4 Confirmed/ Awarded 3 Final Negotiation (STATUS OF ENGAGEMENT OF SUB-CONTRACTORS/SUPPLIERS ) 2 Complete comparison (as at 5th June 2008 ) 1 Obtaining quotation 0 Task Not Started
(Item ) Description Expected Delivery date on site (Provided by PM)
(MOTOR CITY (Both Project) )
Submitted 6 9 4 4 7 5 5 7 7 2 9
Remarks Status
Invited
1.0 HEAD OFFICE ADMINISTRATION 1.1 Insurance 1.2 Performance Bond & Advance Payment Bond 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 SITE ADMINISTRATION Hoarding, gantry gate Site Office, site facilities, etc Project Signboard Temporary road access Tower Crane Mobile Crane Diesel Cleaning works - Waste Disposal Tank - water, diesel, septic Surveyor Temporary lighting Temporary water Temporary telephone Security Genset Testing Scaffolding Safety, First aid
(A0 ) SITE WORKS/ ENABLING WORKS (A1 ) Site Clearance & Earthworks (A2 ) Shoring works (A3 ) Dewatering (A4 ) Gunniting (A5 ) Piling works (A6 ) Blockworks a. Material b. Sub-contractor (A7 ) Waterproofing, pile head treatment (A8 ) Anti-Termite Treatment (A9 ) Sub-Structure RC works a. Labour b. Rebar c. Concrete d. Formwork