CONSTRUCTION AND DESIGN OF
MULTISTOREY BUILDING
AT
UNITECH LTD
INTRODUCTION
Projects Undertaken
1. Construction of residential building (escape)
1.1
1.2
1.3
1.4
Excavation, Layout and Foundation
Column layout, shuttering and casting
Slab, Beam shuttering and casting
Important Components
2. Introduction to bonded slab post tensioning
2.1 Post tensioning
2.2 benefits
2.3 Tendons and stressing
Projects Undertaken
3. Design of building component
3.1
3.2
3.3
3.4
Formwork design
Staircase design
Deep Beams
Slabs
PROJECT 1
CONSTRUCTION OF MULTISTOREY BUILDING
Excavation, Layout and Foundation
Excavation is a process of making trenches by digging up
of earth for the construction of foundations and
basements.
Excavation level at escape site is 219.825 mm
Excavation is done by the JCB on the hourly basis
After the excavation the surface is leveled called surface
dressing
Layout is done on the PCC poured over leveled surface.
Column and foundation (raft ) steel is then laid as per
drawings.
Points to take care: layout should be checked properly.
Check any difference between architectural and structural
drawings regarding location of column.
After excavation check the stability of temporary structures built
near the excavated ground.
Before laying raft reinforcement, shuttering wall which is mainly
brick wall should be built and should be filled with soil on other
side.
Check the direction of chair bars in the raft