Residential Construction
Comments
Content
ID
Task
Mode
0
Task Name
Duration
Residential
Construction
152 days
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Tue
2/17/15
1
General Conditions 21 days
Tue 2/17/15
2
Finalize plans
20 days
and develop
estimate with
owner, architect
Sign contract and 1 day
notice to
proceed
Apply for
0 days
Permits
Secure
0 days
foundation
permit
Secure
0 days
framing
permit
Secure
0 days
electrical
permit
Secure
0 days
plumbing
permit
Secure HVAC 0 days
permit
Tue 2/17/15
General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]
Tue 3/17/15
General contractor,Architect,Owner,Mortgage lender
3
4
5
6
7
8
9
Project: Residential Constructio
Date: Tue 2/17/15
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 1
Oct
W
ID
Task
Mode
10
11
12
13
14
15
16
17
18
19
20
21
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
3/17
May 10, '15 Jun 7, '15
S
W
S
T
M
Secure
0 days
miscellaneous
permits
Site Work
3 days
Tue 3/17/15
Clear and grub 1 day
lot
Install temporary 1 day
power service
Wed 3/18/15
Site excavation contractor
Thu 3/19/15
Electric company
1 day
Fri 3/20/15
Electric contractor,Plumbing contractor
42 days
Mon 3/23/15
Excavate for
3 days
foundations
Form basement 13 days
walls
Place concrete 12 days
for foundations
& basement
walls basement 7 days
Cure
walls for 7 days
Strip basement 2 days
wall forms
Waterproof/insulate
2 days
basement walls
Mon 3/23/15
Install
underground
utilities
Foundation
Project: Residential Constructio
Date: Tue 2/17/15
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Wed 3/18/15
Site excavation contractor
Concrete contractor
Thu 3/26/15
Concrete contractor
Tue 4/14/15
Thu 4/30/15
Concrete contractor
Mon 5/11/15
Concrete contractor
Wed 5/13/15
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 2
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Oct
W
ID
Task
Mode
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Inspector
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Perform
foundation
inspection
Backfill
foundation
Framing
1 day
Fri 5/15/15
2 days
Mon 5/18/15
22 days
Wed 5/20/15
Install 1st floor
joists
Lay 1st floor
decking
Frame 1st floor
walls
Frame 1st floor
corners
Install 2nd floor
joists
Frame 2nd floor
decking
Frame 2nd floor
walls
Frame 2nd floor
corners
Complete roof
framing
Conduct framing
inspection
Dry In
2 days
Wed 5/20/15
2 days
Fri 5/22/15
4 days
Tue 5/26/15
1 day
Mon 6/1/15
2 days
Tue 6/2/15
2 days
Thu 6/4/15
3 days
Mon 6/8/15
2 days
Thu 6/11/15
3 days
Mon 6/15/15
Framing contractor
1 day
Thu 6/18/15
Inspector
22 days
Thu 6/18/15
Project: Residential Constructio
Date: Tue 2/17/15
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 3
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Oct
W
ID
Task
Mode
36
37
38
39
40
41
42
43
44
45
46
47
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Framing contractor
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Install 1st floor
sheathing
Install 2nd floor
sheathing
Install roof
decking
Install felt,
flashing and
shingles
Hang 1st floor
exterior doors
Install 1st floor
windows
Install 2nd floor
windows
Exterior Finishes
3 days
Fri 6/19/15
3 days
Wed 6/24/15
3 days
Thu 6/18/15
3 days
Mon 7/6/15
Roofing contractor
1 day
Thu 7/9/15
Framing contractor
3 days
Fri 7/10/15
3 days
Wed 7/15/15
19 days
Mon 7/20/15
Complete
exterior brick
Complete
exterior siding
Utility
Rough-B97Ins and
Complete Concrete
Rough-in
plumbing
16 days
Mon 7/20/15
3 days
Tue 8/11/15
21 days
Tue 6/23/15
5 days
Mon 6/29/15
Project: Residential Constructio
Date: Tue 2/17/15
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Masonry contractor
Framing contractor
Plumbing contractor
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 4
Oct
W
ID
Task
Mode
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Inspector
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
48
Conduct rough-in 1 day
plumbing
inspection
Mon 7/6/15
49
Place concrete 11 days
for basement
floor
Rough-in
5 days
electrical
Conduct rough-in 1 day
electrical
inspection
Tue 7/7/15
52
Rough-in HVAC
Tue 7/7/15
Heating and AC contractor
53
Conduct rough-in 1 day
HVAC inspection
Fri 7/10/15
Inspector
54
Rough-in
2 days
communication phone, cable,
computer, alarm
Interior Finishes
30 days
Tue 6/23/15
50
51
55
56
57
Insulation
3 days
11 days
Place wall
1 day
insulation - 1st
floor
Project: Residential Constructio
Date: Tue 2/17/15
Concrete contractor
Electric contractor
Mon 6/29/15
Inspector
Mon 7/6/15
Electric contractor
Mon 7/20/15
Mon 7/20/15
Insulation contractor
Mon 7/20/15
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 5
Oct
W
ID
Task
Mode
58
59
60
61
62
63
64
65
66
67
Task Name
Duration
Place wall
insulation 2nd floor
Place ceiling
insulation 2nd floor
Conduct
insulation
inspection
Drywall
Start
1 day
Tue 7/21/15
1 day
Fri 7/31/15
1 day
Mon 8/3/15
9 days
Tue 7/21/15
Install drywall 2 days
- 1st floor
walls
Install drywall 2 days
- 1st floor
overhead
Install drywall 2 days
2nd floor walls
Tue 7/21/15
Install drywall 2 days
2nd floor
overhead
Tape and float 1 day
1st floor
drywall
Tape and float 1 day
2nd floor
drywall
Wed 7/29/15
Project: Residential Constructio
Date: Tue 2/17/15
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Insulation contractor
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Thu 7/23/15
Drywall contractor
Mon 7/27/15
Drywall contractor
Drywall contractor
Mon 7/27/15
Drywall contractor
Fri 7/31/15
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 6
Oct
W
ID
Task
Mode
68
69
70
71
72
73
74
75
76
Task Name
Duration
Paint and
Wallpaper
Texture all
except entry
and kitchen 1st floor
Paint all
except entry
and kitchen 1st floor
Hang
wallpaper
entry and
kitchen - 1st
floor
Texture all 2nd floor
Paint all - 2nd
floor
Paint exterior
siding & trim
work
Cabinets
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
17 days
Tue 7/28/15
1 day
Tue 7/28/15
Painting contractor
1 day
Wed 7/29/15
Painting contractor
1 day
Thu 7/30/15
Painting contractor
1 day
Wed 7/29/15
Painting contractor
1 day
Thu 7/30/15
Painting contractor
4 days
Fri 8/14/15
6 days
Fri 7/31/15
Install 1st floor 2 days
- kitchen
cabinets
Fri 7/31/15
Project: Residential Constructio
Date: Tue 2/17/15
Painting contractor
Finish carpentry contractor
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 7
Oct
W
ID
Task
Mode
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
77
Install 1st floor 1 day
- master bath
and guest
cabinets
Tue 8/4/15
Finish carpentry contractor
78
Install 2nd
1 day
floor - hall
bath and
private bath
cabinets
Install chair
2 days
rails, crown
moldings, trim
Wed 8/5/15
Finish carpentry contractor
80
Finish Plumbing 6 days
Tue 8/4/15
81
Complete 1st 1 day
floor - kitchen
plumbing
Complete 1st 2 days
floor - master
bath and guest
plumbing
Tue 8/4/15
Complete 2nd 2 days
floor - hall
bath and
private bath
plumbing
Fri 8/7/15
79
82
83
Project: Residential Constructio
Date: Tue 2/17/15
Finish carpentry contractor
Thu 8/6/15
Plumbing contractor
Plumbing contractor
Wed 8/5/15
Plumbing contractor
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 8
Oct
W
ID
Task
Mode
84
85
86
87
88
89
90
91
Task Name
Duration
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Inspector
Conduct finish 1 day
plumbing
inspection
Tue 8/11/15
Finish Electrical 3 days
Tue 8/11/15
Complete 1st 1 day
floor circuits
to service
panel
Complete 2nd 1 day
floor circuits
to service
panel
Conduct finish 1 day
electrical
inspection
Tue 8/11/15
Electric contractor
Wed 8/12/15
Electric contractor
Thu 8/13/15
Inspector
Complete
2 days
communications
wiring phone, cable,
computer,
alarm
Finish
HVAC
3 days
Wed 8/12/15
Electric contractor
Complete 1st 1 day
floor - zone 1
HVAC
Project: Residential Constructio
Date: Tue 2/17/15
Oct
W
Fri 8/14/15
Heating and AC contractor
Fri 8/14/15
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 9
ID
Task
Mode
92
93
94
95
96
97
98
99
100
101
102
Task Name
Duration
Complete 2nd 1 day
floor - zone 2
HVAC
Conduct HVAC 1 day
inspection
Carpet, Tile and
Appliances
Tile entry,
kitchen and
baths
Carpet 1st
floor
Carpet 2nd
floor
Install
appliances
Landscaping and
Grounds Work
Pour concrete
driveway and
sidewalks
Install backyard
fence
Sod and
complete
plantings - front
yard
Project: Residential Constructio
Date: Tue 2/17/15
8 days
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Oct
W
Mon 8/17/15
Heating and AC contractor
Tue 8/18/15
Inspector
3 days
Wed
8/19/15
Wed 8/19/15
2 days
Mon 8/24/15
2 days
Wed 8/26/15
Flooring contractor
1 day
Fri 8/28/15
Appliance contractor
12 days
Thu 8/20/15
2 days
Thu 8/20/15
2 days
Mon 8/31/15
2 days
Wed 9/2/15
Flooring contractor
Flooring contractor
Concrete contractor
Fencing contractor
Landscape contractor
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 10
ID
103
104
105
106
107
108
Task
Mode
Task Name
Duration
Sod and
complete
plantings backyard
Final Acceptance
Complete final
inspection for
certificate of
occupancy
Cleanup for
occupancy
Perform final
walk-through
inspection
Complete punch
list items
Project: Residential Constructio
Date: Tue 2/17/15
Start
Jan 18, '15
M
F
Feb 15, '15
T
S
W
Mar 15, '15
Apr 12, '15
S
T
M
F
T
May 10, '15 Jun 7, '15
S
W
S
T
M
Jul 5, '15
F
T
S
Aug 2, '15
W
S
Aug 30, '15
Sep 27, '15
T
M
F
T
S
Oct
W
Landscape contractor
1 day
Fri 9/4/15
8 days
Mon 9/7/15
1 day
Mon 9/7/15
Inspector
1 day
Tue 9/8/15
Maid service
1 day
Wed 9/9/15
Owner
5 days
Thu 9/10/15
General contracto
Task
Inactive Task
Manual Summary Rollup
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 11
Sponsor Documents