cKenney’s renovated
HVAC systems in a 30-story
Charlotte office tower for
a law school tenant.
THE CHALLENGE
The 10 floors of the heavily populated law
school required more outside air than typical
office space. The challenge, how to deliver the
air thru an occupied high rise building while
maintaining the budget and meeting the
aggressive five-month project schedule.
THE SOLUTION
McKenney’s worked with the design team
and decided that installing a 92-ton outside
air unit on top of the building would be more
cost effective than installing individual custom
units above the ceilings on each floor. This
approach saved the project approximately
$200,000. Diligent field coordination between
McKenney’s, the general contractor, police,
local transit service, parking lot owners
and insurance companies was necessary
to ensure a safe and efficient helicopter lift
process. An existing open shaft was used
to install a duct riser from the roof down to
the school’s ten floors.
THE RESULTS
McKenney’s delivered the project on time
and within budget without any disruption
to other tenants.
Setting the Bar High
PROJECT NAME
Law School HVAC Upgrade
PROJECT LOCATION
Charlotte, North Carolina
PROJECT TEAM
Owner: Building
Management Company
General Contractor:
Balfour Beatty
Architect: Jenkins • Peer
Engineer: Barrett Woodyard
& Associates
Subcontractor: McKenney’s, Inc.
SPECIALIZATIONS
Design/Assist
Pipe Shop Prefab
Sheet Metal Shop Prefab
MARKETS
Commercial Office
Corporate Campus
Education
The content of this document is not intended as an endorsement.
www.mckenneys.com
© 2014 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.
McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners.
404-622-5000
[email protected]
1056 Moreland Industrial Boulevard
Atlanta, Georgia 30316
704-357-1200
[email protected]
3601 Performance Road
Charlotte, North Carolina 28214