NOVA COLLEGE OF ENGINEERING AND TECHNOLOGY
VEGAVARAM, JANGAREDDIGUDEM
Marks Obtained:
nd
III B.Tech II-Semester II Internal Examinations, February 2005
MANAGEMENT SCIENCE
Sign of valuer:
(For C.S.E & I.T)
Date:
Name:
Branch:
1) In process chart, the symbol for inspection is______ A) D
Roll No.:
.B) O
C) ∆ D) □
[
]
[
]
3) The ____ chart points out the causes for the variations between samples based on averages. [
A) R
B) X
C) C
D) P
]
4) In __________________ production, the product is made on the basis of customer’s order.
A) Mass B) Batch C) Job order D) shop
[
]
5) In work study, there are two board components. One is Method study, while the other is_____. [
A) Duty study B) Work Measurement C) order study D) shop study
]
2) Quality may be of two types: quality of design and quality of________________
A) Inspection B) control
C) conformance D) desire
6) The chart, which identifies the main events sequence-wise considering only operations and inspections, is
called_____________.
[
]
A) Outline process chart B) Two handed process chart c) flow diagram D) simo chart
7) Among the following, what is not the advantage of urban site over rural site?
[
]
A) Land cost B) Good transport facilities C) availability of skilled labour D) Good civic amenities are available.
8) Give expansion of word ‘SIMO’ in SIMO chart _______________.
[
A) Single military organization B) Single Motion c) Simultaneous motion D) Single image option
]
9)In the time measuring device wink counter,1 wink = ____________________ of a minute
A) 2000 B) 1/2000 C) 200 D) 1/200
]
[
10) Among the following, which is not true about good plant layout.
[
]
A) increases effort of workers B) reduces spoilage C) less material handling D) less work in process.
11) Among the following , which is not true about rural site.
[
]
A) Land is cheap B) Less restrictions on pollution C) less taxes D) Good civic amenities are available.
12) For _________ unit, nearness to raw material is a major factor for plant location
A) Coal mine B) CinemaTheatre C) Advertising D) marketing
[
]
13) What is the most suitable site for starting a Mega Superbazaar _______________
A) Urban B) Rural C) Suburban D) Can’t say
[
]
14) Which among the following industries depends mostly on seaways.
A) Software
B) Export import based
C) Pharmacy
D) Banking
[
15) Productivity can be increased by __________.
A) increasing output B) decreasing input c) both A & B D) Can’t say
[
]
16) A sugar factory is an example of ____________________________ production.
[
]
17) The time measuring device used in SIMO chart is called ____________________
A) Electronic timer B) Wink counter C) Stop clock D) Tachometer
[
]
18) ______________ process chart records the activities of the left & right hands of
an operator as related to each other.
A) Outline process chart B) Two handed process chart c) flow diagram D) simo chart
[
]
19) The modified form of flow diagram, using thread is called _______________diagram.
A) Process B) ) flow C) simo D) String
[
]
20) The formula for standard time is Standard time = (observed time X_____) + allowances .
A) Process time B) flow factor C) Rating factor D) planning factor