Question 1. Question : (TCO 4) An example of resource leveling would be
o fast tracking a project to finish early.
o crashing a project to meet a critical deadline.
o ensuring resource usage is balanced.
o removing work from a project to compress its schedule.
Question 2. Question : (TCO 6) You are the project manager of a major IT project in Italy. You review your earned value report and you see that your SPI is .68. What does this mean to you?
o The project is doing fine. No corrective actions are needed.
o The project is slightly ahead of schedule. No corrections are needed.
o The project is slightly behind schedule. Corrections are needed.
o The project is very much behind schedule. Immediate corrections are needed.
Comments
Content
MGMT 404 DeVry Week 7 Quiz Latest
MGMT404
MGMT 404 DeVry Week 7 Quiz Latest
MGMT 404 DeVry Week 7 Quiz Latest
Question 1. Question : (TCO 4) An example of resource leveling would be
o fast tracking a project to finish early.
o crashing a project to meet a critical deadline.
o ensuring resource usage is balanced.
o removing work from a project to compress its schedule.
Question 2. Question : (TCO 6) You are the project manager of a major IT project in Italy. You review your earned value report and you see that your SPI is .68. What does this mean to you?
o The project is doing fine. No corrective actions are needed.
o The project is slightly ahead of schedule. No corrections are needed.
o The project is slightly behind schedule. Corrections are needed.
o The project is very much behind schedule. Immediate corrections are needed.