Relationships (cont’d)
• Start-to-Start
– Start-to-Start relationship implies that
an activity can start once another
specified activity has started
– For example, the design phase can start
as soon as the permitting process has
started

Relationships (cont’d)
• Finish-to finish
– Finish-to-Finish relationship implies
that the completion of an activity is
dependent upon the completion of
another activity. This relation ship is
commonly used with start-to-start
relationships
– For example, the software user’s
manual can be started after the start
of coding and testing but can’t be
completed until coding and
debugging is completed

Relationships (cont’d)
• Start-to-Finish
– Start-to-Finish relationship implies that
an activity can’t be completed until the
predecessor activity has started
– This type of relationship is very rarely
used

Resources
• All projects consume resources!
• Resources are not just people:
– resources can include money, material,
equipment, and more.
– How well these resources are allocated
and monitored is a key measure of any
project’s success or failure

Resources (Cont’d)
• Assigning resources to a project
and monitoring and reporting
against the schedule provides the
project manager with:
– Ability to estimate remaining work
– Ability to prepare accurate progress
payments
– Ability to provide historical data
– Ability to address changes

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close