Integration between PP module and PM module Hi, This document explains integration between PP module and Plant Maintenance (PM) module.... Overview: Integration Overview: Integration between PP and PM modules happens during following scenarios... A) During Capacity Planning for work centers B) For tracking the usage value of PRT's

Process flow of integration during Capacity Planning for work centers: When the production work center is overloaded with capacity, if we try to do capacity leveling and want to shift the capacity to other dates, where already some preventive maintenance activity is planned for the same work center ( equipment) during that period, then system will not allow to reschedule the production order to those days. PP Work center is Equipment in i n PM. In the concerned equipment's master data you can mention the PP work centers name. This links the PP work center and PM equipment. Process flow... Create work center :

Generated by Jive on 2015-05-29+02:00 1

Integration between PP module and PM module

in the capacities header tab maintain the data as per the requirement....

Generated by Jive on 2015-05-29+02:00 2

Integration between PP module and PM module

Now save the work center.... Create Routing : Create the routing for material and assign the work center for operation as shown in the below screen shots...

Generated by Jive on 2015-05-29+02:00 3

Integration between PP module and PM module

Now save the Routing.. Create BOM : Create the BOM for the material through CS01 for creation of Production orders...

Generated by Jive on 2015-05-29+02:00 4

Integration between PP module and PM module

this completes the master data from Production planning module side.... Create Equipment : Create equipment in Plant maintenance module through IE01 and assign the work center ( created in PP module ) in the location tab as shown below. and assign the planning plant as same the work center plant...

Generated by Jive on 2015-05-29+02:00 5

Integration between PP module and PM module

Generated by Jive on 2015-05-29+02:00 6

Integration between PP module and PM module

Generated by Jive on 2015-05-29+02:00 7

Integration between PP module and PM module

Save the equipment..... Now create Preventive Maintenance order for the above equipment through IW31...

Generated by Jive on 2015-05-29+02:00 8

Integration between PP module and PM module

Now give the order start date as 26.05.2014 and end date as 30.05.2014 as shown below...

Generated by Jive on 2015-05-29+02:00 9

Integration between PP module and PM module

maintain system condition as not in operation as shown below....

Generated by Jive on 2015-05-29+02:00 10

Integration between PP module and PM module

Finally save the Preventive Maintenance order...

Now create production order for material 2570 through CO01...

Generated by Jive on 2015-05-29+02:00 11

Integration between PP module and PM module

Now give the start date as 22.05.2014 and end date as 27.05.2014 as shown below..and release the order and save the production order...

Generated by Jive on 2015-05-29+02:00 12

Integration between PP module and PM module

Now create one more production order for the same material with same start and end dates as shown below... this is for creating the capacity overload for the period....

Generated by Jive on 2015-05-29+02:00 13

Integration between PP module and PM module

then save the order... Now check the capacity situation of the work center in the CM50 transaction...

Generated by Jive on 2015-05-29+02:00 14

Integration between PP module and PM module

Generated by Jive on 2015-05-29+02:00 15

Integration between PP module and PM module

above you can observe that there is a capacity overload on dates 23.05.2014, 26.05.2014 and 27.05.2014....now as there is a overload we will try reschedule the one of the production order to other dates on the capacity planning table with function capacity leveling...

Generated by Jive on 2015-05-29+02:00 16

Integration between PP module and PM module

in the next selection screen give work center, plant, capacity category and Capacity planner grp

Now execute

Generated by Jive on 2015-05-29+02:00 17

Integration between PP module and PM module

Now take the second production order ( 60004673) and try dispatch it on the dates 28.05.2014 to 30.05.2014 where already preventive maintenance order is present which is shown in black color..

Generated by Jive on 2015-05-29+02:00 18

Integration between PP module and PM module

Now when you try to dispatch the second production order system will not allow you to do on the dates of preventive maintenance dates and it will rescheduled (dispatched) to subsequent dates as shown below...

Generated by Jive on 2015-05-29+02:00 19

Integration between PP module and PM module

Now save the planning table and observe the change in dates in second production order..

Generated by Jive on 2015-05-29+02:00 20

Integration between PP module and PM module

Process flow of integration for tracking the usage value of PRT's : Tracking of usage of a tool in production, every time a tool is used there should be a count of that usage...This requires PP-PM integration. A production resource tool as equipment is created with the measuring points. The PRT will then be assigned to the operation that requires usage. During confirmation of the production order, the system will automatically record the usage as measuring documents. In this way, the count of the tool usage is monitored... Thanks Kumar

Generated by Jive on 2015-05-29+02:00 21

Sponsor Documents

Recommended

No recommend documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close