Awad Hanna - Project Tracking

Published on November 2016 | Categories: Documents | Downloads: 45 | Comments: 0 | Views: 169
of 24
Download PDF   Embed   Report

Project Tracking

Comments

Content

Project Tracking to Improve
Labor Productivity:
An Earned Value Approach
By
Awad S. Hanna, Ph.D., P.E.
Professor
University of Wisconsin-Madison
Department of Civil and Environmental
Engineering
2314 Engineering Hall, 1415 Engineering Dr.
Madison, WI, 53706
Tel (608) 263-8903
[email protected]

President
Hanna Consulting Group Inc.
1314 Farwell Drive
Madison, WI 53704
Tel (608) 246-0221
Fax (608) 246-0614

No part of this publication may be reproduced or transmitted in any form, or by any
means, without written consent from Hanna Consulting Group Inc.

©
1

Biography
Awad S. Hanna, Ph.D., P.E
Awad S. Hanna is a professor and chair of the construction engineering and management program
at the University of Wisconsin-Madison, department of Civil and Environmental Engineering.
Dr. Hanna holds M. S. and Ph.D. degrees from Penn State University and he is a register
professional engineer in the U S and Canada. Awad has been an active construction
practitioner, educator and researcher for over 30 years. He has taught construction
management courses at Penn State University, Memorial University of Newfoundland, Canada,
and University of Wisconsin-Madison. Dr. Hanna has conducted several research projects for
the Electrical Contracting Foundation including landmark studies on the cumulative impact of
change orders on electrical/mechanical labor productivity, schedule compression and
acceleration, impact of stacking of trades on labor productivity, performance evaluation for
electrical supervisors, and craftsmen, and productivity factors in electrical construction. Dr.
Hanna has conducted research for other national organizations including the National Highway
Research Program, the Mechanical Contracting Foundation, the New Horizon Foundation and
the Construction Industry Institute. Dr. Hanna has taught more than 300 successful seminars
and workshops in more than 35 states on topics such as change orders impacts, project
scheduling, estimating, labor productivity, construction delay claims.

Dr. Hanna is also a national consultant representing and assisting many contractors and owners in
productivity losses related to change orders, acceleration and compression, delay, and trade
stacking.

Prof. Awad Hanna

©
2

Why Track Labor Productivity?

Ross Umentum

©
3

Productivity Improvement
y

What can’t be measured
can’t be improved

Ross Umentum

©
4

Learning Objectives
1.

Accurately measure physical project
percent complete in real time

2.

Measure project performance every
reporting period. “Performance Factor”

3.

Predict project outcomes as early as 20-25%
project complete

4.

Identify problem areas and activities

Ross Umentum

©
5

Objectives (Continued)
5.

Establish and validate Hanna’s Control Points

6.

Track change orders and quantify impact

7.

Track Project Schedule

8.

Analysis of trends

9.

Project ratios analysis (Apprentice/Journeyman
ratio)

10. Track a variety of actual mechanical/SM
construction projects

Ross Umentum

©
6

Productivity Analysis
Selected
Selected Activity
Activity
In
In Progress
Progress

Work
Work hours
hours

Quantities
Quantities

Productivity
Productivity
Calculations
Calculations

Performance
Performance
Evaluation
Evaluation

Workhour
Workhour
Forecast
Forecast

Analysis
Analysis of
of
Trends
Trends

Prof Awad S. Hanna

©
7

Estimate Activity Percent Complete
(Output)
1)

Subjective Evaluation (Observed)

2)

Quantity Installed as Measured

3)

Binary Approach

4)

Partial Complete Method
Ductwork Installation% of Work
Detailing/Coordination

15%

Hanger Installation

15%

Duct Rough-In

50%

Finish and Trim Work20%
TOTAL

100%

Ross Umentum

©
8

Earned Value Fundamentals

Earned Hours = Qty(Installed)x(Estimated Production Rate
Earned Hours=Qty(Installed)/Qty(Estimated)xBase
Hours(Estimated)
Or

Earned Hours=Base Hours(Estimated) x Percent Complete

Prof. Awad Hanna

9

©

Develop Work Breakdown
Structure

HVAC
DUCTS

Erected

Connected

Accepted

Phase Breakdown
Area Breakdown

Hanna 2004
Prof. Awad Hanna

©

10

Set up The Earned Value Spread Sheet
Code

Description

Base % Complete
Hr

Earned

Actual

Total Estimated Hours

Prof. Awad Hanna

©

11

Simplified Earned Value Example
(1)
Activity

(2)
Budgeted
Hours

(3)
Percent
Complete

(4)
Earned
Hours

(5)
Actual
Hours

(6)
Activity
Performanc
e Factor

Ductwork 1st Floor Area A

973

78%

759

867

0.88

Ductwork 1st Floor Area B

821

59%

484

579

0.84

Ductwork 2nd Floor Area A

325

30%

98

65

1.50

Ductwork 2nd Floor Area B

151

15%

23

15

1.51

Piping 1st Floor Area A

383

100%

383

366

1.05

Piping 1st Floor Area B

574

40%

230

248

0.93

Piping 2nd Floor Area A

456

5%

23

23

0.99

Piping 2nd Floor Area B

195

0%

0

0

N/A

AHU on 2nd Floor

160

35%

56

65

0.86

Grilles/Flex

240

25%

60

55

1.09

VAV's

38

50%

19

24

0.79

Linear Diffusers 1st Floor

75

95%

71

85

0.84

Linear Diffusers 2nd Floor

58

0%

0

0

N/A

Misc. Metal Install

20

25%

5

5

1.00

Set Equipment

54

30%

16

12

1.35

4523

49%

2226

2409

0.92

PROJECT TOTALS

Ross Umentum

©

12

Example (Continued)
Job % Complete = Σ Earned = 2226 = 0.492
Σ Base
4523
Performance Factor =

Σ Earned = 2226 = 0.92
Σ Actual 2409

Predicted Hrs at Comp. = Hrs-to-date = 2409 = 4896
Job % Comp. 0.492
4896 > 4523, therefore cost overrun to date.

Ross Umentum

©

13

Typical Performance Factor Curve

1.0

25%

50%

75%

100%

% Complete

Ross Umentum

©

14

Examples: Case Studies
y

Example 3 Projects Tracked
- See below for summary of completed case studies
Project Item

Case Study #1

Case Study #2

Case Study #3

Type of Work

Mechanical

Architectural
Sheet Metal

Sheet Metal

Project Size (Man-hours)

13,731

15,268

7,344

Project Duration (Weeks)

17

29

37

Project Location

Lower Midwest

Western US

Upper Midwest

Final Labor Status

Under by 371 hrs. Over by 1,159 hrs. Under by 923 hrs.

Final Schedule Status

Behind by 2 wks Behind by 12 wks. Ahead by 13 wks.

Ross Umentum

©

15

Contractor Input Worksheet

Ross Umentum

©

16

Quantity Installed Worksheet

Ross Umentum

©

17

Method Summary Worksheet

Ross Umentum

©

18

Performance Factors: Quantity
Installed
Project Performance Factors for Quantity Installed Method

1.30

1.27
1.19

1.18

1.20

1.19

1.17

1.15

Performance Factor

1.15
1.14
1.10
1.06

1.04

1.06

1.08

1.05

1.13

1.12

1.14

1.01

1.00

1.03

1.00
0.95

0.95

0.93

0.87

0.75

20%

0.92

Case Study #1
Case Study #2
Case Study #3
Planned Productivity

0.80

10%

0.94

0.94

0.93

0.90

0.70
0%

0.95

0.99

30%

40%

50%

60%

Percent Complete

70%

Ross Umentum

80%

90%

100%

©

19

Performance Factors: Subjective
Evaluation
Project Performance Factors for Subject Evaluation Method
1.30
1.26

1.29
1.26

1.20

1.16

1.21

1.13

Performance Factor

1.18
1.10

1.07
1.02

1.07

0.98

1.00

0.96

0.96

0.97

0.88

0.98
0.96

0.92

0.88

20%

30%

40%

1.03
0.94

0.94

0.92

0.95

Case Study #1
Case Study #2
Case Study #3
Planned Productivity

0.80

10%

1.02

0.99

0.92

0.92

0.90

0.70
0%

1.13

50%

60%

Percent Complete

70%

Ross Umentum

80%

90%

100%

©

20

Forecast Error: Quantity Installed
Man-Hour Forecast Error Against Actual Final Man-Hours

15%

11.0%
10%

Forecast Error

7.5%

6.1%

9.3%

5.7%
4.1%

5%

5.2%

3.6%
4.4%

3.2%

2.0%

1.8%

0%

0.0%
-0.2%

-0.8%

-3.3%

-2.7%

-2.7%

-5%
-7.2%

-4.5%

-5.5%
-6.0%

Case Study #1
Case Study #2
Case Study #3
Zero Error

-10%
-12.7%
-15%
0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Percent Complete

Ross Umentum

©

21

Forecast Error: Subjective Evaluation
Man-Hour Forecast Error Against Actual Final Man-Hours

10%
7.5%

5.9%

6.0%

5%
2.8%
2.2%

Forecast Error

0.3%

0.5%

2.4%

-2.7%

-2.3%

0.0%

-0.4%

0%
-3.2%

2.9%

3.7%

-2.8%

-1.4%

-0.7%

-2.3%

-5%

-4.5%
-5.6%

-5.5%

-6.6%
-10%

Case Study #1
Case Study #2
Case Study #3
Zero Error

-11.2%
-12.6%
-15%
0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Percent Complete

Ross Umentum

©

22

Project Tracking Benefits
y

Early Warning Signs of Labor and/or Schedule Over-runs

y

Identification of Underproductive Activities

y

Preparation of Future Estimates

y

Proving Construction Inefficiency Claims

Ross Umentum

©

23

Major Conclusions
y

The Project Performance Factor does not vary by
more than 10% at the 30% project completion mark.

y

The Quantity Installed and Subjective Evaluation
Method have a man-hour forecast error of less than
10% for the entire project duration.

y

The linear regressed man-hour forecasts become
useful (accurate) after 25% project complete.

Ross Umentum

©

24

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close