Residential Construction
Comments
Content
ID
Task
Mode
0
1
2
3
4
5
6
7
8
9
Task Name
Duration
Start
Finish
Mar
13, '16
S
Residential
Construction
152 days
General Conditions 21 days
Finalize plans
20 days
and develop
estimate with
owner, architect
Sign contract
1 day
and notice to
proceed
Apply for
0 days
Permits
Secure
0 days
foundation
permit
Secure
0 days
framing
permit
Secure
0 days
electrical
permit
Secure
0 days
plumbing
permit
Secure HVAC 0 days
permit
Project: Residential Constructio
Date: Wed 4/27/16
Wed
4/27/16
Apr 10, '16
T
M
May 8, '16
F
T
S
Jun 5, '16
W
S
Jul 3, '16
T
M
Thu
11/24/16
Wed 4/27/16Wed 5/25/16
Wed
Tue 5/24/16
4/27/16
General contractor[50%],Architect[50%],O
General contractor,Architect,Owner,Mor
Wed
5/25/16
Wed
5/25/16
Wed
5/25/16
Wed
5/25/16
Wed
5/25/16
Wed
5/25/16
5/25
Wed
5/25/16
Wed
5/25/16
5/25
Wed
5/25/16
Wed
5/25/16
5/25
Wed
5/25/16
Wed
5/25/16
5/25
Wed
5/25/16
Wed
5/25/16
5/25
5/25
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 1
ID
Task
Mode
10
11
12
13
14
15
16
17
18
19
20
21
Task Name
Duration
Start
Finish
Mar
13, '16
S
Secure
0 days
miscellaneous
permits
Site Work
3 days
Clear and grub 1 day
lot
Install
1 day
temporary
power service
Install
1 day
underground
utilities
Foundation
42 days
Excavate for
3 days
foundations
Form basement 13 days
walls
Place concrete 12 days
for foundations
& basement
walls basement 7 days
Cure
walls for 7 days
Strip basement 2 days
wall forms
Waterproof/insulate
2 days
basement walls
Project: Residential Constructio
Date: Wed 4/27/16
Wed
5/25/16
Apr 10, '16
T
M
May 8, '16
F
T
Wed
5/25/16
Thu 5/26/16 Mon 5/30/16
Thu 5/26/16 Thu 5/26/16
Wed
6/22/16
Thu 7/7/16
M
Site excavation contractor
Concrete contractor
Concrete
Fri 7/8/16
Mon
7/18/16
Tue 7/19/16 Wed
7/20/16
Thu 7/21/16 Fri 7/22/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 2
Jul 3, '16
T
Electric contractor,Plumbing contract
Tue 5/31/16 Wed 7/27/16
Tue 5/31/16 Thu 6/2/16
Tue 6/21/16
S
Electric company
Mon
5/30/16
Fri 6/3/16
5/25
Jun 5, '16
W
Site excavation contractor
Fri 5/27/16 Fri 5/27/16
Mon
5/30/16
S
ID
Task
Mode
22
23
24
25
26
27
28
29
30
31
32
33
34
Task Name
Duration
Start
Finish
Mar
13, '16
S
Perform
1 day
foundation
inspection
Backfill
2 days
foundation
Framing
22 days
Install 1st floor 2 days
joists
Lay 1st floor
2 days
decking
Frame 1st floor 4 days
walls
Frame 1st floor 1 day
corners
Install 2nd floor 2 days
joists
Frame 2nd floor 2 days
decking
Frame 2nd floor 3 days
walls
Frame 2nd floor 2 days
corners
Complete roof 3 days
framing
Conduct framing 1 day
inspection
Project: Residential Constructio
Date: Wed 4/27/16
Mon
7/25/16
Apr 10, '16
T
M
May 8, '16
F
T
Mon
7/25/16
Tue 7/26/16 Wed
7/27/16
Thu 7/28/16 Fri 8/26/16
Thu 7/28/16 Fri 7/29/16
Mon 8/1/16 Tue 8/2/16
Wed 8/3/16 Mon 8/8/16
Tue 8/9/16 Tue 8/9/16
Wed
Thu 8/11/16
8/10/16
Fri 8/12/16 Mon
8/15/16
Tue 8/16/16 Thu 8/18/16
Fri 8/19/16 Mon
8/22/16
Tue 8/23/16 Thu 8/25/16
Fri 8/26/16 Fri 8/26/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 3
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
35
36
37
38
39
40
41
42
43
44
45
46
47
Task Name
Duration
Start
Finish
Mar
13, '16
S
Dry In
Install 1st floor
sheathing
Install 2nd floor
sheathing
Install roof
decking
Install felt,
flashing and
shingles
Hang 1st floor
exterior doors
Install 1st floor
windows
Install 2nd floor
windows
Exterior Finishes
Complete
exterior brick
Complete
exterior siding
Utility
Rough-B97Ins and
Complete
Concrete
Rough-in
plumbing
Project: Residential Constructio
Date: Wed 4/27/16
22 days
3 days
3 days
Fri 8/26/16
Mon
8/29/16
Thu 9/1/16
3 days
Fri 8/26/16 Tue 8/30/16
3 days
Tue 9/13/16 Thu 9/15/16
1 day
Fri 9/16/16 Fri 9/16/16
3 days
Mon
Wed
9/19/16
9/21/16
Thu 9/22/16 Mon
9/26/16
Tue 9/27/16 Fri 10/21/16
Tue 9/27/16 Tue
10/18/16
Wed
Fri 10/21/16
10/19/16
Wed
Wed
8/31/16
9/28/16
3 days
19 days
16 days
3 days
21 days
5 days
Apr 10, '16
T
M
May 8, '16
F
T
S
Jun 5, '16
W
S
Jul 3, '16
T
M
Mon 9/26/16
Wed
8/31/16
Mon 9/5/16
Mas
Tue 9/6/16 Mon
9/12/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 4
ID
Task
Mode
48
49
50
51
52
53
54
55
56
57
Task Name
Duration
Start
Finish
Mar
13, '16
S
Conduct
1 day
rough-in
plumbing
inspection
Place concrete 11 days
for basement
floor
Rough-in
5 days
electrical
Conduct
1 day
rough-in
electrical
inspection
Rough-in HVAC 3 days
Conduct
1 day
rough-in HVAC
inspection
Rough-in
2 days
communication
- phone, cable,
computer, alarm
Interior Finishes 30 days
Insulation
11 days
Place wall
1 day
insulation 1st floor
Project: Residential Constructio
Date: Wed 4/27/16
Apr 10, '16
T
M
May 8, '16
F
T
Tue 9/13/16 Tue 9/13/16
Wed
9/14/16
Wed
9/28/16
Tue 9/6/16 Mon
9/12/16
Tue 9/13/16 Tue 9/13/16
Wed 9/14/16Fri 9/16/16
Mon
Mon
9/19/16
9/19/16
Wed
8/31/16
Thu 9/1/16
Tue 9/27/16 Mon 11/7/16
Tue 9/27/16 Tue 10/11/16
Tue 9/27/16 Tue 9/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 5
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
58
59
60
61
62
63
64
65
66
Task Name
Duration
Start
Finish
Mar
13, '16
S
Place wall
1 day
insulation 2nd floor
Place ceiling 1 day
insulation 2nd floor
Conduct
1 day
insulation
inspection
Drywall
9 days
Install drywall 2 days
- 1st floor
walls
Install drywall 2 days
- 1st floor
overhead
Install drywall 2 days
2nd floor
walls
Install drywall 2 days
2nd floor
overhead
Tape and float 1 day
1st floor
drywall
Project: Residential Constructio
Date: Wed 4/27/16
Wed
9/28/16
Wed
9/28/16
Mon
10/10/16
Mon
10/10/16
Tue
10/11/16
Tue
10/11/16
Apr 10, '16
T
M
May 8, '16
F
T
Wed 9/28/16Mon 10/10/16
Wed
Thu 9/29/16
9/28/16
Fri 9/30/16 Mon
10/3/16
Tue 10/4/16 Wed
10/5/16
Thu 10/6/16 Fri 10/7/16
Tue 10/4/16 Tue 10/4/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 6
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
67
68
69
70
71
72
73
74
75
Task Name
Duration
Start
Finish
Mar
13, '16
S
Tape and float 1 day
2nd floor
drywall
Paint and
17 days
Wallpaper
Texture all
1 day
except entry
and kitchen 1st floor
Paint all
1 day
except entry
and kitchen 1st floor
Hang
1 day
wallpaper
entry and
kitchen - 1st
floor
Texture all - 1 day
2nd floor
Paint all - 2nd 1 day
floor
Paint exterior 4 days
siding & trim
work
Cabinets
6 days
Project: Residential Constructio
Date: Wed 4/27/16
Mon
10/10/16
Mon
10/10/16
Wed
10/5/16
Wed
10/5/16
Thu
10/27/16
Wed
10/5/16
Apr 10, '16
T
M
May 8, '16
F
T
Thu 10/6/16 Thu 10/6/16
Fri 10/7/16 Fri 10/7/16
Thu 10/6/16 Thu 10/6/16
Fri 10/7/16 Fri 10/7/16
Mon
10/24/16
Thu
10/27/16
Mon 10/10/16
Mon 10/17/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 7
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
76
77
78
79
80
81
82
Task Name
Duration
Start
Finish
Mar
13, '16
S
Install 1st
2 days
floor - kitchen
cabinets
Install 1st
1 day
floor - master
bath and
guest cabinets
Install 2nd
floor - hall
bath and
private bath
cabinets
Install chair
rails, crown
moldings,
trim
Finish Plumbing
Complete 1st
floor - kitchen
plumbing
Complete 1st
floor - master
bath and
guest
plumbing
Project: Residential Constructio
Date: Wed 4/27/16
Mon
10/10/16
Tue
10/11/16
Wed
10/12/16
Wed
10/12/16
1 day
Thu
10/13/16
Thu
10/13/16
2 days
Fri 10/14/16 Mon
10/17/16
6 days
1 day
Wed 10/12/16
Wed 10/19/16
Wed
Wed
10/12/16
10/12/16
2 days
Thu
10/13/16
Apr 10, '16
T
M
May 8, '16
F
T
Fri 10/14/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 8
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
83
84
85
86
87
88
Task Name
Duration
Start
Finish
Mar
13, '16
S
Complete 2nd 2 days
floor - hall
bath and
private bath
plumbing
Conduct finish 1 day
plumbing
inspection
Finish Electrical 3 days
Complete 1st 1 day
floor circuits
to service
panel
Complete 2nd 1 day
floor circuits
to service
panel
Conduct finish 1 day
electrical
inspection
Project: Residential Constructio
Date: Wed 4/27/16
Mon
10/17/16
Tue
10/18/16
Wed
10/19/16
Wed
10/19/16
Apr 10, '16
T
M
May 8, '16
F
T
Wed 10/19/16
Fri 10/21/16
Wed
Wed
10/19/16
10/19/16
Thu
10/20/16
Thu
10/20/16
Fri 10/21/16 Fri 10/21/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 9
S
Jun 5, '16
W
S
Jul 3, '16
T
M
Plum
ID
Task
Mode
89
90
91
92
93
94
95
96
97
98
Task Name
Duration
Start
Finish
Mar
13, '16
S
Complete
2 days
communications
wiring phone, cable,
computer,
alarm
Finish
HVAC
3 days
Complete 1st 1 day
floor - zone 1
HVAC
Complete 2nd 1 day
floor - zone 2
HVAC
Conduct
1 day
HVAC
inspection
Carpet, Tile and 8 days
Appliances
Tile entry,
3 days
kitchen and
baths
Carpet 1st
2 days
floor
Carpet 2nd
2 days
floor
Install
1 day
appliances
Project: Residential Constructio
Date: Wed 4/27/16
Thu
10/20/16
Apr 10, '16
T
M
May 8, '16
F
T
Fri 10/21/16
Mon 10/24/16
Wed 10/26/16
Mon
Mon
10/24/16
10/24/16
Tue
10/25/16
Tue
10/25/16
Wed
10/26/16
Wed
10/26/16
Thu
10/27/16
Thu
10/27/16
Mon
11/7/16
Mon
10/31/16
Tue 11/1/16 Wed
11/2/16
Thu 11/3/16 Fri 11/4/16
Mon
11/7/16
Mon
11/7/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 10
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
Task
Mode
99
100
101
102
103
104
105
106
107
Task Name
Duration
Start
Finish
Mar
13, '16
S
Landscaping and
Grounds Work
Pour concrete
driveway and
sidewalks
Install backyard
fence
Sod and
complete
plantings - front
yard
Sod and
complete
plantings backyard
Final Acceptance
Complete final
inspection for
certificate of
occupancy
Cleanup for
occupancy
Perform final
walk-through
inspection
Project: Residential Constructio
Date: Wed 4/27/16
12 days
2 days
2 days
2 days
M
May 8, '16
F
T
Fri 10/28/16 Mon
11/14/16
Fri 10/28/16 Mon
10/31/16
Tue 11/8/16 Wed
11/9/16
Thu
Fri 11/11/16
11/10/16
1 day
Mon
11/14/16
8 days
1 day
Tue 11/15/16Thu 11/24/16
Tue
Tue
11/15/16
11/15/16
1 day
Wed
11/16/16
Thu
11/17/16
1 day
Apr 10, '16
T
Mon
11/14/16
Wed
11/16/16
Thu
11/17/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 11
S
Jun 5, '16
W
S
Jul 3, '16
T
M
ID
108
Task
Mode
Task Name
Duration
Start
Finish
Mar
13, '16
S
Complete punch 5 days
list items
Project: Residential Constructio
Date: Wed 4/27/16
Apr 10, '16
T
M
May 8, '16
F
T
Fri 11/18/16 Thu
11/24/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 12
S
Jun 5, '16
W
S
Jul 3, '16
T
M
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
],Architect[50%],Owner[12%],Mortgage lender[12%]
hitect,Owner,Mortgage lender
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 13
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
ctor
Plumbing contractor
ontractor
ncrete contractor
Concrete contractor
Concrete contractor
Concrete contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 14
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
Inspector
Aug 28, '16
W
S
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Site excavation contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Inspector
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 15
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
Oct 23, '16
T
S
F
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Framing contractor
Framing contractor
Framing contractor
Roofing contractor
Framing contractor
Framing contractor
Framing contractor
Masonry contractor
Framing contractor
Plumbing contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 16
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
Inspector
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Concrete contractor
Electric contractor
Inspector
Heating and AC contractor
Inspector
Electric contractor
Insulation contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 17
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
Insulation contractor
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Drywall contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 18
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
Drywall contractor
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Painting contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 19
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Finish carpentry contractor
Nov 20, '16
S
T
M
Dec 18, '16
F
Finish carpentry contractor
Finish carpentry contractor
Finish carpentry contractor
Plumbing contractor
Plumbing contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 20
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Plumbing contractor
Nov 20, '16
S
T
M
Dec 18, '16
F
Inspector
Electric contractor
Electric contractor
Inspector
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 21
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Electric contractor
Nov 20, '16
S
T
M
Dec 18, '16
F
Heating and AC contractor
Heating and AC contractor
Inspector
Flooring contractor
Flooring contractor
Flooring contractor
Appliance contractor
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 22
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
Concrete contractor
Fencing contractor
Landscape contractor
Landscape contractor
Inspector
Maid service
Owner
Project: Residential Constructio
Date: Wed 4/27/16
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 23
T
Jan 15, '17
S
W
S
Jul 3, '16
M
F
Jul 31, '16
T
S
Project: Residential Constructio
Date: Wed 4/27/16
Aug 28, '16
W
S
T
Sep 25, '16
M
F
Oct 23, '16
T
S
W
Nov 20, '16
S
T
M
Dec 18, '16
F
General contractor
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 24
T
Jan 15, '17
S
W
S
Sponsor Documents