LANCO AMARKANTAK POWER PVT. LTD. (UNIT#1 300MW)
Date of inspection:

LAPPL Ref No.-

System – Cooling Tower
Sl No.

1

Activity-Pre commissioning checks
Status

Activity

Yes/No

Remarks

The name plate legend agrees with the approved LAPPL
Plant Nomenclature is clearly visible, properly fixed, durable
and correct with labels.

2

The installation is complete and correct in accordance with
latest drawings.

3

Access for adjustment, maintenance and repairs is
satisfactory.

4

Necessary lifting tools have been provided for future
maintenance, if applicable.

5

Lubricating facilities are satisfactory and correct grades of
oil/grease have been applied.

6

Confirm plant undamaged, fixed and mounted satisfactorily.

7

Check that oil level in bearings can be adequately monitored.

8

Check that there are adequate facilities for filling and draining
of oil.

9

Check that fan is free to rotate and Direction of
Rotation is marked.

10

Check that all foreign materials and temporary
fixtures/supports are removed.

Signature
LAPPL

LITL

PAHARPUR

LANCO AMARKANTAK POWER PVT. LTD. (UNIT#1 300MW)
Date of inspection:

LAPPL Ref No.-

System – Cooling Tower
Sl No.

11

Activity- Pre commissioning checks
Status

Activity

Yes/No

Remarks

Check that all Water line valves are opening and closing
freely (by hand) and check remote operation of the valves, if
provided .Flange alignments are OK.

12

SCL of valves complete. Manufacturers test certificates
are available and properly documented

13

Check the tightness of the flange joints and no fitting element
is missing.

14

Check manholes/access doors are properly closed

15

Access ladder is provided for CT and is safe.

16

Ensure that the sump is provided with a drain valve and the
drain is connected to a nearby trench.

17

Check the alignment with prime mover is proper and record
the alignment readings for future maintenance.

18

Check that all moving parts are adequately guarded.

19

Check whether temperature measuring instruments are
provided for bearings.

20

Check the Fan blade angle and note for future reference.

21

Check the motor as per instruction manual of the
manufacturer.

22

Check the earthing facilities of the motor.

Signature
LAPPL

LITL

PAHARPUR

LANCO AMARKANTAK POWER PVT. LTD. (UNIT#1 300MW)
Date of inspection:

LAPPL Ref No.-

System – Cooling Tower
Sl No.

Activity- Pre commissioning checks
Status

Activity

Yes/No

23

Check the location of the EPB for easy accessibility.

24

CT Fan motor supply is extended from switch board.

25

Confirm that motor is checked as per SCL and No-Load trial

Remarks

taken.
26

Confirm the motor IR healthiness.

27

Confirm the lubrication of the motor.

28

If the Fan is running normal, keep the fans running for 8 hrs.

29

Ensure that there is no leakage of water or lube oil from any
point.

30

Check the vibration at various bearings of fan and motor and
record them.

31

Check the R.P.M.

32

Check that all drains (sump, gear box oil etc.) are piped to a
suitable destination.

Signature
LAPPL

LITL

PAHARPUR

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close