GSCM 530 DeVry Week 5 Homework Assignment
4. Answer the following questions for the following network. Times shown are in days.
a. What is the length of the critical path?
b. What are the earliest start and latest start for E?
c. What is the latest start for B?
d. If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?
6. Consider the following information about a small project:
a. Draw a network diagram.
b. Identify the critical path, earliest start and finish, and slack for each task.
c. Which of these activities should the project manager track most closely?
Comments
Content
GSCM 530 DeVry Week 5 Homework Assignment
GSCM530
GSCM 530 DeVry Week 5 Homework Assignment
GSCM 530 DeVry Week 5 Homework Assignment
4. Answer the following questions for the following network. Times shown are in days.
a. What is the length of the critical path?
b. What are the earliest start and latest start for E?
c. What is the latest start for B?
d. If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?
6. Consider the following information about a small project:
a. Draw a network diagram.
b. Identify the critical path, earliest start and finish, and slack for each task.
c. Which of these activities should the project manager track most closely?