will change the variables
(which we first entered all as zero's in cells B38:B42) and produce a report (Answer Report 1)
Using Excel Solver, we would select Projects A, C, and D!
Project
Value
$34,761
$4,127
$715,502
$416,502
$818,923
$705,507
9.50% <= weighted average cost of capital
rate of return is less than weighted average cost of capital *
(years)
Rate of
Payback
Risk
Relative
Absolute
Return
Period
Factor
Risk
Risk
10.07%
9.68%
11.12%
9.33%
16.58%
298.86%
6.6
19.0
8.2
8.0
5.5
0.0
9.5
18.5
6.1
11.2
12.3
5.7
ent since the return is less than the cost of investments (cost of capital).
d to solve for capital budgeting program decisions given a
ding the right set of projects given a set of contraints:
Budgets for Each Project - - - - - >
Year 4
Year 5
35,000
58,000
18,000
28,000
40,000
77,154
100,000
Microsoft Excel 9.0 Answer Report
Worksheet: [CBAnalysis.xls]Summary
Report Created: 2/26/2003 9:58:29 AM
Target Cell (Max)
Cell
Name
$D$43 Total (SumProduct) NPV
Original Value
0
Final Value
1,806,385
Adjustable Cells
Cell
Name
$B$38 A 1 = Yes
$B$39 B 1 = Yes
$B$40 C 1 = Yes
$B$41 D 1 = Yes
$B$42 E 1 = Yes
Original Value
0
0
0
0
0
Final Value
Constraints
Cell
Name
$E$43 Total (SumProduct) Year 1
$F$43 Total (SumProduct) Year 2
$G$43 Total (SumProduct) Year 3
$H$43 Total (SumProduct) Year 4
$I$43 Total (SumProduct) Year 5
$B$38 A 1 = Yes
$B$39 B 1 = Yes
$B$40 C 1 = Yes
$B$41 D 1 = Yes
$B$42 E 1 = Yes