Restoration of HVAC Systems, Design/Build Solution, Commissioning and more at Warner Robins Air Logistics Center

Published on May 2016 | Categories: Types, Research, Arts & Architecture | Downloads: 36 | Comments: 0 | Views: 173
of 2
Download PDF   Embed   Report

McKenney’s, Inc. offered a turnkey design/build solution including analysis, recommendations, budgetary cost estimates, design, controls, execution, commissioning and more. For more visit http://mckenneys.com.

Comments

Content

Project HigHligHts

B

McKenney’s turnkey HVAC services and Mentor-Protégé partnership paint an efficient picture for Warner Robins Air Logistics Center
Ten years prior, McKenney’s was the prime contractor responsible for the design and construction of the large, custom-built air handlers. As such we were called in by the Maintenance Wing Energy Manager for WRALC to evaluate existing equipment and controls in order to provide recommen-

Project Team ž Prime Contractor: Willis Mechanical ž Owner: WRALC ž Engineer: McKenney’s Inc. The Challenge ž Identify Bldg. 89 HVAC issues ž Offer solutions and budgets to repair equipment and controls ž Provide an opportunity for our protégé by offering a turnkey solution for the hanger repairs The Solution ž An initial audit under a government credit card purchase ž Offered a turnkey design/build solution that met the base’s tight schedule and budget ž Leveraged a mentor-protégé affiliation to expedite repairs ž Trained base maintenance staff to minimize future malfunctions The Results ž Returned the HVAC systems back to their original functioning states, including controls ž Allowed uninterrupted painting of planes in Bldg. 89 while providing optimal temperature and humidity during the process ž Continued our successful protégé relationship by providing an introduction to WRALC

uilding 89 at the Warner Robins Air Logistics Center (WRALC) is used for depainting and painting large military cargo aircraft. Monitoring and regulating temperature and humidity in the hangar is critical during the painting process to meet the technical order and ensure the

quality of the surface finish. In the winter of 2009, temperatures were well below normal. The chilled water and heating coils in the 300,000 cfm, 100 percent outside air handling units serving the hanger froze and burst.

dations for restoring the HVAC system to its original functioning state. The initial evaluation was performed under a government credit card purchase. continued on reverse

For more information contact McKenney’s at 404-622-5000. [email protected] ž www.mckenneys.com

Project HigHligHts

“T

he project at Building 89 highlights the

technical, execution and contract administrative skills that McKenney’s can bring to the table to support the missions and mandates facing government installations across the Southeast.”

McKenney’s began by assembling a highly qualified team composed of in-house engineers, service personnel and controls technicians to conduct a one-day comprehensive assessment of existing conditions, operations and functionality of the Building 89 HVAC systems, including pressure testing the coils. It wasn’t easy. With such a short schedule and with so much system damage it was difficult to pinpoint the most likely failure scenario out of all the possibilities. McKenney’s produced a detailed report of the findings and made several recommendations on equipment and control system repairs, operator training and long-term maintenance strategies to ensure system integrity over the long term. The report also included cost estimates for the recommendations offered. Time and budget constraints only complicated things for the base. In order to get the repairs

done quickly to allow the building to continue being productive, the base negotiated directly with Willis Mechanical, a member of the SBA 8(a) program and McKenney’s official SBA-approved protégé team partner. Repair of the heating and cooling system, the air handler unit coils and controls became a turnkey design/build project. As prime contractor, our protégé performed over 50 percent of the work with McKenney’s performing the remainder. Not only did McKenney’s offer a turnkey solution including analysis, recommendations, budgetary cost estimates, design, controls, execution, commissioning and owner training, we also met our responsibilities to our protégé, Willis Mechanical. This mentor-protégé partnership provided the contract vehicle to allow

WRALC to bring Building 89’s HVAC system back to acceptable operation. According to the Director of Government Facilities at McKenney’s, “The project at Building 89 highlights the technical, execution and contract administrative skills that McKenney’s can bring to the table to support the missions and mandates facing government installations across the Southeast. Our plan is to continue to serve them from a position of expertise and knowledge.”

The information contained here is not intended as an Air Force endorsement.

McKenney’s, Inc. ž 1056 Moreland Industrial Boulevard, Atlanta, Georgia 30316

Copyright © 2011 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close