Cost Criteria

Published on July 2016 | Categories: Documents | Downloads: 36 | Comments: 0 | Views: 194
of 39
Download PDF   Embed   Report

Cost Criteria

Comments

Content

Technical Memorandum #7

DRAFT

2010 SASD SEWER SYSTEM CAPACITY PLAN UPDATE

Technical Memorandum #7

Technical Memorandum Cost Criteria for 2010
System Capacity Plan
PREPARED BY: My Huynh

DATE: September 13, 2011

REVIEWED BY: Sonny Lunde

INTRODUCTION
This Technical Memorandum presents the methodology used to develop estimated costs for project shed areas
proposed in the Sacramento Area Sewer District System Capacity Plan 2010. The estimated costs may then be
incorporated into SASD’s rate and fee study.

1. DEVELOPMENT OF ESTIMATED COST
Estimates of the capital costs associated with the proposed project areas are order of magnitude estimates. An
order of magnitude estimate is one that is made without detailed engineering data, and uses techniques such as
cost curves and scaling factors from similar projects. The overall expected level of accuracy of the cost estimates
is approximately 30%. All costs presented in this memorandum have been adjusted to an Engineering News
Record construction cost index of 9527, which represents the average of the January 2011 ENR cost indexes for
the San Francisco area (10116) and the “20-Cities” ENR average (8938).
The estimated costs were developed using a baseline pipe construction cost with added cost and markups for
related items. An example cost estimate sheet for a hypothetical project is presented in Figure 1.
Figure 1 – Cost Estimate Sheet Example
+
+
+
+
+
=
+
=
+
=
+
+
=

2010 SCP Tech Memo - 7 Cost

Baseline Pipe Construction Costs
Additional Costs for Geotechnical Factors
Additional Costs Traffic Control
Additional Costs for Productivity Factors
Surface Restoration Costs
Costs for Special Structures and Pump Stations
Subtotal
5% Mobilization/Demobilization
Estimated Construction Cost Subtotal
30% Contingencies for Unknown Conditions
ESTIMATED CONSTRUCTION COST
Right-of-Way/Easement Acquisition
25% Engineering, Administration, and Legal Cost
TOTAL PROJECT COST

- Final.Docx

Page 1 of 18
January 12, 2012

Technical Memorandum #7

DRAFT

2. SUMMARY OF ESTIMATED UNIT COST

For easy reference, a summary of estimated unit cost is included in Table 1.
Table 1 – Summary of Estimated Unit Cost
Item

Description

Unit Cost
Range

Section
Reference

Baseline Construction
Open Cut Gravity Sewer

8 to 42-inch diameter, 8 to 28 feet deep

$160 to
$680/lf

3.1.1

Open Cut DIP Force Main

4 to 18-inch diameter, 4 to 16 feet deep

$140 to
$430/lf

3.1.2

Trenchless Pipe Construction

Bore and Jack, Microtunnel, Pipe Ramming.
With and without casing

$305 to
$1,700/lf

3.1.3

Geotechnical Factors
Additional Dewater

Deep well system

$45 to $60/lf

3.2.1

Additional Sheeting and
Shoring

Trench boxes, solid shoring, and sheet piles

$30 to $710/lf

3.2.2

Developed Areas

100% of
baseline cost

Undeveloped Areas

20% of
baseline cost

Northeastern part of service area

100% of
baseline cost

3.2.3

For pipe alignments along major roads with
four or more lanes of traffic.

$45/lf

3.3

Congested Traffic/Utility
Corridor

For pipe alignments along major roads with
four or more lanes of traffic.

15% of
baseline cost

3.4.1

Remove and Replace Delay
Factor

For pipe alignments to be upsized in place.

25% of
baseline cost

3.4.2

Cobble Areas

Hard Rock Areas

3.2.3

Traffic Control
Additional Traffic Control
Productivity Factors

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 2 of 18
January 12, 2012

DRAFT
Table 1 – Summary of Estimated Unit Cost - Continued
Item

Technical Memorandum #7

Description

Unit Cost
Range

Section
Reference

Surface Restoration
Pavement Restoration

Final Paving and patch paving
15 feet width

$100/lf

3.5.1

Landscape Restoration

Replanting in medians and landscaped area
40 feet width

$3.00/sf

3.5.2

Revegetation

Hydroseeding in open areas
80 feet width

$0.25/sf

3.5.2

Creek Restoration

Replanting and minor bank erosion control
40 feet width

$12/sf

3.5.2

Junction Structures

Junction, transition, and turning structure

$25,000 to
$850,000 per
structure

3.6.1

Pump Stations

10 MGD or less firm capacity
Based on low, medium, and high total
dynamic heads.

$0.5 to $6.1M

3.6.2

Sewer Structures

Mobilization/Demobilization

% of subtotal

5%

3.7

Contingencies

% of Estimated Construction Cost Subtotal

30%

3.8

Easement Acquisition
Acquisition Cost

Title reports, appraisals, real estate staff
time

$7,000 per
parcel

3.9

Easements in Newly
Constructed Development

Granted to SASD as condition of
development

No Cost to
SASD

3.9

Temporary Construction
Easements

80 feet width

$0.80/sf

3.9

Permanent Easement

20 feet width

$4.00/sf

3.9

25%

3.10

Engineering, Administration, and
Legal Costs

2010 SCP Tech Memo - 7 Cost

- Final.Docx

% of Estimated Construction Cost

Page 3 of 18
January 12, 2012

DRAFT

3. BASIS OF ESTIMATED COST

Technical Memorandum #7

Construction costs include costs for installation of gravity pipelines, force mains, and pump stations. The basis
for these costs is described below.

3.1 Baseline Pipeline Construction
Baseline pipeline construction costs were developed for open cut gravity sewer trunks, force mains, and
trenchless pipe construction. These costs are based on a combination of construction bids for projects in
Sacramento and other urban areas in California, catalog unit price costing, and adjustments to unit costs
identified in previous SASD Master Plans (2000 and 2006).
Both the baseline gravity pipe and force main construction costs include the following:
 Vertical trench walls to reduce utility conflicts
 Trench box or hydraulic shores
 Select, imported backfill in the pipe zone and native back fill above the pipe zone to the pavement
structural base. It is assumed that the spoil may be hauled to a local disposal site. Backfill would be
compacted to 90 percent to within 2 feet of the ground surface.
 Temporary pavement to be placed over excavated areas in traveled roads at the end of each day.
 Sump pump in the trench used for minor dewatering.
 Minor traffic control including two way flagging, construction area traffic signs, and channelizers.

3.1.1 Open Cut Gravity Sewers
Baseline unit pipe construction costs were developed for gravity collector and trunk sewers ranging from 8 to 42
inches in diameter for four depth-to-invert ranges: 8 to 16 feet, 16 to 20 feet, 20 to 24 feet, and 24 to 28 feet.
These unit costs are presented in Table 2. It was assumed that gravity trunk sewers installed by open-cut
construction would not be constructed deeper than 28 feet deep.
In addition to the baseline gravity pipe and force main cost assumptions, the baseline gravity vcp pipe
construction costs include the following assumptions:
 Pipe material: VCP for 8 to 36-inch sewers; and PVC-lined (or calcareous aggregate) RCP for 39-inch and
larger sewers.
 Manholes will be located every 400 feet in collector pipes (working pipe capacity of less than 1 mgd,
typically pipes 8-inch to 10-inch) and every 500 feet in trunk sewers (working pipe capacity of 1 mgd or
greater, typically pipes 10-inch or greater).
 Trench dams if needed to prevent migration of groundwater along the trench section and/or filter fabric
to prevent migration of soil or intermediate back fill into the pipe zone.
 Collector sewer not to exceed 19 feet in depth.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 4 of 18
January 12, 2012

Technical Memorandum #7

DRAFT
Table 2 – Open Cut Gravity Pipe Unit Cost
Pipe Size
(in)

Open Cut Gravity Pipe Installation Cost ($/lf)
8 to 16
feet depth

16 to 20
feet depth

20 to 24
feet depth

24 to 28
feet depth

Vitrified Clay Pipe
8

160

185

______

______

10

190

210

______

______

12

220

235

260

285

15

255

275

300

325

18

285

310

340

370

21

330

355

385

415

24

365

390

420

450

27

395

420

455

490

30

430

460

495

530

33

465

495

530

565

36

495

530

570

610

Reinforced Concrete Pipe
39

530

565

605

645

42

565

600

640

680

3.1.2 Open Cut Ductile Iron Force Main
Unit baseline pipe construction costs for force mains are presented in Table 3. In addition to the baseline gravity
pipe and force main cost assumptions, the baseline force main construction costs include the following
assumptions:
 A minimum of 4 feet of cover above the pipe.
 Pipe material: Ductile iron pipe.
 Air release valves, vacuum release valves, or combination valves located every 3,000 feet in 60-inch
diameter manholes.
 Trench dams installed at 100 feet spacing in areas with high groundwater along the trench section and
installation of filter fabric to prevent migration of soil or intermediate back fill in the pipe zone.
 Includes trust blocks.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 5 of 18
January 12, 2012

Technical Memorandum #7

DRAFT
Table 3 – Open Cut DIP Force Main Unit Cost
Force Main Size (in)

Less Than 10 Feet Deep
Cost ($/lf)

10 to 16 Feet Deep
Cost ($/lf)

4

140

200

6

150

205

8

160

210

10

170

225

12

180

240

15

245

325

18

275

355

21

300

380

24

355

430

3.1.3 Trenchless Pipe Construction
Trenchless pipe construction is an advantageous pipe method to install pipelines that minimizes impacts to the
public and the restoration. For this System Capacity Plan, baseline pipe construction costs were also developed
for microctunneling, bore and jack, and pipe ramming. Although pipe bursting is often a viable method for
installing and upsizing pipes, its dependency on local utility location information and pipe condition makes it
difficult to consider on a planning level document. The same goes for horizontal directional drilling, with its high
sensitivity to geological conditions. For this reason, SASD has chosen not to include pipe bursting and horizontal
directional drilling as one of its trenchless methods in the System Capacity Plan, but considerations for use can
be evaluated during the Project Development Phase. The following assumptions were made regarding
trenchless pipe construction:
 All highway and railroad crossing will require a casing.
 All major roads (4 lanes or more) will require a trenchless crossing.
 All creek crossing will be constructed using open cut methods (see creek restoration costs in later
section).
 Neither mircrotunneling nor bore and jack construction methods will be used in cobble areas (see
section on “cobble and hard rock construction” for definition of cobble area) Pipe ramming will be used
for required trenchless crossings in cobble areas. Pipe ramming requires a steel casing.
 Bore and jack equipment for 59-inch diameters and smaller is typically auger boring equipment. Auger
boring is not accurate enough for gravity sewer installation. Auger boring can be used to install casings
for force mains.
 Casing is determined by the outside diameter of the carrier pipe bell plus 24 inches with a minimum size
of 36-inches.
 Bore and jack equipment for 60-inch diameters and larger is typically open shield equipment (laser
target used to steer). Open shield equipment is accurate enough for gravity sewer installation.
 Except for microtunneling, unit pricing includes mobilization/demobilization, bore, casing (if specified),
and pipe. Microtunneling includes all of the previous items except for mobilization/demobilization. For
2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 6 of 18
January 12, 2012

Technical Memorandum #7

DRAFT

Microtunneling mobilization/demobilization, bore holes less than 24-inches will cost $110,000; bore
holes 24 to 48-inches will cost $180,000; and bore holes 48 to 72-inches will cost $260,000.
3.1.3.1 Trenchless Construction Cost
The recommended unit costs for trenchless pipe construction are the following:
Table 4 – Trenchless Pipe Construction Unit Cost
Pipe Size
(in)

Direct Jack
(No Casing)

Casing Required

Cobble Area

Microtunneling*
($/lf)

Casing Size
(in)

Microtunneling*
($/lf)

Bore and Jack
($/lf)

Casing Size
(in)

Pipe Ramming
($/lf)

8

820

36

1025

615

37

305

10

820

36

1035

625

40

345

12

820

36

1040

630

42

380

15

845

36

1060

655

47

460

18

845

42

1025

670

55

505

21

895

43

1030

720

56

510

24

895

49

1060

795

61

545

27

980

51

1125

845

63

615

30

980

56

1155

890

68

660

33

980

59

1240

945

71

720

36

980

64

1335

1040

76

820

39

980

68

1470

1105

80

890

42

980

72

1700

1165

84

960

* Unit pricing for microtunneling does not include mobilization and demobilization.
Use the following for microtunnel mobilization and demobilization cost:
Bore holes less than 24-inches $110,000,
Bore holes 24 to 48-inches $180,000,
Bore holes greater than 48-inches $260,000.

3.1.3.2 Jacking and Receiving Pits
The construction for microtunneling, boring and jacking, and pipe ramming pipeline installation also includes
costs associated with the jacking and receiving pits. If a long length of microtunneling is required, then a series
of drives with the associated pits will be used. The maximum drive lengths of the boring or tunneling machines
are shown in Table 5. These drive length are conservative and will work for most areas of Sacramento County.
The recommended costs for jacking and receiving pits are shown in Table 6.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 7 of 18
January 12, 2012

DRAFT
Table 5 – Maximum Drive Lengths
Pipe Diameter (in)

Technical Memorandum #7
Drive Length (ft)

Microtunneling
8 to 10-inch

1,200

12 to 24-inch

700

27 to 33-inch

400

36-inch and larger

150

Pipe Ramming
All Diameters

300

Table 6 – Jacking and Receiving Pit Cost
Pipe Invert Depth

Pit Cost

16 feet or less
Jacking Pit

$80,000

Receiving Pit

$25,000

Greater than 16 feet
Jacking Pit

$115,000

Receiving Pit

$40,000

3.2 Geotechnical Factors
Depending on location and site conditions, pipeline construction may require additional costs associated with
geotechnical factors. These additional costs include increased dewatering, additional sheeting and shoring, and
special equipment or methods associated with construction in difficult soil conditions such as cobbles or rock.
3.2.1 Additional Dewater
The baseline pipeline costs include the cost of sump pump in the trench for minor dewatering. Some areas of
Sacramento County require a more aggressive dewatering scheme. The cost of installation and maintenance of
each dewatering well could range from $1,000 to $5000. The range of costs depends on depth of wells, the need
for sand screens, and the proximity of electrical services for the pump motors. The cost of dewatering also
depends upon the spacing of the dewatering wells. To adequately dewater a trench with high groundwater,
dewatering wells are generally located at least 50 to 75 feet apart. If the soils have large amounts of clay or
other materials which decrease the capability to dewater the soils, wells are frequently spaced 50 feet apart. For
the purposes of this System Capacity Plan, it is assumed that the wells would be spaced 50 feet apart. Therefore,
the unit dewatering cost could range from $20 to $100 per foot.
Dewatering cost will be applied in areas of the County with known high groundwater as shown Figure 2.
2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 8 of 18
January 12, 2012

DRAFT
Figure 2 – High Groundwater Areas

Technical Memorandum #7

For the purpose of this System Capacity Plan, dewatering cost from Table 7 will be applied in areas of the County
with known high groundwater as shown in Figure 2.

Table 7 – Additional Dewatering Unit Cost
Groundwater Infiltration

Additional Dewatering Cost

200 GPD/Acre

$45/LF of pipe

500 GPD/Acre

$60/LF of pipe

All Other Areas

$0 – Minor dewatering included in
the cost of the pipe installation.

3.2.2 Additional Sheeting and Shoring
Sheeting and shoring methods could range from hydraulic shores to interlocking full-sheets. The specific type of
shoring used will depend upon trench depths, soil conditions, and groundwater levels. For the purposes of
determining sheeting and shoring requirements for this System Capacity Plan, three different ground conditions
will be used: no groundwater, undeveloped areas with high groundwater, and developed areas with high

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 9 of 18
January 12, 2012

Technical Memorandum #7

DRAFT

groundwater. For pipeline constructed in areas without high groundwater, it is assumed that hydraulic shores or
trench boxes will be used. This cost is included in the baseline pipe construction cost.
The recommended sheeting and shoring costs for the three conditions and various pipeline depths are
presented in Table 8. The cost of the solid shoring ranges from $1 to $3 per square foot. The cost of the sheet
piles ranges from $20 to $40 per square foot. These costs have been used to also assume that any excavation
deeper than 8 feet in areas of high groundwater area of the County, where the subsurface profile typically
consists of 10 feet of clay over clean sands. Therefore, additional dewatering costs will also be required for open
cut construction in areas of high groundwater (except where sheet piles are used), as indicated in Table 8.
Table 8 – Shoring and Dewater Unit Cost for Various Groundwater Conditions
Depth to
Invert (ft)

8 to 16

16 to 20

20 to 24

24 to 28

No Groundwater

High Groundwater
Undeveloped Area

Baseline

Partially laid back trench with
trench box and dewatering wells.

Solid shoring and dewatering
wells.

$30/LF + dewatering

$75/LF + dewatering

Partially laid back trench with
trench box and dewatering wells.

Solid shoring and dewatering
wells.

$60/LF + dewatering

$110/LF + dewatering

Partially laid back trench with
trench box and dewatering wells.

Solid shoring and dewatering wells

(no additional cost)
Baseline
(no additional cost)
Baseline
(no additional cost)
Baseline
(no additional cost)

$90/LF + dewatering
Partially laid back trench with
trench box and dewatering wells.

High Groundwater
Developed Area

Shoring: $135/LF
$135/LF + dewatering
Interlocking sheet piles
$710/LF

$120/LF + dewatering

3.2.3 Ground Condition
Large portions of Sacramento County have a significant amount of cobbles in the soil. These cobbles, which
originated from the Sierra Nevada Mountains and were carried and deposited in the Sacramento area by the
American River, are rounded and very hard. For this reason, the cobbles can be problematic when constructing a
pipeline. Therefore a cobble construction factor will be added to the portions of the projects in extra processing
of excavated material necessary to produce acceptable backfill, and shoring difficulties. For projects that will be
constructed before the road and utility improvement are built, the challenges are not as great as the projects
that are built after the road and utility improvements have been constructed. For this System Capacity Plan, the
cobble construction factor will be applied within the areas shown in Figure 3. Cobble issues reduce in magnitude
from the northeast to southwest in this area. For this reason, projects located on Gerber Road will have zero
cobble factor and projects located on Florin Road will have 50% cobble factor instead of the 100% cobble factor.
In the northeast corner of the SASD service area, there is hard rock located in the trench zone. This hard rock
significantly reduces construction productivity and adds considerable cost to pipeline projects. For this System
Capacity Plan, the hard rock construction factor will be applied to all projects located in the areas shown in
Figure 3.
2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 10 of 18
January 12, 2012

DRAFT
Figure 3 – Hard Rock and Cobble Construction Factor Areas

Technical Memorandum #7

For the System Capacity Plan, use the following as construction factors:
 Cobble Construction Factor:
Developed Areas: 100% of Baseline Pipe Construction Costs
Undeveloped Areas: 20% of Baseline Pipe Construction Costs
Note: Areas within the cobble area but south of Elder Creek Road, reduce the cobble construction factor
by 50%.
 Hard Rock Construction Factor:
100% of Baseline Pipe Construction Costs

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 11 of 18
January 12, 2012

DRAFT
3.3 Traffic Control

Technical Memorandum #7

Minor traffic control consisting of two-way flagging, construction area signs, traffic cones, and channelizers are
included in the pipe installation cost. For roads identified as having 4 or more lanes, additional traffic control will
be needed. Additional traffic control includes the cost of traffic design and use of flagging, construction area
traffic signs, temporary crash cushions, barricades, channelizes, flashing beacons, K-rails, and changeable
message boards. Traffic control on major roads could range $3000 to $6000 per day. If it is assumed that
construction will proceed at a rate of 100 feet/day, the equivalent cost would be $30 to $60 per foot. For this
System Capacity Plan, the following unit cost will be used:
 Increased Traffic Control: $45 per linear foot of alignment located in major roads (4 or more lanes).

3.4 Productivity Factors
3.4.1 Traffic/Utility Corridor Delay Factor
Constructing a pipeline in a busy road or a road with numerous utilities is slower (and therefore more costly)
than constructing a pipeline in a quiet residential or rural street. Often times, there are restricted work areas
and hours to maintain safe traffic flow, driveway access coordination, and utility conflicts. Therefore a congested
traffic/utility corridor delay factor reflecting the loss of productivity will be added to alignments on roads with 4
or more lanes.
 Congested Traffic/Utility Corridor Delay Factor: 15% of baseline pipe construction costs in major roads
(4 or more lanes).
3.4.2 Remove and Replace Delay Factor
Constructing a new pipeline in an alignment that requires the removal of the existing gravity sewer is more
costly than constructing a pipeline in a new alignment. The additional cost is caused by the necessary bypass
pumping and the extra processing of the excavated material to remove the broken pipe from the backfill
material. However, contractors are very creative and could typically avoid completely removing the pipe or
remove it at a lower cost than traditional means. For those reasons, the remove and replace delay factor will be
the following:
 Remove and Replace Delay Factor: 25% of baseline pipe construction costs.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 12 of 18
January 12, 2012

DRAFT
3.5 Surface Restoration

Technical Memorandum #7

Surface restoration includes replacement of pavement for pipeline alignments in paved roadways and
replacement of landscaping or other vegetation for pipelines constructed in easements or across open land.
3.5.1 Pavement Restoration
To ensure that the pipe trench does not affect the integrity of the road, restoration will be made to the road
structural section above the pipe trench and overlayed. A tee trench will include a 6-inch thick asphalt concrete
pavement over 6-inches of 3/4 –inch aggregate base compacted to 95 percent. The asphalt concrete section will
extend beyond the trench walls by 12 inches. On both sides of the 6-inch thick pavement, a strip of 2-inch deep
grinding and new pavement overlay the road. The grinding and pavement will extend to lip of gutter, lane line,
or center of traffic lane.
To determine the cost of pavement restoration , two factors must be determined: width and unit cost, While the
width of pavement restoration does vary with pipe diameter, the width is more strongly influenced by factors
such as proximity to edge of pavement, raveling of trench wall, and strength of existing pavement. These factors
are hard to determine during the planning stage; therefore, for the System Capacity Plan, a pavement
restoration width of 15 feet (12 foot traffic lane with a 3 foot shoulder) and a pipe trench accommodating an 18inch pipe (42-inch wide trench), will be used.
For the purposes of this Master Plan, an average cost over the entire 15 foot width will be used, as follows:
 Pavement Restoration Cost (15 feet width): $100 per linear foot

3.5.2 Other Restoration
All trunk sewers and constructed outside of paved roadways and temporary lay down areas, if not constructed
by a developer as part of a subdivision, will require either revegetation or landscape restoration. Open cut creek
crossings will require creek restoration. Revegetation, also referred to hydroseeding, is used to restore pipeline
routes located in open fields. Landscape restoration is used when the alignment is located in the landscaped
medians or other landscaped areas. For new subdivisions, pipelines are usually constructed prior to constructing
the subdivision. For this reason revegetation and landscape restoration cost will be included as part of a new
subdivision cost and not part of the capital funding projection.
Where required, both landscape restoration and revegetation will be applied to the entire area disturbed by the
construction operation. Typically, the disturbed area is larger when the alignment goes through an open field
than when the alignment goes through a creek or an area with landscape improvements. For this reason, for this
System Capacity Plan, the revegetation width will be assume to be 80 feet, and the creek and landscape
restoration widths will be 40 feet. The following costs shall be used:
 Landscape Restoration (replanting in medians or landscaped areas, 40 feet wide): $4.00 per square
foot
 Revegetation (hydroseeding in open areas, 80 feet wide): $0.25 per square foot
 Creek Restorations (replanting, minor bank erosion control, 40 feet wide): $12.00 per square foot

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 13 of 18
January 12, 2012

Technical Memorandum #7

DRAFT
3.6 Sewer Structures

3.6.1 Junction Structures
Junction structures are use to combine flows coming from different pipes into one out flowing pipe. They are
required at the connection points of trunk sewers to interceptors. If the trunk sewer is being connected to an
existing or previously constructed interceptor, then the cost for this junction structure will be included in the
trunk sewer cost estimate. If the junction structure is constructed at the time of the interceptor construction,
then it will be assumed to be included in the interceptor cost estimate and not included in the SASD trunk sewer
construction cost.
Transition structures and turning structures are similar to junction structures in construction methods and cost
but differ in not combining flows. For this System Capacity Plan, transition and turning structures will be costed
like junction structures using Table 9.
Table 9 – Junction Structure Cost
Junction Structure

Cost

Trunk Sewer Junction Structure
Less than 24-inch Diameter Outlet Pipe

$25,000

24 to 36-inch Diameter Outlet Pipe

$50,000

Interceptor/Trunk Junction Structure
60-inch or less diameter Interceptor

$165,000

72 to 78-inch Diameter Interceptor

$230,000

84 to 144-inch Diameter Interceptor

$850,000

3.6.2 Pump Stations
Pump stations are used to convey wastewater using pressurized pipelines. Costs can vary greatly depending on
how much wastewater is being conveyed an on how far the wastewater will be pumped. Typically pump stations
of the same firm capacity used to raise the hydraulic grade line (lift stations) require smaller pumps and
appurtenances than pump stations used to convey wastewater from one location to another and are therefore
less costly. The total dynamic head of pump station is a factor for determining the pump size, motor control
center size, switch board size, wet well size, as well as other appurtenances. For those reasons, the pump
stations cost shown in Table 10 are base on three different scenarios representing low, medium, and high head
pump stations.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 14 of 18
January 12, 2012

Technical Memorandum #7

DRAFT
Table 10 – Pump Station Cost
Pump Station
Firm Capacity

Pump Station Cost Based on Total Dynamic Head
Low Head
Less than 60 feet

Medium Head
60 to 120 feet

High Head
Greater than 120 feet

Less than 1 MGD

$560,000

$680,000

$850,000

1 MGD to 2 MGD

$810,000

$980,000

$1,200,000

2 MGD to 3 MGD

$1,200,000

$1,400,000

$1,800,000

3 MGD to 4 MGD

$1,700,000

$2,000,000

$2,400,000

4 MGD to 5 MGD

$2,100,000

$2,400,000

$2,900,000

5 MGD to 6 MGD

$2,700,000

$3,000,000

$3,700,000

6 MGD to 7 MGD

$3,100,000

$3,500,000

$4,200,000

7 MGD to 8 MGD

$3,800,000

$4,300,000

$5,100,000

8 MGD to 9 MGD

$4,200,000

$4,700,000

$5,600,000

9 MGD to 10 MGD

$4,700,000

$5,100,000

$6,100,000

Often times, pump stations are upgraded to increase the pumping and storing capacity. For increasing the
capacity of an existing station, use the following cost factors:
Table 11 – Rehab Pump Station Cost Factor
Pump Station Capacity Increase

Percentage Cost of New Capacity
Pump Station

Less than 0.5 MGD

25%

0.5 to 2 MGD

50%

2 MGD to 4 MGD

75%

Greater than 4 MGD

100%

3.7 Mobilization and Demobilization
These costs usually generally cover contractor activities when the contractor initially moves construction
facilities and equipment to the project site and at the end of the project when removing facilities and equipment
from the site. These costs also include temporary construction needed to begin the project (access roads,
power, internet, etc.). Typically language in SASD construction contracts limit mobilization and demobilization
bid cost to approximately 5 percent to prevent spending an unreasonably large portion of the construction cost
prior to construction.

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 15 of 18
January 12, 2012

Technical Memorandum #7

DRAFT

 Mobilization/Demobilization: 5% of the Construction Cost Subtotal

3.8 Contingencies
This contingency is used to adjust the Estimated Construction Cost Subtotal such that the total cost will account
for unforeseen economic variables that are difficult to quantify or cover portions of work that were not
estimated. The percentage used for an overall project will vary depending upon level of effort at various stages
of the project. The percentage used is adjusted based upon detailed or lack of detailed geotechnical, utility, and
other project details and information. Due to a lack of detailed information during the planning phase, a
contingency factor of 30 percent is considered appropriate for planning level costs.
 Contingencies for Unknown Conditions: 30% of the Estimated Construction Cost Subtotal.

3.9 Easement Acquisition
The acquisition of easements can vary in cost depending on the incidentals (title reports, appraisals, etc.) and
cooperation of the property owners. On average, the cost of acquiring an easement is $7000 per parcel and do
not include the price of the easement. Because higher cost construction projects do not necessarily yield
proportionally higher costs easements and real estate acquisitions, these costs are separately calculated and
excluded from the typical 25% markup for engineering, administration, and legal costs.
Land acquisition is required for any construction area or pipeline located outside of the public right-of-way.
However, if the alignment of the trunk sewer is within a new development being constructed, it is assumed that
the easement will be granted to SASD as a condition of the development. Therefore no easement acquisition
costs will be incurred by SASD.
Easements can vary in cost. SASD usually acquires permanent easements at 50 percent of the land’s fee value as
determined by an independent appraiser. Temporary easements are acquired at 10 percent of the appraised fee
value for a 12-month usage period. Because of unexpected delays to project schedules, temporary easements
are typically obtained six months beyond the need of the easement or a minimum of two years, whichever is
greater. To ensure that property owners work with SASD, the minimum price for a temporary construction
easement and a permanent easement is $500 and $1,000, respectively. Based on Sacramento County Assessor’s
data for 2010, undeveloped land values can greatly depending on the location of property but, averages around
$8 per square foot. Being a planning level document and real estate typically representing a small percentage of
the project cost, it is appropriate at this level to not distinguish between uses of land and to apply the following
costs:





SASD Acquisition Cost : $7,000 per parcel
Easements in a Newly Constructed Development: No cost to SASD
Temporary Construction Easement (80 feet width) : $0.80 per square foot per year
Permanent Easement (20 feet wide for pipelines, 120 x 120 feet for pump station): $4.00 per square
foot

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 16 of 18
January 12, 2012

DRAFT
3.10 Engineering, Administration, and Legal Costs

Technical Memorandum #7

Typically, a markup is applied to the Estimated Construction Cost to account for the various costs in bringing a
planning level concept through design, construction, and closeout. The engineering, administration, and legal
cost item will account for all reasonably anticipated cost items for both the design and a construction phase,
assumed:
 Engineering, Administration, and Legal Costs: 25% of the Total Estimated Construction Cost
This cost item includes and excludes the following:
Include:













Project Development Plan 1 & 2
SASD Design/Project Management
Flow Monitoring and Capacity Analysis
Consultant Design
Environmental Clearance (Mitigated Negative Declaration)
Permitting
Typical Public Outreach
Construction Inspection
Construction Survey
Construction Costs
Administration Costs
Legal Costs

Does not include:
 Program Cost associated with implementing District’s Capital Improvement and Trunk Expansion
Programs
 Easements nor Real Estate Acquisitions

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 17 of 18
January 12, 2012

Technical Memorandum #7

DRAFT

4. REFERENCES
Tabula Version 3.1.2 King County, Washington, November 10, 2010
CSD-1 Master Plan 2000, Technical Memorandum No. 8B, August 1, 2000

CSD-1 Master Plan 2006, Master Plan TM No. 8B - Cost Research Results, February 23, 2006
SASD Standards and Specifications, June 22, 2011, Version 1.0
County of Sacramento Construction Standard Specification, January 2008
SASD New Construction Bid Summary 2000 to 2010
2010 RSMeans Heavy Construction Cost Data, 24th Annual Edition
Ebidboard.com for public agency construction bids from 2008 to 2010
Engineering News-Record, Construction Cost Index
SASD Sewer Ordinance, April 8, 2011.
Sacramento County Assessor’s Office Commercial and Land Sales for 2010
Interceptor Sequencing Study

2010 SCP Tech Memo - 7 Cost

- Final.Docx

Page 18 of 18
January 12, 2012

COST APPENDIX

ENR CONSTRUCTION COST INDEX
Assumption:
‐ Adjust cost to January 2011 dollars using Engineering News Record Construction Cost Index (ENR CCI)
‐ Out of the 20 cities ENR produces cost indices for, San Francisco is the city closest to Sacramento. 
However, Sacramento costs are typically lower thank San Francisco's cost. Therefore to determine the 
ENR CCI for Sacramento, take the average ENR CCI of San Francisco and the 20 cities average.

January 2011 ENR CCI  = average of San Francisco ENR CCI (10116) and 20 Cities ENR CCI (8938)
= 9827

Year
2010
2009
2008
2007
2006
2005
2004

San Fancisco CCI
9896
9738
9363
9096
8618
8309
8228

20 Cities Average CCI
8802
8570
8310
7966
7751
7446
7115

Average CCI
9350
9150
8840
8530
8180
7880
7670

2011 Cost Mark Up Factor
1.02
1.04
1.08
1.12
1.16
1.21
1.24

GRAVITY PIPELINE COST
Costing Range
Year Description

Project

2010

Lower Silver Creek Flood Protection 
and Creek Restoration Project
6‐inch VCP Interstate 680 to Moss Point Drive 
(Reaches 4,5, & 6A)

2010

8‐inch VCP

2007

8‐inch VCP Parke Bridge Trunk Sewer
Sacramento Housing and 
8‐inch VCP
Redevelopment Agency
Laguna Ridge ‐ Whitelock Parkway 
8‐inch VCP
Segment 1
Laguna Ridge ‐ Whitelock Parkway 
8‐inch VCP
Segment 2
Olive Avenue Sewer Trunk Extension
8‐inch VCP

2006
2006
2006
2006
2006
2005

2010

2010

Franklin Crossing Major Roads Phase 1

8‐inch VCP NVS Phase A1 Infrastructure
8
inch VCP Laguna Ridge (North Shed C)
8‐inch VCP
Gravity Sewer Installation and Sewer 
Lift Station Demolition at Oceanhill 
8‐inch VCP Lane from Oceanhill Lane to Beach 
Boulevard at Adams Avenue
8‐inch VCP

2007 8‐inch VCP 
2007 10‐inch VCP
2006 12‐inch VCP
2006 12‐inch VCP
2006 12‐inch VCP

2010 12‐inch VCP

2010 15‐inch VCP
2008 15‐inch VCP
2006 15‐inch VCP

Castro Valley Sanitary Trunk Sewer 
Project
Elk Grove ‐ Major Roads
Elk Grove ‐ Major Roads
Laguna Ridge ‐ Whitelock Parkway 
Segment 1
Laguna Ridge ‐ Whitelock Parkway 
Segment 2
NVS Phase A1 Infrastructure
Lower Silver Creek Flood Protection 
and Creek Restoration Project
Interstate 680 to Moss Point Drive 
(Reaches 4,5, & 6A)
Franklin Crossing Major Roads Phase 1
Laguna Ridge Bruceville Road Phase II
Olive Avenue Sewer Trunk Extension

2006 15‐inch VCP Bruceville Road Segment A
2005 15‐inch VCP Laguna Ridge (North Shed C)

Weighted 
150% Average

Adjusted 2011 
Cost (ENR CCI 
9527)

Construction Bid

Jurisdiction

Length

Unit

Median

Santa Clara Valley 
Water District

405

LF

$145

$73

$218

$158

$162

$145

$130

$200

City of Elk Grove

636

LF

$69

$34

$103

$65

$66

$58

$70

$67

City of Elk Grove

50%

$112

124

LF

$160

$80

$240

$155

$174

$150

$116

$375

$194

$160

1890

LF

$125

$63

$188

$126

$146

$125

$225

$125

$110

$145

City of Elk Grove

254

LF

$166

$83

$249

$166

$193

$166

City of Elk Grove

1787

LF

$145

$73

$218

$145

$168

$145

County of Sacramento

274

LF

$275

$138

$413

$306

$354

$275

$336

$93

Sacramento
Sacramento

192
1730

LF
LF

$290
$135

$145
$68

$435
$203

$247
$130

$287
$157

$150
$84

$302
$130

$290
$165

$140

City of Huntington 
Beach

335

LF

$210

$105

$315

$206

$210

$175

$210

$120

$310

$215

County of Alameda

254

LF

$200

$100

$300

$187

$191

$130

$140

$260

$131

$208 $200 $240

City of Elk Grove
City of Elk Grove

5726
1021

LF
LF

$50
$62

$25
$31

$75
$93

$50
$65

$56
$73

$48
$55

$46
$52

$50
$54

$57
$62

$48
$54

City of Elk Grove

835

LF

$195

$98

$293

$195

$226

$195

City of Elk Grove

1584

LF

$170

$85

$255

$170

$197

$170

Sacramento

269

LF

$250

$125

$375

$249

$289

$166

$331

$250

Santa Clara Valley 
Water District

290

LF

$180

$90

$270

$193

$197

$150

$180

$250

City of Elk Grove

1143

LF

$91

$46

$137

$87

$89

$75

$92

$90

City of Elk Grove

1254

LF

$96

$48

$144

$95

$103

$145

$94

$96

County of Sacramento

521

LF

$190

$95

$285

$168

$194

$190

$190

$123

City of Elk Grove
Sacramento

649
557

LF
LF

$170
$165

$85
$83

$255
$248

$170
$156

$197
$189

$170
$115

$170

$180

$92

$160

$48 $109 $86
$91 $106 $93

$55
$63

Costing Range
Year Description
2006 15‐inch VCP

Project
Aerojet Interceptor 1B

Jurisdiction

Length

Unit

Median

50%

Weighted 
150% Average

Adjusted 2011 
Cost (ENR CCI 
9527)

Construction Bid

County of Sacramento

106

LF

$358

$179

$536

$346

$402

$255

$330

$415

$385

2005 18‐inch VCP Laguna Ridge (North Shed C)
Sacramento
Castro Valley Sanitary Trunk Sewer 
2010 18‐inch VCP
County of Alameda
Project
2009 18‐inch VCP Lake Murray Trunk Sewer
City of San Diego
Magnolia‐Fillmore‐Golden Sewer From 
2010 18‐inch VCP
City of Riverside
SR‐91 to Cochran Avenue
Magnolia‐Fillmore‐Golden Sewer From 
City of Riverside
2010 18‐inch VCP
SR‐91 to Cochran Avenue
2005 21‐inch VCP Laguna Ridge (North Shed C)
Sacramento
2005 24‐inch VCP Laguna Ridge (North Shed C)
Sacramento
Natomas Phase 1
2005 24‐inch VCP
County of Sacramento

4048

LF

$193

$96

$289

$190

$229

$138

$195

$190

$235

2005 24‐inch VCP

Natomas Phase 2

Castro Valley Sanitary Trunk Sewer 
Project
Castro Valley Sanitary Trunk Sewer 
2010 24‐inch VCP
Project
2009 24‐inch VCP Lake Murray Trunk Sewer
2005 27‐inch VCP Laguna Ridge (North Shed C)
Aerojet Interceptor 1B
2006 27‐inch VCP
2010 24‐inch VCP

2006 27‐inch VCP NVS Phase A1 Infrastructure
2009 27‐inch VCP Lake Murray Trunk Sewer
2005 30‐inch VCP Laguna Ridge (North Shed C)
Sacramento Housing and 
2006 30‐inch VCP
Redevelopment Agency
Sacramento Housing and 
2006 30‐inch VCP
Redevelopment Agency
Sacramento Housing and 
2006 30‐inch VCP
Redevelopment Agency
2006 30‐inch VCP NVS Phase A1 Infrastructure
Aerojet Interceptor 1B
2006 36‐inch VCP

2691

LF

$200

$100

$300

$212

$216

$200

$180

$200

$252

$188 $250 $214

2549

LF

$147

$74

$221

$132

$138

$92

$120

$160

$150

$92

1340

LF

$175

$88

$263

$164

$167

$121

$140

$150

$183

$120 $185 $175 $195 $205

2075

LF

$185

$93

$278

$184

$188

$134

$162

$185

$173

$175 $199 $225 $195 $208

1191
4631

LF
LF

$225
$279

$113
$139

$338
$418

$225
$263

$273
$318

$181
$209

$250
$286

$200
$277

$270
$280

2904

LF

$391

$196

$587

$393

$476

$391

$348

$440

County of Sacramento

1058

LF

$600

$300

$900

$526

$636

$451 $1,100

$600

County of Alameda

1161

LF

$300

$150

$450

$299

$305

$320

$260

$240

$389

$253 $300 $330

County of Alameda

2265

LF

$251

$126

$377

$267

$272

$250

$260

$250

$263

$251 $350 $245

City of San Diego
Sacramento

1163
1130

LF
LF

$200
$343

$100
$171

$300
$514

$197
$320

$204
$387

$167
$224

$200
$335

$190
$350

$225
$370

$150 $155 $163 $200 $275 $241 $417

County of Sacramento

201

LF

$438

$219

$656

$428

$496

$425

$375

$450

$460

Sacramento
City of San Diego
Sacramento

1929
3668
222

LF
LF
LF

$290
$247
$410

$145
$124
$205

$435
$371
$615

$292
$234
$390

$338
$244
$472

$303
$152
$229

$282
$250
$450

$290
$205
$370

$240
$510

$247 $210 $184 $270 $270 $317 $405

2940

LF

$705

$353 $1,058

$693

$804

$720

$640

$535

$705

$867

910

LF

$500

$250

$750

$465

$540

$830

$500

$456

$440

$867

705

LF

$565

$283

$848

$493

$571

$930

$565

$473

$440

$867

Sacramento

6123

LF

$325

$163

$488

$353

$410

$425

$325

$310

County of Sacramento

2677

LF

$453

$226

$679

$483

$560

$415

$400

$490

$625

$95 $134 $225 $170 $147 $163

Pipe Cost vs Pipe Diameter
$1,000
Pipe Cost

$800
$600
$400

Series1

$200

Linear (Series1)

$0
0

5

10

15

20

25

30

35

40

y = 14.45x + 25.07
R² = 0.538

Pipe Diameter (in)

MANHOLE COST PER LINEAR FOOT
Manholes
48‐inch Manhole < 16 feet deep Pipe 8‐21
48‐inch Manhole > 16 feet deep Pipe 12‐21
60‐inch Manhole < 16 feet deep Pipe 24<
60‐inch Manhole > 16 feet deep Pipe 24<
72‐inch Manhole > 16 feet deep

Average Cost
7500
13500
8000
16000
19000

Spacing 400 Spacing 500
19
15
N/A
27
N/A
16
N/A
32
N/A
38

Check Okay

VCP GRAVITY PIPELINE COST
Pipe Size
Cost
6
111.77
8
140.67
10
169.57
12
198.47
15
241.82
18
285.17
21
328.52
24
371.87
27
415.22
30
458.57
33
501.92
36
545.27

Depth
8 to 16
8 to 16
8 to 16
8 to 16
8 to 16
16 to 20
16 to 20
16 to 20
16 to 20
20 to 24
20 to 24
20 to 24

USE THIS FOR GRAVITY PIPELINE COST
Pipe Size
8' to 16'
16' to 20'
VCP ‐ 6
135
160
VCP ‐ 8
160
185
VCP ‐ 10
190
210
VCP ‐ 12
220
235
VCP ‐ 15
255
275
VCP ‐ 18
285
310
VCP ‐ 21
330
355
VCP ‐ 24
365
390
VCP ‐ 27
395
420
VCP ‐ 30
430
460
VCP ‐ 33
465
495
VCP ‐ 36
495
530
RCP ‐ 39
530
565
RCP‐ 42
565
600

8' to 16'
$131
$160
$189
$213
$257

16' to 20'

20' to 24'

24' to 28'

$312
$356
$404
$447
$491
$534
$577

20' to 24'
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
260
300
340
385
420
455
495
530
570
605
640

24' to 28'
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
285
325
370
415
450
490
530
565
610
645
680

CHECK ‐ MASTER PLAN 2006 ADJUSTED VALUES (ENR CCI 8064)
8' to 16'
16' to 20'
Pipe Size
Adjusted 
Adjusted Value
Variance
Variance
Value
6
‐‐‐‐‐‐
N/A
‐‐‐‐‐‐
N/A
8
$177
‐$17
‐‐‐‐‐‐
N/A
10
$201
‐$11
‐‐‐‐‐‐
N/A
12
$224
‐$4
$236
‐$1
15
$260
‐$5
$284
‐$9
‐$10
$319
‐$9
18
$295
21
$331
‐$1
$354
$1
24
$366
‐$1
$390
$0
27
$402
‐$7
$425
‐$5
30
$437
‐$7
$461
‐$1
33
$473
‐$8
$508
‐$13
36
$508
‐$13
$543
‐$13
39
$532
‐$2
$579
‐$14
42
$567
‐$2
$614
‐$14

20' to 24'
Adjusted 
Variance
Value
‐‐‐‐‐‐
N/A
‐‐‐‐‐‐
N/A
‐‐‐‐‐‐
N/A
$0
$260
$5
$295
‐$3
$343
$7
$378
$7
$413
‐$6
$461
‐$1
$496
‐$13
$543
‐$9
$579
‐$9
$614
‐$22
$662

24' to 28'
Adjusted 
Variance
Value
‐‐‐‐‐‐
N/A
‐‐‐‐‐‐
N/A
‐‐‐‐‐‐
N/A
$284
$1
$319
$6
$366
$4
$402
$13
$449
$1
$496
‐$6
$532
‐$2
$579
‐$14
$626
‐$16
$662
‐$17
$709
‐$29

FORCE MAIN COST
Assumption:
‐ Force mains to be in depth range of 4 to 16 feet. Force mains located deeper than 16 feet, use unit cost for gravity pipe.
‐ Force main to be ductile iron pipe.
‐ Air release valves and manhole vault to be installed every 3000 feet (included in unit price for force main).

Description

Pavement 
Removal/Temporary 
Replacement 
CY
$/CY

Trench 
Excavation

Dewatering

ARV Installation 
and Manhole

Pipe and 
Installation

Pipe Bedding

Intermediate 
Backfill & 
Compaction
CY
$/CY

Backfill & 
Compaction

Hauling of 
Cost Per 
Excess Native  Total Cost Linear  Use
Material
Foot
LS
$/LS
$/LF
$
$/LF

CY

$/CY

CY

$/CY

LF 

$/LF

LF 

$/LF

CY

$/CY

CY

$/CY

4" DIP less than 10 feet deep

500

$4.00

1222

$28.70

444

$15.00

1000

$4.00

1000

$36.41

110

$45.00

170

$28.70

942

$45.00

367

$12.00

$140,783

$141

4" DIP 10 to 16 feet deep

500

$4.00

1889

$28.70

1111

$15.00

1000

$4.00

1000

$36.41

110

$45.00

170

$28.70

1609

$45.00

567

$8.00

$200,050

$200

$200

6" DIP less than 10 feet deep

500

$4.00

1222

$28.70

444

$15.00

1000

$4.00

1000

$42.24

110

$45.00

170

$28.70

942

$45.00

367

$12.00

$146,613

$147

$150

6" DIP 10 to 16 feet deep

500

$4.00

1889

$28.70

1111

$15.00

1000

$4.00

1000

$42.24

110

$45.00

170

$28.70

1609

$45.00

567

$8.00

$205,880

$206

$205

8" DIP less than 10 feet deep

500

$4.00

1222

$28.70

444

$15.00

1000

$4.00

1000

$46.20

110

$45.00

170

$28.70

942

$45.00

367

$12.00

$150,573

$151

$160

8" DIP 10 to 16 feet deep

500

$4.00

1889

$28.70

1111

$15.00

1000

$4.00

1000

$46.20

110

$45.00

170

$28.70

1609

$45.00

567

$8.00

$209,840

$210

$210

10" DIP less than 10 feet deep

500

$4.00

1222

$28.70

444

$15.00

1000

$4.00

1000

$62.70

110

$45.00

170

$28.70

942

$45.00

367

$12.00

$167,073

$167

$170

10" DIP 10 to 16 feet deep

500

$4.00

1889

$28.70

1111

$15.00

1000

$4.00

1000

$62.70

110

$45.00

170

$28.70

1609

$45.00

567

$8.00

$226,340

$226

$225

12" DIP less than 10 feet deep

500

$4.00

1222

$28.70

444

$15.00

1000

$4.00

1000

$78.10

110

$45.00

170

$28.70

942

$45.00

367

$12.00

$182,473

$182

$180

12" DIP 10 to 16 feet deep

667

$4.00

1889

$28.70

1111

$15.00

1000

$4.00

1000

$78.10

110

$45.00

170

$28.70

1609

$45.00

567

$8.00

$242,407

$242

$240

15" DIP less than 10 feet deep

667

$4.00

1630

$28.70

593

$15.00

1000

$4.00

1000

$107.80

150

$45.00

220

$28.70

1260

$45.00

489

$12.00

$245,740

$246

$245

15" DIP 10 to 16 feet deep

667

$4.00

2519

$28.70

1481

$15.00

1000

$4.00

1000

$107.80

150

$45.00

220

$28.70

2149

$45.00

756

$8.00

$324,762

$325

$325

18" DIP less than 10 feet deep

667

$4.00

1630

$28.70

593

$15.00

1000

$4.00

1000

$138.38

150

$45.00

220

$28.70

1260

$45.00

489

$12.00

$276,315

$276

$275

18" DIP 10 to 16 feet deep

667

$4.00

2519

$28.70

1481

$15.00

1000

$4.00

1000

$138.38

150

$45.00

220

$28.70

2149

$45.00

756

$8.00

$355,337

$355

$355

21" DIP less than 10 feet deep

667

$4.00

1630

$28.70

593

$15.00

1000

$4.00

1000

$163.13

150

$45.00

220

$28.70

1260

$45.00

489

$12.00

$301,065

$301

$300

21" DIP 10 to 16 feet deep

667

$4.00

2519

$28.70

1481

$15.00

1000

$4.00

1000

$163.13

150

$45.00

220

$28.70

2149

$45.00

756

$8.00

$380,087

$380

$380

24" DIP less than 10 feet deep

667

$4.00

1630

$28.70

593

$15.00

1000

$4.00

1000

$214.88

150

$45.00

220

$28.70

1260

$45.00

489

$12.00

$352,815

$353

$355

24" DIP 10 to 16 feet deep

667

$4.00

2519

$28.70

1481

$15.00

1000

$4.00

1000

$214.88

150

$45.00

220

$28.70

2149

$45.00

756

$8.00

$431,837

$432

$430

Use these cost for force mains

Force Main Diameter (in)
4
6
8
10
12
15
18
21
24

Less than 10 Feet 
Deep
Cost ($/lf)
140
150
160
170
180
245
275
300
355

10 to 16 Feet 
Deep
Cost ($/lf)
200
205
210
225
240
325
355
380
430

Force main
60‐inch Manhole < 16 feet deep
Air Release Valve ‐ ARI Nylon D‐20
Cost per LF Based on Spacing of 3,000 feet

Cost
$8,000
$2,500
$4

$140

BORE AND JACK COST
Assumptions:
‐ Bore and jack unit cost include mobilization and demobilization cost and carrier pipe and                   
installation cost.
‐ Bore and jack unit cost does not include jacking and receiving pit cost.

Carrier Pipe 
Diameter 
(in)

Steel Casing 
Pipe Diameter 
(in)

Bore and Jack 
Cost 
($/lf)

8
10
12
15
18
21
24
27
30
33
36
39
42

36
36
36
36
42
43
49
51
56
59
64
68
72

575
575
575
575
625
675
735
765
800
845
925
980
1030

Pipe and 
Total Bore and  Use this for Bore and 
Installation 
Jack Cost 
Jack Unit Cost 
Cost 
($/lf)
($/lf)
($/lf)
$40.50
$616
$615
$51.50
$627
$625
$56.00
$631
$630
$78.00
$653
$655
$42.50
$668
$670
$46.50
$722
$720
$58.00
$793
$795
$79.00
$844
$845
$87.50
$888
$890
$100.25
$945
$945
$113.00
$1,038
$1,040
$124.00
$1,104
$1,105
$135.00
$1,165
$1,165

MICROTUNNELING COST
Assumptions:
‐ Average production rate is 32 to 60 feet per day.
‐ Unit price of microtunnel includes the cost of bore and carrier pipe. Mobilization and demobilization is separate.
‐ Smaller pipelines (15‐inch diameter or smaller) will be using microtunneling for force mains, pipe material will be 
ductile iron.
‐ Larger pipeline (18‐inch diameter or greater) will be using microtunneling for trunk sewers, pipe material will be 
reinforced concrete.
‐ Jacking and receiving pits will be separate items and are not included in the unit cost of pipe ramming.
MOBILIZATION AND DEMOBILIZATION
Typical mobilization cost approximately $44,000 per day. 
Bore Hole Diameter

Mobilization/
Demobilization ($/Day)

Traveling 
Days

Mobilization/Demobilization Cost
(Job)

Less than 24‐inch
24 to 48‐inch
Greater than 48‐inch

$44,000
$44,000
$44,000

2.5
4
6

$110,000
$180,000
$260,000

MICROTUNNEL
Pipe 
Tunnel 
Diameter Diameter
(in)
(in)
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
‐‐‐‐‐‐
8 ‐ DIP
10 ‐ DIP
12 ‐ DIP
15‐ DIP
18 ‐ RCP
21 ‐ RCP
24 ‐ RCP
27 ‐ RCP
30 ‐ RCP
33 ‐ RCP
36 ‐ RCP
39 ‐ RCP
42 ‐ RCP

8
10
12
15
18
21
24
27
30
33
36
39
42
36
36
36
36
42
43
49
51
56
59
64
68
72

Tunnel 
Production Rate
(lf/day)

Tunnel 
Equipment
($/lf)

60
60
60
58
58
55
50
50
50
50
50
50
50
50
50
50
50
50
50
49
48
47
44
41
37
32

$75.00
$75.00
$75.00
$77.59
$77.59
$81.82
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$91.84
$112.50
$114.89
$122.73
$131.71
$145.95
$168.75

Equipment 
Casing 
Technician Installation
($/lf)
($/lf)
$10.33
$10.33
$10.33
$10.69
$10.69
$11.27
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.65
$15.50
$15.83
$16.91
$18.15
$20.11
$23.25

$733.33
$733.33
$733.33
$758.62
$758.62
$800.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$897.96
$916.67
$936.17
$1,000.00
$1,073.17
$1,189.19
$1,375.00

Carrier 
Pipe
($/lf)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$40.50
$51.50
$56.00
$78.00
$42.50
$46.50
$58.00
$79.00
$87.50
$100.25
$113.00
$124.00
$135.00

Use this for 
Microtunnel 
Microtunnel 
Unit Cost
Unit Cost
($/lf)
($/lf)
$819
$820
$819
$820
$819
$820
$847
$845
$847
$845
$893
$895
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$1,023
$1,025
$1,034
$1,035
$1,038
$1,040
$1,060
$1,060
$1,025
$1,025
$1,029
$1,030
$1,060
$1,060
$1,124
$1,125
$1,154
$1,155
$1,240
$1,240
$1,336
$1,335
$1,479
$1,470
$1,702
$1,700

PIPE RAMMING COST
Assumptions:
‐ Pipe ramming is most useful in short drives and shallow applications.
‐ Mobilization and demobilization cost will be included in the unit price of pipe ramming.
‐ Pipe installation cost will also be include in the price of pipe ramming.
‐ Due to the lack of available cost information on pipe ramming, unit price cost for pipe ramming will be 
obtained from ENR CCI adjustments from Master Plan 2000.
‐ Casing to accommodate carrier pipe bell plus 12 inches.
‐ Smaller pipelines (15‐inch diameter or smaller) will be using pipe ramming for force mains, pipe material will 
be ductile iron.
‐ Larger pipelines (18‐inch diameter or greater) will be using pipe ramming for trunk sewers, pipe material 
will be reinforced concrete.
‐ Jacking and receiving pits will be separate items and are not included in the unit cost for pipe ramming

Pipe and 
Pipe Ramming  Adjusted Pipe 
Cost 2000 (ENR  Ramming Cost 
Installation 
Casing Size
Pipe Size 
Cost
(ENR CCI 9527)
CCI 6474)
($/lf)
($/lf)
($/lf)
37‐inch
$180
$265
8‐inch
$40.50
40‐inch
$200
$294
10‐inch
$51.50
42‐inch
$220
$324
12‐inch
$56.00
47‐inch
$260
$383
15‐inch
$78.00
55‐inch
$315
$464
18‐inch
$42.50
56‐inch
$315
$464
21‐inch
$46.50
61‐inch
$330
$486
24‐inch
$58.00
63‐inch
$365
$537
27‐inch
$79.00
68‐inch
$390
$574
30‐inch
$87.50
71‐inch
$420
$618
33‐inch
$100.25
76‐inch
$480
$706
36‐inch
$113.00
80‐inch
$520
$765
39‐inch
$124.00
84‐inch
$560
$824
42‐inch
$135.00

Pipe Type
DIP
DIP
DIP
DIP
RCP
RCP
RCP
RCP
RCP
RCP
RCP
RCP
RCP

Total Pipe 
Ramming 
Cost
($/lf)
$305
$346
$380
$461
$506
$510
$544
$616
$661
$718
$819
$889
$959

Use this for 
Pipe 
Ramming 
Cost ($/lf)
$305
$345
$380
$460
$505
$510
$545
$615
$660
$720
$820
$890
$960

ADDITIONAL SHEETING AND SHORING COST
Assumption:
‐ There is limited information on project cost for sheeting and shoring. Projects are typically bid on a lump sum basis and therefore making it 
difficult to determine actual sheeting and shoring cost.
‐ Adjust unit pricing from SASD Master Plan 2000 based on ENR CCI.

Master Plan 2000 (ENR CCI 6474)

Unit Cost Adjustment (ENR CCI 9827)

Use these Unit Cost for System Capacity Plan

High 
High 
High 
High 
High 
High 
Groundwater  Groundwater 
No 
Groundwater  Groundwater 
No 
No 
Groundwater  Groundwater 
Depth (ft)
Groundwater Undeveloped  Developed  Groundwater  Undeveloped  Developed  Groundwater  Undeveloped  Developed 
Area (LF)
Area (LF)
Area (LF)
Area (LF)
Area (LF)
Area (LF)
Baseline
20
50
Baseline
$29
$74
Baseline
$30
$75
8 to 16
Baseline
40
75
Baseline
$59
$110
Baseline
$60
$110
16 to 20
Baseline
60
90
Baseline
$88
$132
Baseline
$90
$135
20 to 24
Baseline
80
480
Baseline
$118
$706
Baseline
$120
$710
24 to 28

Check Sheet Piles at 24 to 28 feet 
Pipe depth at 26 feet, excavation depth at 27 feet
Sheet Piles 25' deep excavation range
drive, extract, and salvage
Sheet Piles =

=$26.50 sf

$715.50 compared to $710/lf
okay

ADDITIONAL TRAFFIC CONTROL COST
Assumptions:
‐ Minor traffic control consisting of two‐way flagging, construction area signs, traffic cones, and 
channelizers are included in the pipe installation cost.
‐ Additional traffic control to be used on major roads. Major roads have 4 or more lanes.
‐ Because traffic control is usually bid as a lump sum item, it is difficult to determine traffic control 
costs from previous project bids. Therefore traffic control cost are obtained from catalogued unit 
items.

Typical cost for 2000 feet of pipeline installation on major road
Description
Traffic Control Design
K‐Type Rail
Portable Changeable Message
Channelizer/Crash barrels

Quantity
1
2000
1
1

Unit Cost
$25,000.00
$24.00
$10,000.00
$5,000.00

Unit
LS
LF
EA
LS
Total

Cost
$25,000.00
$48,000.00
$10,000.00
$5,000.00
$88,000.00

Price per Linear Foot

$44.00

Use this for traffic control

$45/LF

REVEGETATION COST
Cost Range
Bid 
Year

Description

2010

Hydroseeding

2010

Hydroseeding

2010

Hydroseeding

2010

Hydroseeding

2009

Hydroseeding

2009

Hydroseeding

Project

Jurisdiction

Santa Clara 
Lower Silver Creek Flood Protection 
Valley Water 
and Creek Restoration Project
District
Santa Clara 
Lower Silver Creek Flood Protection 
Valley Water 
and Creek Restoration Project
District
Santa Clara 
Lower Silver Creek Flood Protection 
Valley Water 
and Creek Restoration Project
District
Santa Clara 
Lower Silver Creek Flood Protection 
Valley Water 
and Creek Restoration Project
District
County of 
Metro Air Park Gravity Connector
Sacramento
County of 
Metro Air Park Force Main
Sacramento

Quantity Unit

Median

50%

150%

Adjusted to 2011 
Weighted 
Cost (ENR 9527)
Average
($/SF)

Construction Bid

84330

SF

$0.25

$0.13

$0.38

$0.27

$0.27

$0.28

$0.10

$0.25

38500

SF

$0.15

$0.08

$0.23

$0.13

$0.13

$0.15

$0.10

$0.25

7900

SF

$0.13

$0.07

$0.20

$0.12

$0.12

$0.13

$0.10

$0.25

26200

SF

$0.12

$0.06

$0.18

$0.11

$0.11

$0.10

$0.12

$0.25

2

AC

$2,500.00

$1,250.00

$3,750.00

$2,266.67

$0.05

$2,500.00

$1,800.00

$6,000.00

$2,500.00

12

AC

$1,700.00

$850.00

$2,550.00

$1,764.05

$0.04

$1,700.00

$1,600.00

$2,000.00

$1,250.00

Average
Use 

$0.12
$0.25

per SF

$1,900.00

$1,250.00 $1,635.00 $1,600.00 $2,900.00 $2,100.00 $1,700.00 $2,525.87 $1,907.75

PUMP STATION COST (1 MGD to 10 MGD)
Assumption:
‐ Minimum forcemain velocity is 3 feet per second. Maximum forcemain velocity is 8 feet per second.
‐ Maximum discharge pressure is 80 psi.
Pump 
Station

Flow 
(MGD)

 Flow 
(GPM)

Velocity
(fps)

1 MGD
1 MGD
1 MGD
1 MGD
2 MGD
2 MGD
2 MGD
2 MGD
3 MGD
3 MGD
3 MGD
3 MGD
4 MGD
4 MGD
4 MGD
4 MGD
5 MGD
5 MGD
5 MGD
5 MGD
5 MGD
5 MGD
6 MGD
6 MGD
6 MGD
6 MGD
6 MGD
6 MGD
6 MGD
6 MGD

1.00
1.00
1.00
1.00
2.00
2.00
2.00
2.00
3.00
3.00
3.00
3.00
4.00
4.00
4.00
4.00
5.00
5.00
5.00
5.00
5.00
5.00
6.00
6.00
6.00
6.00
6.00
6.00
6.00
6.00

694
694
694
694
1,389
1,389
1,389
1,389
2,083
2,083
2,083
2,083
2,778
2,778
2,778
2,778
3,472
3,472
3,472
3,472
3,472
3,472
4,167
4,167
4,167
4,167
4,167
4,167
4,167
4,167

7.9
7.9
4.4
4.4
5.7
5.7
3.9
3.9
5.9
5.9
3.8
3.8
5.0
5.0
3.5
3.5
6.3
6.3
4.4
4.4
3.2
3.2
7.6
7.6
5.3
5.3
3.9
3.9
3.0
3.0

Nominal 
Pipe Size
(in)
6
6
8
8
10
10
12
12
12
12
15
15
15
15
18
18
15
15
18
18
21
21
15
15
18
18
21
21
24
24

Pipe Inside 
Diameter
(in)
6.0
6.0
8.0
8.0
10.0
10.0
12.0
12.0
12.0
12.0
15.0
15.0
15.0
15.0
18.0
18.0
15.0
15.0
18.0
18.0
21.0
21.0
15.0
15.0
18.0
18.0
21.0
21.0
24.0
24.0

Pipe Length
(ft)
500
3,600
500
14,300
500
12,000
500
20,000
500
13,800
500
20,000
500
20,000
500
20,000
500
15,700
500
20,000
500
20,000
500
11,300
500
20,000
500
20,000
500
20,000

Friction Head
(ft)
C=130
19
136
5
134
6
137
2
94
5
137
2
67
3
114
1
47
4
135
2
71
1
34
6
137
2
100
1
47
1
25

Static Head
(ft)

Minor Head
(ft)

TDH
(psi)

47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

65
183
51
180
52
183
49
140
51
183
48
114
49
161
48
94
51
182
48
118
47
80
53
183
49
146
48
94
47
71

Discharge 
Pressure
(psi)
29
80
22
79
23
80
21
62
23
80
21
50
22
70
21
41
22
80
21
52
21
35
23
80
21
64
21
41
21
31

Pump 
Horse Power
(hp)
23
64
18
63
37
128
34
98
54
193
51
119
69
225
67
131
89
319
85
206
83
140
111
385
103
307
100
197
99
150

Pump 
Station

Flow 
(MGD)

 Flow 
(GPM)

Velocity
(fps)

7 MGD
7 MGD
7 MGD
7 MGD
7 MGD
7 MGD
8 MGD
8 MGD
8 MGD
8 MGD
8 MGD
8 MGD
8 MGD
8 MGD
9 MGD
9 MGD
9 MGD
9 MGD
9 MGD
9 MGD
9 MGD
9 MGD
10 MGD
10 MGD
10 MGD
10 MGD
10 MGD
10 MGD
10 MGD
10 MGD

7.00
7.00
7.00
7.00
7.00
7.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00

4,861
4,861
4,861
4,861
4,861
4,861
5,556
5,556
5,556
5,556
5,556
5,556
5,556
5,556
6,250
6,250
6,250
6,250
6,250
6,250
6,250
6,250
6,944
6,944
6,944
6,944
6,944
6,944
6,944
6,944

6.1
6.1
4.5
4.5
3.4
3.4
7.0
7.0
5.1
5.1
3.9
3.9
3.1
3.1
7.9
7.9
5.8
5.8
4.4
4.4
3.5
3.5
6.4
6.4
4.9
4.9
3.9
3.9
3.2
3.2

Nominal 
Pipe Size
(in)
18
18
21
21
24
24
18
18
21
21
24
24
27
27
18
18
21
21
24
24
27
27
21
21
24
24
27
27
30
30

Pipe Inside 
Diameter
(in)
18.0
18.0
21.0
21.0
24.0
24.0
18.0
18.0
21.0
21.0
24.0
24.0
27.0
27.0
18.0
18.0
21.0
21.0
24.0
24.0
27.0
27.0
21.0
21.0
24.0
24.0
27.0
27.0
30.0
30.0

Pipe Length
(ft)
500
20,000
500
20,000
500
20,000
500
16,000
500
20,000
500
20,000
500
20,000
500
13,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000

‐ Based on the table above, TDH ranges for low, medium, and high pump stations are
Low head pump station 
= less than 60 TDH
Medium head pump station
= 60 to 120 THD
High head pump station 
=120 or greater pump station
‐ Use Tabula 3.1.2 to calculate pump station cost
‐ Use TDH of 50 feet, 100 feet, 180 feet to represent low, medium, and high head

Friction Head
(ft)
C=130
3
132
2
63
1
33
4
136
2
80
1
42
1
24
5
137
2
100
1
52
1
29
3
121
2
63
1
36
1
21

Static Head
(ft)

Minor Head
(ft)

TDH
(psi)

47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

50
179
48
109
47
79
51
182
49
127
48
88
47
70
52
183
49
146
48
98
47
76
50
167
48
110
47
82
47
68

Discharge 
Pressure
(psi)
22
78
21
48
21
35
22
80
21
56
21
39
21
31
23
80
21
64
21
43
21
33
22
73
21
48
21
36
21
30

Pump 
Horse Power
(hp)
122
439
118
268
116
194
142
511
136
355
133
248
132
197
163
579
155
461
151
311
149
239
174
587
169
385
166
288
165
238

Pump Station Cost Using Tabula 3.1.2
50 feet TDH (ENR CCI 8815)
PS Firm 
Capacity
<1 MGD
1 to 2 MGD
2 to 3 MGD
3 to 4 MGD
4 to 5 MGD
5 to 6 MGD
6 to 7 MGD
7 to 8 MGD
8 to 9 MGD
9 to 10 MGD

Wet Well Depth
15 feet
$430,000

20 feet
$430,000
$739,000

25 feet

30 feet

35 feet

$751,000
$1,040,000 $1,170,000
$1,490,000 $1,670,000
$1,790,000 $2,010,000
$2,350,000
$2,680,000

Average PS  Adjusted PS Cost  Use these Low 
Cost Low  (ENR CCI 9527) 
Head Pump 
40 feet
45 feet
Head
Low Head
Station Values
$430,000
$557,678
$560,000*
$745,000
$805,175
$810,000
$1,105,000
$1,194,252
$1,200,000
$1,580,000
$1,707,619
$1,700,000
$1,900,000
$2,053,466
$2,100,000
$2,620,000
$2,485,000
$2,685,717
$2,700,000
$3,000,000
$2,840,000
$3,069,391
$3,100,000
$3,360,000 $3,720,000 $3,540,000
$3,825,931
$3,800,000
$3,720,000 $4,130,000 $3,925,000
$4,242,028
$4,200,000
$4,080,000 $4,530,000 $4,305,000
$4,700,000
$4,652,721

*Add 20% markup to account for variability in small pump stations

100 feet TDH (ENR CCI 8815)
PS Firm 
Capacity
<1 MGD
1 to 2 MGD
2 to 3 MGD
3 to 4 MGD
4 to 5 MGD
5 to 6 MGD
6 to 7 MGD
7 to 8 MGD
8 to 9 MGD
9 to 10 MGD

Wet Well Depth
15 feet
$522,000

20 feet
$522,000
$896,000

25 feet

30 feet

35 feet

$912,000
$1,250,000 $1,380,000
$1,740,000 $1,920,000
$2,080,000 $2,310,000
$2,680,000
$3,040,000

Average PS  Adjusted PS Cost  Use these 
Cost 
(ENR CCI 9527)  Medium Head 
40 feet
45 feet
Medium 
Medium Head Pump Station 
$522,000
$676,995
$680,000*
$904,000
$977,017
$980,000
$1,315,000
$1,421,214
$1,400,000
$1,830,000
$1,977,812
$2,000,000
$2,195,000
$2,372,293
$2,400,000
$2,950,000
$2,815,000
$3,000,000
$3,042,372
$3,360,000
$3,200,000
$3,500,000
$3,458,469
$3,760,000 $4,120,000 $3,940,000
$4,300,000
$4,258,239
$4,150,000 $4,560,000 $4,355,000
$4,706,760
$4,700,000
$4,540,000 $4,990,000 $4,765,000
$5,149,876
$5,100,000

*Add 20% markup to account for variability in small pump stations

180 feet TDH (ENR CCI 8815)
PS Firm 
Capacity
<1 MGD
1 to 2 MGD
2 to 3 MGD
3 to 4 MGD
4 to 5 MGD
5 to 6 MGD
6 to 7 MGD
7 to 8 MGD
8 to 9 MGD
9 to 10 MGD

Wet Well Depth
15 feet
$653,000

20 feet
25 feet
30 feet
35 feet
$653,000
$1,130,000 $1,140,000
$1,570,000 $1,710,000
$2,150,000 $2,330,000
$2,580,000 $2,810,000
$3,260,000
$3,700,000

*Add 20% markup to account for variability in small pump stations

Average PS  Adjusted PS Cost  Use these High 
Cost High  (ENR CCI 9527) 
Head Pump 
40 feet
45 feet
Head
High Head
Station Values
$653,000
$846,892
$850,000*
$1,135,000
$1,226,676
$1,200,000
$1,640,000
$1,772,465
$1,800,000
$2,420,928
$2,240,000
$2,400,000
$2,695,000
$2,912,679
$2,900,000
$3,530,000
$3,395,000
$3,669,219
$3,700,000
$4,020,000
$3,860,000
$4,171,778
$4,200,000
$5,058,010
$5,100,000
$4,500,000 $4,860,000 $4,680,000
$4,970,000 $5,380,000 $5,175,000
$5,592,992
$5,600,000
$5,440,000 $5,890,000 $5,665,000
$6,122,570
$6,100,000

Check Pump Station ‐ 1 mgd Low Head
DESCRIPTION
Mobilization
Clearing and Grubbing
Grading, Excavation, Site Preparation
Dewatering
Aggregate Base for PS Pad (120' x 120')
Asphalt for PS Pad (120' x 120')
Chain link fence
20' Chain link Swing Gate
5' Chain link Man Entry Gate
Wash Pad
Electrical Panel Canopy
Bypassing
Sewer Gravity Pipe (8‐inch diameter)
Discharge Manhole (MH + PVC Lining)
Wet Well
Valve Vault and Bypass Vault
Electrical, Lighting, and Instrumentation
Site Piping
Pump 20 Hp
Start Up and Testing
Generator
Odor Control

QUANTITY
1
1
1600
1
1600
522
435
2
1
1
1
1
100
1
1
1
1
1
2
1

UNIT COST
20000
4000
1.01
10000
26.28
71.5
47.5
3600
800
5000
4000
85000
160
8500
75000
25000
100000
50000
15000
10000

UNIT
LS
LS
SY
LS
SY
Ton
LF
EA
EA
EA
EA
LS
LF
EA

LS

Total

COST
$20,000
$4,000
$1,616
$10,000
$42,048
$37,323
$20,663
$7,200
$800
$5,000
$4,000
$85,000
$16,000
$8,500
$75,000
$25,000
$100,000
$50,000
$30,000
$10,000
$0
$0
$552,150 compared to $560,000
okay

Check Pump Station Cost Against Previously Built Projects
Acceptable Bid Range
Bid Year
2004
2004
2007
2007
2008

2008
2008
2008
2011

Bid Year
2004
2004
2007
2007
2008
2008
2008
2008
2011

Pump Station

Capacity

S132 ‐ Chrysanthy Pump Station
S129 ‐ Fruitridge Center Pump Station
S144 ‐ Wilson Road Pump Station
S145 ‐ Lambert Road Pump Station
S142 ‐ Elk Grove Promenade

3.6 mgd
8.7 mgd
.7 mgd
.7 mgd
2 mgd

S143 ‐ Florin Mall Lift Station

0.5 mgd

S146 ‐ Walnut Grove Pump Station
S147 ‐ Cameron Road Pump Station
Creek Protection Project ‐ Arcade Creek

Pump Station
S132 ‐ Chrysanthy Pump Station
S129 ‐ Fruitridge Center Pump Station
S144 ‐ Wilson Road Pump Station
S145 ‐ Lambert Road Pump Station
S142 ‐ Elk Grove Promenade
S143 ‐ Florin Mall Lift Station
S146 ‐ Walnut Grove Pump Station
S147 ‐ Cameron Road Pump Station
Creek Protection Project ‐ Arcade Creek

1.6 mgd
1.6 mgd
0.5 mgd

Capacity
3.6 mgd
8.7 mgd
.7 mgd
.7 mgd
2 mgd
0.5 mgd
1.6 mgd
1.6 mgd
0.5 mgd

PS Head
Low
High
High

Low
High
High
Low

Weighted 
Average Bid
1,242,361
5,227,223
1,065,596
911,765
736,823
560,557
1,353,081
1,301,271
482,633

Medium Bid
1,225,000.00
5,557,945.50
1,046,460.00
875,580.00
727,000.00

‐ 50%
612,500
2,778,973
523,230
437,790
363,500

+ 50%
1,837,500
8,336,918
1,569,690
1,313,370
1,090,500

511,195.00
1,395,050.00
1,358,775.00
508,700.00

255,598
697,525
679,388
254,350

766,793
2,092,575
2,038,163
763,050

Adjusted Average 
Comparison Pump 
Weighted Average 
Bid 2011(ENR CCI 
Station Cost
Bid
2011 9527)

Pump Station Bids

1,242,361
5,227,223
1,065,596
911,765
736,823

1,540,528
6,481,756
1,193,467
1,021,177
795,769

1,700,000
5,600,000
710,000
710,000
810,000

1,011,637
3,566,500
895,454
840,330
767,270

1,127,349
4,938,641
1,268,410
900,460
716,200

1,205,000
6,177,250
875,540
804,300
727,000

560,557
1,353,081
1,301,271
482,633

605,401
1,461,328
1,405,373
482,633

460,000
1,200,000
1,200,000
460,000

697,264
1,436,300
1,425,675
290,500

511,195
1,328,566
1,234,855
429,800

473,211
1,384,200
1,380,050
512,700

Adjusted 
Adjusted 
Actual Cost 
Actual Cost  Comparison Pump 
Average Bid 
of Pump 
of PS (ENR 
2011(ENR CCI 
Station Cost
Station
CCI 2011)
2011 9527)
1,540,528
1,011,637
1,254,430
1,700,000
6,481,756
3,566,500
4,422,460
5,600,000
1,193,467
875,540
980,605
850,000
1,021,177
804,300
900,816
850,000
795,769
767,270
828,652
970,000
605,401
697,264
753,045
550,000
1,461,328
1,297,320
1,401,106
1,200,000
1,405,373
1,258,575
1,359,261
1,200,000
482,633
454,000
454,000
550,000

Variance
‐26.21%
‐21.03%
15.37%
5.98%
‐14.57%
36.92%
16.76%
13.27%
‐17.45%

1,058,500
6,226,500
1,261,250
1,064,900

1,193,700

1,142,200

940,200
850,700

1,152,720
1,009,900

1,466,200
1,376,650
572,000

1,593,960
1,473,100
330,000

950,530
1,024,350
508,700

1,309,000

1,372,725

1,225,000

1,399,000

1,348,818

1,351,194

1,297,320
1,258,575
595,000

1,152,399
1,083,392
454,000

1,247,300
1,102,800
651,000

1,536,199
1,488,133

1,438,100
1,340,900

1,405,900
1,426,775

1,406,573

REAL ESTATE COST
COMMERCIAL LAND SALES
Address
Sale Price
6451 Stockton Bl 
 Augusta Wy 
0000 Reese Rd 

$615,000
$72,500
$46,500

Sale Date

SF

7/23/2010 107,288
10/29/2010
2/17/2010

10,683
12,000

1200 Creekside Dr 

$2,200,000

6/22/2010 151,589

0000 Creekside Dr 

$820,620

0000 Iron Point Rd 
0000 Recycle Rd 

$2,475,000
$250,000

6/24/2010 584,531
6/30/2010 53,302

6915 Elk Grove Bl 

$2,000,000

7/30/2010 176,804

8706 W Stockton Bl 
8706 W Stockton Bl 
8980 Grant Line Rd 
8980 Grant Line Rd 
8980 Grant line Rd 

$1,250,000
$1,250,000
$602,000
$602,000
$602,000

 Laguna Grove Dr 

$1,300,000

3/24/2010 240,887

9770 Auto City Dr 

$1,084,000

5/21/2010 246,550

8/13/2010

6/8/2010
6/8/2010
10/15/2010
10/15/2010
10/15/2010

68,389

629,573
629,573
171,191
171,191
171,191

$/SF

Notes
Subject property is a vacant, level, in‐fill commercial lot.  Plans approved for a 24,700 
$5.73 sqft retail/office center.
Brokered all cash sale to the Catholic Church which owns the adjacent parcel to the 
$6.79 west of the subject.   Subject property has been marketed and listed as apartment 
$3.88
Across the street from Mercy Hospital Folsom, plans to construction medical office 
$14.51 bldg.
Arms length transaction thru broker.   Vacant office land across the street from 
$12.00 Mercy Folsom Hospital.  Purchased for investment.
This was an REO sale.  The buyer does not have immediate plans for the land at this 
$4.23 time.
$4.69 Auto salvage yard.
Unimproved 4‐acre parcel on north side of Elk Grove Blvd about 1/4 mile west of 
Bruceville.  Buyer plans 110,000 sq ft, 2‐story senior assisted living residential care 
$11.31 facility.  Seller paid all expenses relating to new parcel map and entitlements.  Seller 
117‐0220‐025‐0000 to hold for re‐entitlement and sell.  Purchase with tentative map 
per Comps.  MP03 Proposed residential development sold with tentative map to 
$1.99 developer for re‐entitlement and re‐sale to builder.  Buyer also purchased adjacent 
$1.99
$3.52
$3.52
$3.52
Brokered all Cash Sale.  First open market sale after internal (Chrysler) CIOS 
conveyance pursuant to US Bankruptcy Court.  Per Blake Snider (405‐8000), sales 
$5.40 price based upon negotiations.  Listed @ $11 psf.   No freeway visibility.
Brokered cash REO Sale.  Confirmed w/Andrew Pfeifer VP 305‐779‐4075 arms length 
transaction.  Proposed Hyundai dealership ‐ relocating from Florin Rd.  MP03 
$4.40 contiguous vacant parcels.

0000 Sunrise Bl 

$29,900

11/22/2010

22,758

$1.31

 Greenback Ln 

$100,000

2/25/2010

25,657

$3.90

4/27/2010 560,182

$8.93

100 Promenade Cir 

$5,000,000

10635 Fair Oaks Bl 

$350,000

9/3/2010

36,590

$9.57

1544 Hood Rd 

$368,000
2/19/2010 75,460
Average Commericial Cost

$4.88
$5.80

MP2 Brokered cash sale.  One parcel in flood zone.  The parcels located in busy and 
noisy intersection.  Per telephone conversation with the listing agent,  Carlos 
Skozlows at Coldwell Banker. The other parcel needs off‐sites improvements.
No broker involved  in the purchased of the subject property.  The subject vacant 
land has no street frontage and is landlocked behind parcel #223‐0142‐044‐0000.  
Currently, the vacant land is used for storage of containers and cars.   The owners of 
parcel #223‐0142‐044‐0000, purchased the subject vacant land.  Unable to verified 
Assemblage, sale out of foreclosure, Full off‐sites, Purchased by Kaiser Foundation 
for future medical office building.  Buyer states there is no particular timeline for 
construction.   Subject is located in the Promenade at Gateway Sacramento which is 
Direct from seller.  Subject located on a very, busy street.  The topography is mostly 
level with some sloping.  No site improvements.  Vacant land located on the corner 
of Fair Oaks and Central Ave.  This corner has a 4‐way stop and is very busy.  The 
developed for apartments.  Some infrastructure in place, road, some electrical and 
water.  Property was foreclosed on 20091001 and taken by Unite Commercial Bank 
as Receiver for East West Bank. Property was listed thru MLS and Loopnet.  Buyer 
per SF

RESIDENTIAL LAND SALES
Address
Sale Price
2100 6Th St
$100,000
0 57Th St
$75,000
2931 39Th St
$30,000
3833 36Th St
$20,000
4082 73Rd St
$29,000
4440 52Nd St
$45,000
4208 Sierra Vista Av
$5,000
0 Enrico Bl
$50,000
5115 64Th St
$4,000
29 Bunratty Ct
$35,000
978 Briarcrest Wy
$60,000
0 Pocket Rd
$850,000
7713 E Shore Dr
$219,000
6565 Lang Av
$75,000
0 Hing Av
$10,000
0 Citrus Av
$20,000
0 Citrus Av
$19,000
7419 Persimmon Av
$200,000
7471 Della Cr
$75,000
8596 Unsworth Av
$230,000
0 Birch Ranch Dr
$225,000
11867 Country Grdn Dr $1,470,000
4831 Birch Valley Wy
$2,441,000
12295 El Portal Wy
$2,144,000
0 Mormon St
$80,000
659 Hancock Dr
$55,000
801 Cristina Ct
$67,000
805 Cristina Ct
$87,500
1514 Gionata Wy
$52,500
810 Cristina Ct
$80,000
784 Lorena Ln
$75,500
0 Trowbridge Ct
$198,000
107 Kemp Ct
$150,000
498 Listowe Dr
$190,000
729 Heritage Pl
$245,000
$210,000
700 Glen Mady Wy
$148,000
1731 Lake Vista Wy
1763 Barrhead Ct
$185,000
539 Serpa Wy
$172,000
1804 Ruan Ct
$182,500
414 Tobrurry Wy
$150,000
449 Serpa Wy
$250,000
365 Tobrurry Wy
$122,000
369 Tobrurry Wy
$130,000
335 Tobrurry Wy
$130,000
264 Tobrurry Wy
$148,000
323 Tobrurry Wy
$160,000
12785 Thornberg Wy
$262,000
10856 Wraysbury Wy
$246,000
10820 Atherstone Dr
$237,000
6442 Lago Cr
$84,000
6334 Cazador
$25,000
0 Cottonwood Ln
$300,000
7894 Iona Wy
$216,000
0 Gerber Rd
$362,500
0 Gerber Rd
$280,000
8800 Bradshaw Rd
$500,000
$1,840,000
8891 Cobble Crest Dr
10651 Halfway Rd
$66,000
0 Lee School Rd
$143,000
0 Simpson Ranch Ct
$250,000
0 Simpson Ranch Ct
$188,000
$130,000
8900 Good Shepherd Ln
$240,000
8920 Good Shepherd Ln
0 Bradshaw Rd
$280,000
9135 Shire Oaks Ln
$156,500
9136 Shire Oaks Ln
$340,000
0 Meiss Rd
$45,000
0 Washington Av
$50,000
$6,000
3136 Academy Wy
52 Morell Ct
$79,000
$30,000
0 Cottage Wy
6232 Gobernadores Ln
$152,000
1235 Jacob Ln
$150,000

Sale Date
4/20/2010
6/11/2010
6/28/2010
12/6/2010
5/7/2010
3/10/2010
10/13/2010
6/30/2010
12/6/2010
7/19/2010
3/23/2010
11/29/2010
2/10/2010
12/27/2010
4/14/2010
8/27/2010
8/10/2010
8/4/2010
12/29/2010
5/7/2010
12/2/2010
6/3/2010
12/30/2010
5/28/2010
7/30/2010
11/17/2010
12/28/2010
12/14/2010
12/8/2010
9/14/2010
8/31/2010
4/12/2010
9/21/2010
6/22/2010
1/28/2010
2/10/2010
12/10/2010
5/6/2010
3/25/2010
9/3/2010
7/25/2010
12/21/2010
10/21/2010
9/30/2010
4/20/2010
7/28/2010
2/5/2010
12/22/2010
9/15/2010
9/14/2010
6/23/2010
4/6/2010
9/7/2010
2/19/2010
11/12/2010
9/10/2010
6/16/2010
3/31/2010
5/24/2010
8/10/2010
8/2/2010
4/22/2010
6/17/2010
3/2/2010
1/15/2010
12/6/2010
3/1/2010
5/21/2010
10/20/2010
12/6/2010
12/23/2010
10/19/2010
6/30/2010
6/30/2010

$/SF
$31.25
$9.26
$5.30
$3.83
$4.76
$7.20
$0.96
$2.61
$0.46
$5.39
$6.56
$8.20
$18.62
$0.68
$0.54
$2.99
$2.84
$3.18
$10.34
$3.52
$1.08
$173.99
$3.79
$5.15
$15.31
$6.65
$2.93
$3.81
$3.72
$5.35
$6.21
$8.93
$19.13
$7.79
$17.32
$13.39
$9.34
$7.15
$7.64
$9.79
$7.00
$20.83
$4.90
$4.54
$6.70
$8.65
$8.37
$3.90
$183.45
$169.89
$7.14
$7.23
$0.52
$5.61
$0.60
$0.46
$63.77
$8.22
$0.82
$0.70
$0.30
$0.23
$1.91
$0.46
$1.35
$1.88
$3.12
$0.34
$3.83
$0.98
$1.27
$3.34
$4.26
$9.44

Average Residential Cost
Average of Commercial and Residential
Temporary Construction Easements (10%)
Use for TCE
Permanent Easement (50%)
Use for Permanent Easement

$10.02
$7.91
$0.79
$0.80
$3.96
$4.00

Address
5411 Lambert Rd
8244 Wymark Dr
9990 Winkle Cr
11201 Ketcherside Ln
14059 Diabloview Ct
0 Twin Cities Rd
13067 Stockton Bl
0 Kost Rd
9768 Pringle Av
13459 John Rocha Cr
13570 John Rocha Cr
13500 John Rocha Cr
13444 John Rocha Cr
13472 John Rocha Cr
13585 John Rocha Cr
13542 John Rocha Cr
13514 John Rocha Cr
712 Union St
708 Tyler Is Br Rd
0 Sorento Rd
8341 Nathalie Wy
8340 Nathalie Wy
8336 Nathalie Wy
7341 8Th St
0 7Th Av
637 O St
0 Elkhorn Bl
6740 18Th St
0 U St
7720 Nelson Ln
7129 Walnut Av
231 E St
0 Rio Linda Bl
0 2Nd St
340 Pinedale Av
5041 Sully St
4320 Santa Ana Av
855 Rio Robles Av
0 Peerless Av
0 Telegraph Av
148 Lost Creek Dr
126 Flat Rock Dr
164 Temperance Rv Ct
5425 College Oak Dr
5425 College Oak Dr
0 Walnut Av
5234 Bell Wood Wy
1335 Grace Av
4337 Marysville Bl
4024 Astoria St
4332 Poseidon Ln
0 Hope Ln
4040 Braxton Ln
6350 Mariposa Av
8000 Sunset Av
8261 Winding Wy
4350 Chicago Av
51 Morey Av
3637 Presidio St
0 South Av
8672 Old Villa Ct
3410 Montclaire St
8178 Streng Av
0 Bryan Wy
3925 Hollister Av
0 Fair Oaks Bl
0 Sutter Hill Ln
6148 Sutter Av
6146 Sutter Av
0 Fair Oaks Bl
8490 London Plain Ct
8551 Heather Cross Wy
2741 Altos Av
1035 Sonoma Av
1027 Opal Ln
per SF
per SF
per SF per year
per SF

Sale Price
$180,000
$3,700,000
$1,528,000
$110,000
$75,000
$75,000
$675,000
$102,500
$95,225
$95,225
$95,225
$95,225
$95,225
$99,950
$99,950
$99,950
$99,950
$35,000
$52,500
$45,000
$60,000
$58,000
$58,000
$112,000
$18,000
$55,000
$40,000
$70,000
$590,000
$50,000
$125,500
$58,000
$87,000
$25,000
$27,000
$50,000
$50,000
$18,000
$5,000
$170,000
$155,000
$100,000
$52,500
$39,500
$35,000
$57,000
$96,500
$50,000
$20,000
$35,000
$72,500
$160,000
$707,000
$382,000
$200,000
$25,000
$195,000
$500,000
$21,500
$6,000
$89,000
$130,000
$375,000
$207,000
$121,900
$91,500
$25,000
$235,000
$98,000
$100,000
$135,000
$60,000
$15,000
$10,000
$12,500

Sale Date
12/2/2010
12/30/2010
3/31/2010
12/30/2010
1/28/2010
11/2/2010
9/29/2010
7/7/2010
6/4/2010
6/4/2010
6/4/2010
6/4/2010
6/4/2010
5/10/2010
3/15/2010
1/19/2010
1/15/2010
3/3/2010
10/13/2010
10/15/2010
5/3/2010
4/9/2010
3/29/2010
8/19/2010
2/26/2010
12/23/2010
12/6/2010
5/14/2010
8/16/2010
12/20/2010
3/25/2010
11/12/2010
1/12/2010
12/7/2010
5/19/2010
2/16/2010
10/5/2010
7/19/2010
9/16/2010
8/18/2010
4/5/2010
7/26/2010
9/23/2010
1/5/2010
5/13/2010
2/17/2010
2/10/2010
1/14/2010
7/12/2010
6/15/2010
5/28/2010
3/2/2010
10/6/2010
6/11/2010
10/14/2010
2/19/2010
5/14/2010
7/27/2010
12/6/2010
3/10/2010
12/7/2010
9/7/2010
1/14/2010
8/6/2010
6/30/2010
2/11/2010
4/23/2010
8/31/2010
4/30/2010
5/6/2010
5/25/2010
8/25/2010
10/14/2010
12/6/2010
5/21/2010

$/SF
$0.13
$6.41
$179.45
$0.25
$1.90
$0.97
$1.22
$0.97
$1.35
$1.32
$1.11
$1.16
$1.16
$1.17
$1.32
$1.22
$1.22
$10.03
$2.68
$0.19
$6.63
$7.01
$6.88
$2.89
$1.17
$0.54
$0.53
$1.12
$2.28
$1.77
$2.32
$0.67
$0.21
$1.25
$1.24
$1.97
$1.01
$2.02
$0.36
$1.70
$13.46
$4.25
$3.75
$2.32
$2.05
$2.84
$13.03
$0.46
$1.70
$2.00
$4.76
$5.17
$3.16
$50.40
$4.69
$3.38
$4.54
$0.98
$3.53
$1.15
$7.05
$16.15
$18.20
$7.09
$3.33
$4.73
$1.18
$11.88
$10.97
$1.23
$7.08
$9.37
$1.86
$1.78
$1.91

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close