Work Breakdown Structure of a 2-storey residential construction

Comments

Content

ID

Task
Mode
0

Task Name

Duration

Residential
Construction

152 days

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Tue
2/17/15

1

General Conditions 21 days

Tue 2/17/15

2

Finalize plans
20 days
and develop
estimate with
owner, architect
Sign contract and 1 day
notice to
proceed
Apply for
0 days
Permits
Secure
0 days
foundation
permit
Secure
0 days
framing
permit
Secure
0 days
electrical
permit
Secure
0 days
plumbing
permit
Secure HVAC 0 days
permit

Tue 2/17/15

General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]

Tue 3/17/15

General contractor,Architect,Owner,Mortgage lender

3

4
5

6

7

8

9

Project: Residential Constructio
Date: Tue 2/17/15

Tue 3/17/15

3/17

Tue 3/17/15

3/17

Tue 3/17/15

3/17

Tue 3/17/15

3/17

Tue 3/17/15

3/17

Tue 3/17/15

3/17

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 1

Oct
W

ID

Task
Mode
10

11
12
13

14

15
16
17
18

19
20
21

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

3/17

May 10, '15 Jun 7, '15
S
W
S
T
M

Secure
0 days
miscellaneous
permits
Site Work
3 days

Tue 3/17/15

Clear and grub 1 day
lot
Install temporary 1 day
power service

Wed 3/18/15

Site excavation contractor

Thu 3/19/15

Electric company

1 day

Fri 3/20/15

Electric contractor,Plumbing contractor

42 days

Mon 3/23/15

Excavate for
3 days
foundations
Form basement 13 days
walls
Place concrete 12 days
for foundations
& basement
walls basement 7 days
Cure
walls for 7 days
Strip basement 2 days
wall forms
Waterproof/insulate
2 days
basement walls

Mon 3/23/15

Install
underground
utilities
Foundation

Project: Residential Constructio
Date: Tue 2/17/15

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Wed 3/18/15

Site excavation contractor
Concrete contractor

Thu 3/26/15

Concrete contractor

Tue 4/14/15

Thu 4/30/15
Concrete contractor

Mon 5/11/15

Concrete contractor

Wed 5/13/15

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 2

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Oct
W

ID

Task
Mode
22

23
24
25
26
27
28
29
30
31
32
33
34
35

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Inspector

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Perform
foundation
inspection
Backfill
foundation
Framing

1 day

Fri 5/15/15

2 days

Mon 5/18/15

22 days

Wed 5/20/15

Install 1st floor
joists
Lay 1st floor
decking
Frame 1st floor
walls
Frame 1st floor
corners
Install 2nd floor
joists
Frame 2nd floor
decking
Frame 2nd floor
walls
Frame 2nd floor
corners
Complete roof
framing
Conduct framing
inspection
Dry In

2 days

Wed 5/20/15

2 days

Fri 5/22/15

4 days

Tue 5/26/15

1 day

Mon 6/1/15

2 days

Tue 6/2/15

2 days

Thu 6/4/15

3 days

Mon 6/8/15

2 days

Thu 6/11/15

3 days

Mon 6/15/15

Framing contractor

1 day

Thu 6/18/15

Inspector

22 days

Thu 6/18/15

Project: Residential Constructio
Date: Tue 2/17/15

Site excavation contractor

Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 3

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Oct
W

ID

Task
Mode
36
37
38
39

40
41
42
43
44
45
46

47

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Framing contractor

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Install 1st floor
sheathing
Install 2nd floor
sheathing
Install roof
decking
Install felt,
flashing and
shingles
Hang 1st floor
exterior doors
Install 1st floor
windows
Install 2nd floor
windows
Exterior Finishes

3 days

Fri 6/19/15

3 days

Wed 6/24/15

3 days

Thu 6/18/15

3 days

Mon 7/6/15

Roofing contractor

1 day

Thu 7/9/15

Framing contractor

3 days

Fri 7/10/15

3 days

Wed 7/15/15

19 days

Mon 7/20/15

Complete
exterior brick
Complete
exterior siding
Utility
Rough-B97Ins and
Complete Concrete
Rough-in
plumbing

16 days

Mon 7/20/15

3 days

Tue 8/11/15

21 days

Tue 6/23/15

5 days

Mon 6/29/15

Project: Residential Constructio
Date: Tue 2/17/15

Framing contractor
Framing contractor

Framing contractor
Framing contractor

Masonry contractor
Framing contractor

Plumbing contractor

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 4

Oct
W

ID

Task
Mode

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Inspector

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

48

Conduct rough-in 1 day
plumbing
inspection

Mon 7/6/15

49

Place concrete 11 days
for basement
floor
Rough-in
5 days
electrical
Conduct rough-in 1 day
electrical
inspection

Tue 7/7/15

52

Rough-in HVAC

Tue 7/7/15

Heating and AC contractor

53

Conduct rough-in 1 day
HVAC inspection

Fri 7/10/15

Inspector

54

Rough-in
2 days
communication phone, cable,
computer, alarm
Interior Finishes
30 days

Tue 6/23/15

50
51

55
56
57

Insulation

3 days

11 days

Place wall
1 day
insulation - 1st
floor

Project: Residential Constructio
Date: Tue 2/17/15

Concrete contractor

Electric contractor

Mon 6/29/15

Inspector

Mon 7/6/15

Electric contractor

Mon 7/20/15
Mon 7/20/15
Insulation contractor

Mon 7/20/15

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 5

Oct
W

ID

Task
Mode
58

59

60

61
62

63

64

65

66

67

Task Name

Duration

Place wall
insulation 2nd floor
Place ceiling
insulation 2nd floor
Conduct
insulation
inspection
Drywall

Start

1 day

Tue 7/21/15

1 day

Fri 7/31/15

1 day

Mon 8/3/15

9 days

Tue 7/21/15

Install drywall 2 days
- 1st floor
walls
Install drywall 2 days
- 1st floor
overhead
Install drywall 2 days
2nd floor walls

Tue 7/21/15

Install drywall 2 days
2nd floor
overhead
Tape and float 1 day
1st floor
drywall
Tape and float 1 day
2nd floor
drywall

Wed 7/29/15

Project: Residential Constructio
Date: Tue 2/17/15

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Insulation contractor

Insulation contractor

Inspector

Drywall contractor

Drywall contractor

Thu 7/23/15

Drywall contractor

Mon 7/27/15

Drywall contractor

Drywall contractor

Mon 7/27/15

Drywall contractor

Fri 7/31/15

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 6

Oct
W

ID

Task
Mode
68
69

70

71

72
73
74

75
76

Task Name

Duration

Paint and
Wallpaper
Texture all
except entry
and kitchen 1st floor
Paint all
except entry
and kitchen 1st floor
Hang
wallpaper
entry and
kitchen - 1st
floor
Texture all 2nd floor
Paint all - 2nd
floor
Paint exterior
siding & trim
work
Cabinets

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

17 days

Tue 7/28/15

1 day

Tue 7/28/15

Painting contractor

1 day

Wed 7/29/15

Painting contractor

1 day

Thu 7/30/15

Painting contractor

1 day

Wed 7/29/15

Painting contractor

1 day

Thu 7/30/15

Painting contractor

4 days

Fri 8/14/15

6 days

Fri 7/31/15

Install 1st floor 2 days
- kitchen
cabinets

Fri 7/31/15

Project: Residential Constructio
Date: Tue 2/17/15

Painting contractor

Finish carpentry contractor

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 7

Oct
W

ID

Task
Mode

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

77

Install 1st floor 1 day
- master bath
and guest
cabinets

Tue 8/4/15

Finish carpentry contractor

78

Install 2nd
1 day
floor - hall
bath and
private bath
cabinets
Install chair
2 days
rails, crown
moldings, trim

Wed 8/5/15

Finish carpentry contractor

80

Finish Plumbing 6 days

Tue 8/4/15

81

Complete 1st 1 day
floor - kitchen
plumbing
Complete 1st 2 days
floor - master
bath and guest
plumbing

Tue 8/4/15

Complete 2nd 2 days
floor - hall
bath and
private bath
plumbing

Fri 8/7/15

79

82

83

Project: Residential Constructio
Date: Tue 2/17/15

Finish carpentry contractor

Thu 8/6/15

Plumbing contractor

Plumbing contractor

Wed 8/5/15

Plumbing contractor

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 8

Oct
W

ID

Task
Mode
84

85
86

87

88

89

90
91

Task Name

Duration

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Inspector

Conduct finish 1 day
plumbing
inspection

Tue 8/11/15

Finish Electrical 3 days

Tue 8/11/15

Complete 1st 1 day
floor circuits
to service
panel
Complete 2nd 1 day
floor circuits
to service
panel
Conduct finish 1 day
electrical
inspection

Tue 8/11/15

Electric contractor

Wed 8/12/15

Electric contractor

Thu 8/13/15

Inspector

Complete
2 days
communications
wiring phone, cable,
computer,
alarm
Finish
HVAC
3 days

Wed 8/12/15

Electric contractor

Complete 1st 1 day
floor - zone 1
HVAC

Project: Residential Constructio
Date: Tue 2/17/15

Oct
W

Fri 8/14/15
Heating and AC contractor

Fri 8/14/15

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 9

ID

Task
Mode
92

93

94
95

96
97
98
99
100

101
102

Task Name

Duration

Complete 2nd 1 day
floor - zone 2
HVAC
Conduct HVAC 1 day
inspection
Carpet, Tile and
Appliances
Tile entry,
kitchen and
baths
Carpet 1st
floor
Carpet 2nd
floor
Install
appliances
Landscaping and
Grounds Work
Pour concrete
driveway and
sidewalks
Install backyard
fence
Sod and
complete
plantings - front
yard

Project: Residential Constructio
Date: Tue 2/17/15

8 days

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Oct
W

Mon 8/17/15

Heating and AC contractor

Tue 8/18/15

Inspector

3 days

Wed
8/19/15
Wed 8/19/15

2 days

Mon 8/24/15

2 days

Wed 8/26/15

Flooring contractor

1 day

Fri 8/28/15

Appliance contractor

12 days

Thu 8/20/15

2 days

Thu 8/20/15

2 days

Mon 8/31/15

2 days

Wed 9/2/15

Flooring contractor

Flooring contractor

Concrete contractor

Fencing contractor
Landscape contractor

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 10

ID
103

104
105

106
107

108

Task
Mode

Task Name

Duration

Sod and
complete
plantings backyard
Final Acceptance
Complete final
inspection for
certificate of
occupancy
Cleanup for
occupancy
Perform final
walk-through
inspection
Complete punch
list items

Project: Residential Constructio
Date: Tue 2/17/15

Start

Jan 18, '15
M
F

Feb 15, '15
T
S
W

Mar 15, '15
Apr 12, '15
S
T
M
F
T

May 10, '15 Jun 7, '15
S
W
S
T
M

Jul 5, '15
F
T

S

Aug 2, '15
W
S

Aug 30, '15
Sep 27, '15
T
M
F
T
S

Oct
W

Landscape contractor

1 day

Fri 9/4/15

8 days

Mon 9/7/15

1 day

Mon 9/7/15

Inspector

1 day

Tue 9/8/15

Maid service

1 day

Wed 9/9/15

Owner

5 days

Thu 9/10/15

General contracto

Task

Inactive Task

Manual Summary Rollup

External Milestone

Split

Inactive Milestone

Manual Summary

Deadline

Milestone

Inactive Summary

Start-only

Progress

Summary

Manual Task

Finish-only

Manual Progress

Project Summary

Duration-only

External Tasks

Page 11

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close