Techno Economic Assessment

Published on December 2016 | Categories: Documents | Downloads: 51 | Comments: 0 | Views: 204
of 18
Download PDF   Embed   Report

Comments

Content

Centre for Energy Technology
Ricoh Clean Energy Scholarship

Techno-economic assessment of novel engineering systems for stranded geothermal energy resources.

Ashok A. Kaniyal Prof. Graham ‘Gus’ J. Nathan Prof. Jonathan J. Pincus

Delivering innovative technologies for a clean energy future

School of Mechanical Engineering

Life Impact | The University of Adelaide

Centre for Energy Technology

Australia’s Energy Network

Electricity transmission network

Geothermal resources in Cooper Basin

Geothermal resources in Cooper Basin
Slide 1

Oil and Natural Gas Pipeline Life Impact | The University of Adelaide network (Geoscience Australia, 2009)

Centre for Energy Technology

The Geothermal-Data Centre Concept

• Geothermal data fibre link – Capital: $60 m + $15 m (Op ex).

National Broadband Network (NBN)
(NBN Co., 2010)

Geothermal-data fibre link Proposed NBN Co Fibre optic links Fibre optic node
Geothermal-data fibre link ~ $60m

DBCDE, 2010.

Slide 2

Life Impact | The University of Adelaide

Centre for Energy Technology

Presentation outline • Gap in literature; • Techno-economic analysis framework;

• Analysis of Geothermal-data centre concept – early results;
• Future work; • Conclusions.
Slide 3

Life Impact | The University of Adelaide

Centre for Energy Technology

Gap in literature
• Economic assessment of geothermal direct heat and EGS CHP applications. • Address limitations of other novel geothermal engineering systems,
– Dickinson et al. (2010) and Atrens et al. (2009).

• Geothermal-data centre ‘micro-grid’ follows complementary network infrastructure investment.
– c.f. Siddiqui and Maribu (2009), Fleten (2007).

• Application of dynamic capital investment decision methods,
– Not considered in this context.

Slide 4

Life Impact | The University of Adelaide

Centre for Energy Technology

Aims
• Technical feasibility of direct heat and CHP enhanced geothermal system applications, • Economic viability of fibre optic network and geothermal plant under data centre client servicing scenarios: – Net present value - Deterministic static analysis, – NPV approach + dynamic demand and geothermal plant cost uncertainty.

• Social welfare analysis – a case for public involvement in project.
• Application of techno-economic framework to other eng systems.
Slide 5 Life Impact | The University of Adelaide

Centre for Energy Technology

Framework for techno-economic analysis

1. Develop a concept for an engineering system.
Increasing detail 2. Steady state thermodynamic analysis of plant concept. 3. Static NPV analysis of investment. 4. Dynamic analysis of investment in geothermal and network resource faculties. 5. Social benefit analysis of investment in plant and network resource.

Slide 6

Life Impact | The University of Adelaide

Centre for Energy Technology

Standardised data centre unit

• Modular data centre of total capacity 350 kWe (Barroso, 2007):
– IT load = 270 kWe – Cooling load = 200 kWr
Cooling load ~200 kWr
Data Centre Co.
hv Geothermal-data fibre link (1000-1500 km)

NBN market

IT electrical load ~270 kWe

Slide 7

Life Impact | The University of Adelaide

Centre for Energy Technology

EGS CHP – Organic Rankine cycle steady state analysis
Injection well Production well Temperature [K]

Geo-fluid: water
6

Geothermal water: Tin = 508 K, TH = 490 K, ΔT = 5 K, = 50 kg/s.
Radial turbine

490 320 5 5s

6

1 2

Pre-heater

Evaporator
1

4

3 2s

Geo-fluid
5

Generator Wnet = 1.2 MWe

Feed pump
4 3

Entropy (s) [kJ/kg-K]

Absorption refrigeration cycle (not shown) 2 NH3-H20

Ext. heat exchanger Absorption cycle: generator

Φ ≈ 68% (Tc = 562 K, Tin = 375 K, TH = 320 K)

DiPippo (2005) Heberle and Bruggemann (2010) Liu , Chien and Wang (2004)

Refrigeration load

Slide 8

Life Impact | The University of Adelaide

Centre for Energy Technology

Energy consumption pattern

Natural gas electricity generation ≈ 2.55 MWe

Organic Rankine Cycle 1.2 MWe
Geothermal Local CHP Direct heat cooling Absorption chiller cooling 14x Modular data centres

Total IT electrical Load 3.75 MWe
hv

NBN market

Geothermal-data fibre link (1500 km)

3.6 MWth (input) > 2.8MWr (average required output) Absorption chiller plant: COP = 1.0

Broad X Absorption Chiller Design Manual (2008)
Slide 9 Life Impact | The University of Adelaide

Centre for Energy Technology

EGS wells and ORC plant costing

Cost component First injection + production well pair ORC plant
+ natural gas storage tank + construction + contingency.

A$ M $30.5 M $3.82 M

Additional production wells
Ulrich (1984) Vasudevan and Agrawal (2000)

$10.2 M

Slide 10

Life Impact | The University of Adelaide

Centre for Energy Technology

ORC plant economies of scale
$18

Cost of plant and installation (A$ M)

Grass roots capital (Full Plant) ($AUD) Plant size incrementation cost comparison (4 plant units)

$16 $14 $12 $10 $8

4 x 1 plant unit (PU) $15.87 m 3 PU + 1 PU = $12.51m 2 PU x 2 = $11.69m 4 PU $10.93 m

$6
$4 $2 $0 1 2 3 4 5

Geothermal ORC plant units (corresp. no. of production wells)

Slide 11

Life Impact | The University of Adelaide

Centre for Energy Technology

Local CHP – Net Present Value scenarios
NPV scenario iteration Mk 1 Description

- Increasing rate of data centre commitment,

- Early investment = no construction lag.
Mk 2

- Increasing rate of data centre commitment, - Economies of scale investment in plant.

Rt = Annual revenue received per data centre, Ct = Capital and ongoing operating expenditure. i = Cost of capital = 6%

Slide 12

Life Impact | The University of Adelaide

Centre for Energy Technology

Local CHP – Net Present Value scenarios
0 $1 2 3 4 5 15% 10% 5% 0% -5% -10%

NPV and Total expenditure (A$ M)

-$20 -$40 -$60 -$80 -$100

-$120
-$140 -$160

-15%
-20%

Number of capacity increments (production wells + ORC plant) 1 Total expenditure Mk 2
Total expenditure Mk 2 3

-25%

Slide 13

NPV/Total expenditure Mk 1 2

Life Impact | The University NPV/Total expenditure Mk 2 3 of Adelaide

NPV/Total expenditure

Centre for Energy Technology

Fibre optic network investment
Cumulative NPV of investment in Geothermal-Data Fibre link
$100

Cumulative net present value (A$ M)

28% subscription
$80 $60

40% subscription 50% subscription 60% subscription Barroso (2007)

$40
$20 $0 -$20 -$40 -$60

Years
5 10 15 20 25 30 35 40 45

-$80 Slide 14

Life Impact | The University of Adelaide

Centre for Energy Technology

Dynamic investment decision
• Real options approach. • An optimal path for capacity investments given uncertain:
– Data centre demand for remote co-location and competition b/w sites,
• Method: Aguerrevere (2003);

– Influence of learning on cost of establishing geothermal wells and plant,
• Method: Bolton and Faure-Grimaud (2009).

• Social welfare analysis under uncertain demand – public subsidy?
– Method: Danau (2010).

Slide 15

Life Impact | The University of Adelaide

Centre for Energy Technology

Future work

• Another application: Wind CHP – a techno-economic analysis? • H2-fuel cells CHP for NEM feed-in and adsorption desalination. • Common use plant c.f. fibre optic network investment.

Slide 16

Life Impact | The University of Adelaide

Centre for Energy Technology

Conclusions

• Enhanced geothermal system CHP application technically feasible. • Geothermal-data centre concept is economically viable. • Techno-economic framework applicable to other unique engineering systems and geographies.

Slide 17

Life Impact | The University of Adelaide

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close