Construction and Design of Multistorey Building

Comments

Content

EXCAVATION

LAYOUT

RAFT FOUNDATION

COULMN CASTING
 On the raft the column layout is done.
 Layout for starter.
 The column ties and link bars are provided as per column





reinforcement drawings and general specifications.
Displacement of main bars should be provided with L bar
The plumb of formwork should be checked.
Height of cast should be calculated accurately.
Avoid caps as far as possible.

LAYOUT , PEDESTAL & STARTER

LINKS & TIES

PLUMB & FORMWORK, CASTING,CURING

SLAB, BEAM SHUTTERING & CASTING
 beam bottom is first laid on the column and then slab formwork

is laid
 After the reinforcement, the slab is checked for steel as per

drawings and level required.
 A camber of 5 mm in provided in the center of slab.
 Casting of slab should be discontinue at l/3 from the support.

SLAB STAGES

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close