Boiler Erection

Date: 13/01/2007

By Surendra Singh Kushwaha

 

BOILER ERECTION •  Column erection •  Pressure part erection •  Miscellaneous

 

COLUMN ERECTION • The boiler presently in use are hanging type. • The column are broken up during manufacture into several pieces and transported to site • Where it is pre assembled in two or three pieces and erected. • Utmost care is taken in the pre-assembly stage to maintain the matching of the of the column end faces and to achieve vertically well within the tolerance limit  

COLUMN ERECTION

• Verticality is single most important factor and is given top priority • The maximum column verticality is 20mm. • Once the column erection is over up to the full height cross beams are placed securely over the column which supports the main boiler

 

COLUMN ERECTION

• In order to carry out this job special erection tool like cranes with extra long boom to carry heavy loads at that height are used. •  After cross beam erection, entire structure structure is adequately braced to achieve sufficient strength.

 

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close