COMPETENCY BASED LEARNING MATERIAL

Sector: Qualification:

CONSTRUCTION PLUMBING NC II

Unit of Competency:

Prepare Pipe for Installation
Module Title:

Preparing Pipe for Installation
Institution:

PTC MALILIPOT Basud, Malilipot Albay
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

PTC MALILIPOT

Prepare Pipe for Installation

Page 1 of 75

NATIONAL CERTIFICATE LEVEL II
QUALIFICATION LEVEL

COMPETENCY-BASED LEARNING MATERIALS
No. 1. Basic Competencies Module Title Code

Participate in workplace communication Work in a team environment Practice career professionalism Practice occupational health and safety procedures
Common Competencies

1. Participating in workplace communication 2. Working in a team environment 3. Practicing career professionalism 4. Practicing occupational health and safety procedures
Module Title

500311105 500311106 500311107 500311108
Code

2. 3. 4.

No. 1.

Prepare construction materials and tools Observe procedures, specifications and manuals of instruction Perform mensuration and calculations Maintain tools and equipment
Core Competencies

1. Preparing construction materials and tools 2. Observing procedures, specifications and manuals of instruction 3. Performing mensuration and calculations 4. Maintaining tools and equipment
Module Title

CON931201 CON311201

2.

3.

CON311203 CON311204
Code

4.

No. 1. 2.

Prepare pipes for installation Make piping joints and connections Perform minor construction works Perform single unit plumbing installation and assemblies Perform plumbing repair and maintenance works Conduct pipe leak testing

1. Preparing pipes for installation 2. Making piping joints and connections 3. Performing minor construction works 4. Performing single unit plumbing installation and assemblies 5. Performing plumbing repair and maintenance works 6. Conducting pipe leak testing

CON713301 CON713302 CON713303 CON713304 CON713305 CON713306

3.

4.

5.

6.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 2 of 75

HOW TO USE THIS COMPETENCY BASED LEARNING MATERIAL
Welcome to the module in Prepare Pipes for Installation. This module contains training materials and activities for you to complete.
The unit of competency “Preparing Pipes for Installation” contains knowledge, skills and attitudes required for Plumbing. It is one of the core

competencies at National Certificate level II (NCII). You are required to go through a series of learning activities in order to complete each learning outcome of the module. In each learning outcome are Information Sheets and Instruction Sheets (Reference Materials for further reading to help you better understand the required activities.) Follow these activities on your own and answer the self-check at the end of each learning outcome. You may remove a blank answer sheet at the end of each module (or get one from your facilitator/trainer) to write your answers for each self-check. If you have questions, don’t hesitate to ask your facilitator for assistance. Recognition of Prior Learning (RPL) You may already have some or most of the knowledge and skills covered in this learner’s guide because you have:   been working for some time Already completed training in this area.

If you can demonstrate to your trainer that you are competent in a particular skill or skills, talk to him/her about having them formally recognized so you don’t have to do the same training again. If you have a qualification or Certificate of Competency from previous training, show it to your trainer. If the skills you acquired are still current and relevant to the unit/s of competency they may become part of the evidence you can present for RPL. If you are not sure about the currency of your skills, discuss this with your trainer. At the end of this module is a Learner’s Diary. Use this diary to record important dates, jobs undertaken and other workplace events that will assist you in providing further details to your trainer or assessor. A Record of Achievement is also provided for your trainer to complete once you complete the module.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 3 of 75

This module was prepared to help you achieve the required competency, in Prepare Pipes for Installation. This will be the source of information for you to acquire knowledge and skills into this particular trade independently and at your own pace, with minimum supervision or help from your instructor.
Remember to:

 

Talk to your trainer and agree on how you will both organize the Training of this unit. Read through the module carefully. It is divided into sections, which cover all the skills, and knowledge you need to successfully complete this module. Work through all the information and complete the activities in each section. Read information sheets and complete the self-check. Suggested references are included to supplement the materials provided in this module. Most probably your trainer will also be your supervisor or manager. He / She is there to support you and show you the correct way to do things. Your trainer will tell you about the important things you need to consider when you are completing activities and it is important that you listen and take notes. You will be given plenty of opportunity to ask questions and practice on the job. Make sure you practice your new skills during regular work shifts. This way you will improve both your speed and memory and also your confidence. Talk to more experienced workmates and ask for their guidance. Use the self-check questions at the end of each section to test your own progress. When you are ready, ask your trainer to watch you perform the activities outlined in this module.
Prepare Pipe for Installation
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

 





 

  

PTC MALILIPOT

Page 4 of 75

 

As you work through the activities, ask for written feedback on your progress. Your trainer keeps feedback/pre-assessment reports for this reason. When you have successfully completed each element, ask your trainer to mark on the reports that you are ready for assessment.

When you feel confident that you have had sufficient practice, ask your Trainer to evaluate you. The results of your assessment will be recorded in your Progress Chart and Accomplishment Chart.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 5 of 75

MODULE CONTENT
UNIT OF COMPETENCY: MODULE TITLE: MODULE DESCRIPTOR: PREPARE PIPE FOR INSTALLATION PREPARING PIPE FOR INSTALLATION This module includes the competencies required to identify and select materials, tools and equipment and to cut and thread pipes. 20 HOURS

NOMINAL DURATION:

MODULE DISCRIPTOR: This unit covers the knowledge, skills and attitudes in the preparation of pipes prior to installation except copper pipe. LEARNING OUTCOMES: Upon completion of this module, the trainee/student must be able to: 1. Identify and select materials, tools and equipment

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 6 of 75

COMPETENCY SUMMARY
Qualification Title : CERTIFICATE LEVEL : UNIT OF COMPETENCY: MODULE TITLE : NOMINAL DURATION : Plumbing NC II NC II Prepare Pipe for Installation Preparing Pipe for Installation 20 hrs

INTRODUCTION: This module contains information and suggested learning activities on preparing pipe for installation. It includes instructions on how to interpret plumbing plan, select plumbing materials for installation, identify and explain the different tools and equipment and their uses, and the OH & S of safe handling of hand tools. Completion of this module will help you in the understanding of succeeding modules on making piping joints and connections. This module consists of one (1) learning outcome and four (4) learning content that contains learning activities for both knowledge and skills, supported with information sheets, self-check activities and task/job sheets, and gathered from different sources. Before you perform the manual exercises, read the information/operation sheet and answer the self-activities provided to ascertain to yourself and your instructor that you are equipped with the knowledge necessary to perform the skill portion of the particular learning outcomes. Upon completion of this module, please report to your instructor for assessment to check your understanding of the knowledge and skills requirements of this module. If you pass the assessment, let your trainer mark competent on your Trainees Record Book (TRB) and you will be given a certificate of completion. SUMMARY OF LEARNING OUTCOMES LEARNING OUTCOME 1. Identify and select materials, tools and equipment

CONTENTS: 1. 2. 3. 4.
PTC MALILIPOT

Plumbing blue print reading Plumbing materials and their uses Plumbing tools and equipment and their uses and function Safety handling of Plumbing hand tools and equipment
Prepare Pipe for Installation
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

Page 7 of 75

ASSESSMENT CRITERIA: 1. 2. 3. Work instructions are read and interpreted in accordance with job requirements Materials, tools and equipment are selected and prepared according to job requirements Appropriate PPE is selected according to job requirements

ASSESSMENT METHOD 1. 2. 3. 4. 5. Practical Demonstration Interview Written Test Direct observation Portfolio

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 8 of 75

LO 1.IDENTIFY AND SELECT MATERIALS, TOOLS AND EQUIPMENT CONTENTS: 1. 2. 3. 4. Plumbing blue print reading Plumbing materials and their uses Plumbing tools and equipment and their uses and function Safety handling of Plumbing hand tools and equipment

ASSESSMENT CRITERIA: 1. Work instructions are read and interpreted in accordance with job requirements 2. Materials, tools and equipment are selected and prepared according to job requirements 3. Appropriate PPE is selected according to job requirements CONDITIONS: Students /trainees must be provided with the following: PPE Blue print or Building Plan/ working layout plan Plumbing tools and equipment Manufacturer operating procedure manual List of Plumbing materials and Checklist

METHODOLOGIES: Interactive discussion Self-paced instruction Demonstration ASSESSMENT METHODS: Interview Written examination Practical demonstration Direct observation
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

PTC MALILIPOT

Prepare Pipe for Installation

Page 9 of 75

Learning Experiences Learning Outcome No. 1 Identify and select materials, tools and equipment Learning Activities Special Instructions Read Information Sheet 1.1-1a on Give emphasis on the different Plumbing Blue Print Reading plumbing symbols and abbreviations Answer Self Check 1.1-1a Read Information Sheet 1.1-1b on Interpreting Plumbing Layout Plan Perform Task Sheet 1.1-1b on interpreting plumbing layout plan Read Information Sheet 1.1-2a on Plumbing Materials specification and uses Answer Self Check 1.1-2a Read Information Sheet 1.1-2b on Plumbing fittings Answer Self check 1.1-2b Perform Task Sheet 1.1-2b Read Information Sheet 1.1-3 on Plumbing Tools and Equipment’s for installation Answer Self Check 1.1-3 View slide presentation or visit www.plumbinghelp.ca Perform Task Sheet 1.1-3 on Tools and equipment identification Compare to answer key 1.1-1a Interpret Plumbing Drawings Evaluate using performance criteria checklist 1.1-1b Take time to understand especially the materials specification and uses Compare to answer key 1.1-2a Describe plumbing fittings and identify its uses Compare to answer key 1.1-2b Evaluate using performance criteria checklist 1.1-2b Identify different plumbing tools and equipment and their uses in installation Compare to answer key 1.1-3 Familiarize plumbing tools and category With a partner and using the Performance Criteria Checklist 1.1-3 evaluate your performance

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 10 of 75

Read Information Sheet 1.1-4 on Hand Give emphasis especially on Safety and Power tools Safety reminder on handling hand and power tools Answer Self Check1.1-4 Compare to answer key 1.1-4

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 11 of 75

Information Sheet No. 1.1-1a Plumbing Blue Print Reading
Learning Objectives: After reading this INFORMATION SHEET, YOU MUST be able to explain, identify standard plumbing symbols, abbreviation. INTRODUCTION In addition to practical training with tools and materials, a plumber must learn to the plumbing symbols and abbreviation. It is difficult for a plumber to make any interpretation of a plan if he/ she do not know the plumbing symbols and abbreviation indicated in the plumbing layout or print and specifications SYMBOLS AND ABBREVIATIONS A common set of symbols are used on architectural prints to represent materials, building objects, and various dimensions and locations. Piping symbols are used by architect and mechanical engineers on prints to represent plumbing fixtures and piping systems, as well as pipe fittings and valves used to construct plumbing systems. A print is a drawing showing a building structure and all of its components. Prints are also referred to as blueprints or working drawings. Specifications are written information that supplements the prints and provides additional details that could not be shown on the prints or that require additional description such as information on legal responsibilities, insurance, quality of workmanship, and other necessary details such as brands and types of plumbing fixtures and equipment. See figure 1.1

Note: Symbols and Abbreviations in plumbing trade may appear similar in other qualification but it may have different meaning and application.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 12 of 75

Figure 1.1. Shows plumbing symbols on fixtures, fittings, pipe, and valves

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 13 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 14 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 15 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 16 of 75

Plumbing Abbreviations are used on a set of prints to describe materials and processes while conserving space on the prints. Only uppercase letters are used for abbreviations on prints. Figure 1.2. Shows plumbing terms and their corresponding abbreviations. TERM Adapter Alignment Area Drain Back pressure Bathroom Bathtub Cast Iron Cast Iron Pipe Check Valve Clean out Concrete Pipe Cold Water Drinking Fountain Dishwasher Elbow Electric Water Cooler Elevation Flange Flared Floor Drain Galvanized Iron Hot Water Inside Diameter Kitchen Kitchen Sink Lavatory Manhole Manhole Cover Pipe Line Plumbing Roof Drain Sanitary Sewer Shower Shower Drain
PTC MALILIPOT

Abbreviation ADPTR ALIGN AD BP B BT CI CIP CV CO CP CW DF DW ELB EWC EL FLG FLDC FD GALVI HW ID K or KIT KS LAV MH MC PPLN PLMB RD SAN SEW SH SD
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

Prepare Pipe for Installation

Page 17 of 75

Soil Pipe Soil Stack Thread Toilet Tubing Union Urinal Vent Vent Pipe Vent Stack Washing Machine Waste Waste Pipe Waste Stack Water Water Closet Water Meter Water Heater

SP SSK THD T TBG UN UR V VP VS WM W WP WS WTR WC WM WH

Note: View slide presentation on plumbing symbols or visit www.plumbinghelp.ca for more plumbing symbols and abbreviation not indicated in the module.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 18 of 75

Self Check No. 1.1-1a
A. Identification: Identify what is described on the following:

1. A drawing showing a building structure and all of its components. 2. Written information that supplements the prints and provides additional
details that could not be shown on the prints.

3. Used on architectural prints to represent materials, building objects, and
various dimensions and locations. 4. Used on a set of prints to describe materials and processes while conserving space on the prints. Only uppercase letters are used for abbreviations on prints.

B. Matching Type: Match column A with column B. A a. Symbol 1. Tee 2. Elbow 90º 3. Wye 4. Union 5. Elbow 45º b. Abbreviation 6. Water Closet 7. Shower 8. Lavatory 9. Floor Drain 10. Urinal A. WC B. C. D. LAV E. F. UR G. SH H. I. J. FD B

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 19 of 75

Answer Key No. 3.1-1 A. Identification 1. 2. 3. 4. Prints Specifications Symbols Abbreviation

B. Matching Type 1. C 2. E 3. H 4. I 5. B 6. A 7. G 8. D 9. J 10. F

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 20 of 75

Information Sheet No. 1.1-1b Plumbing Blue Print Interpretation
Learning Objectives: After reading this INFORMATION SHEET, YOU MUST be able to interpret plumbing layout plan. INTRODUCTION Interpreting plumbing layout plan is a very critical aspect in plumbing installation. Any misinterpretation of a layout or drawing may result into back job and can contribute to the loss of materials. Schematic and Isometric Piping Drawing A plumber must develop schematic and isometric piping drawings for smaller buildings to become familiar with the lay out of the different plumbing systems. 1. Plan View shows where the plumbing fixtures and piping are to be located and as where they are to be installed.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 21 of 75

2. A schematic piping drawing, or diagrammatic piping drawing, is a drawing of piping system without regards to scale and exact location of the fixture shown on the drawing.

3. An Isometric piping drawing is a three dimensional drawing of a plumbing system.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 22 of 75

Self Check No. 1.1-1a
Identification: Identify what is described on the following:

1. Shows where the plumbing fixtures and piping are to be located and as where they are to be installed. 2. Is a drawing of piping system without regards to scale and exact location of the fixture shown on the drawing. 3. A three dimensional drawing of a plumbing system.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 23 of 75

Answer Key No. 1.1-1 Identification

1. Plan View 2. Schematic Drawing 3. Isometric Drawing

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 24 of 75

Task Sheet No. 1.1-1 Interpret Plumbing Layout Plan Title: Interpreting Plumbing Layout Plan

Performance Objectives: Given the plumbing layout plan the trainee should be able to interpret the plan and a make list of the standard plumbing symbols and abbreviation indicated on the plan. Supplies and Materials: Plumbing Layout Plan, Performance Criteria Check List Steps: 1. Secure Plumbing layout plan at the learning resource area. 2. Make a list of different plumbing symbols and abbreviation indicated. 3. Interpret the plumbing layout plan. 4. Check your work against the Performance Criteria Checklist with your trainer. 5. Present your work to your Trainer for evaluation. Assessment Method: Evaluation of finished output, Performance Criteria Checklist

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 25 of 75

Performance Criteria Checklist Task Sheet 1.1-1 Trainees Name ______________________________ Date: _________ CRITERIA Did the trainee … 1. Secured plumbing layout plan? 2. List down plumbing symbols indicated in the plumbing layout plan. 3. Identified / interpret correctly the following symbols and abbreviation: A. Symbol Tee Union Elbow 90˚ Wye P-trap Elbow 45˚ Sanitary Tee Clean out Vent pipe Waste pipe Cold Water Supply Hot Water Supply Valve B. Abbreviation Water Closet Lavatory Shower Floor Drain Vent thru roof 4. Was the trainee’s performance achieved the criteria given? YES NO

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 26 of 75

Information Sheet No. 1.1-2a
Plumbing Materials LEARNING OBJECTIVES: After reading this INFORMATION SHEET, YOU MUST be able to identify and select plumbing materials needed in a specific job. INTRODUCTION: Plumbing as defined as the installation of pipes, fitting, fixtures and other apparatus in conveying and supplying water into different parts of the building and to dispose and discharge waste water and other substances out of the building. This module tackles about the different plumbing materials those plumbing codes permit to use. PLUMBING MATERIALS KINDS/ TYPES AND CLASSIFICATION The Revised Plumbing Code of the Philippines specifies the type of piping materials that may be used for each plumbing system. Plumbing code bases of selecting materials are the soil types, ground condition, local rainfall and frost or freezing conditions. Consult the plumbing code to ensure that only codeapprove material is being used for plumbing system. Pipe is a cylindrical tube used for conveying potable water, wastewater, waterborne waste, and air from one location to another. There are numerous kinds of pipes available for plumbing installation but so far, the most popular and commonly used are: Note: Refer to the Revised Plumbing Code of the Philippines found at the learning resource area for the materials approve by the code. 1. PLASTIC PIPE  Characteristics: – Low Initial Cost – Ease Of Assembly – Lightweight – Corrosion Resistant – Low friction loss – Fire resistant – Maintenance free A. Types of Plastic Pipe
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 27 of 75

ABS (Acrylonitrite-ButedieneStyrene) • Uses: – Sanitary Drainage – Vent Piping – Storm Water Drainage Size Availability: – 11/4- 6 inch diameter – 10 ft or 20 ft. lengths



PVC (Polyvinyl Chloride) • Uses: – Cold water lines – Drains – Irrigation • Size Availability: – 1/2” to 4” diameter – 10 and 20 ft. lengths

CPVC (Chlorinated Polyvinyl Chloride) • Uses: – Cold and hot water lines – High temperature and pressure lines • Size Availability: – 1/2” ND 3/4” diameter – 10 ft. lengths
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

PTC MALILIPOT

Prepare Pipe for Installation

Page 28 of 75

PE ( Polyethelyne) Underground water service Size Availability: – 3/4 to 2” diameter – 100 ft. coils –



2. COPPER PIPE  Characteristics: – Resists corrosion – Accepted by virtually every plumbing code – Will not burn or support combustion and decompose to toxic gases – Easy to join – Easily formable – Lightweight – Economical

A. TYPES OF COPPER PIPE TYPE K (GREEN) • Uses: – Domestic water – Service and distribution – Fire protection – Solar – Fuel/fuel oil – HVAC • Available Sizes: – Straight lengths: ¼’’ to 8’’ 20 ft. – Coils: ¼’’ to 1’’ - 100 ft.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 29 of 75

TYPE L (Blue) • Uses: – Domestic water – Service and distribution – Fire protection – Solar – Fuel/fuel oil – Liquefied petroleum (LP) gas – HVAC – Snow melting • Size Availability: – Straight lengths: ¼’’ to 8’’ 20 ft. – Coils: ¼’’ to 1’’ – 100 ft.

TYPE M (Red) • USES:  Domestic water  Service and distribution  Fire protection  Solar  Fuel/fuel oil  Liquefied petroleum (LP) gas  HVAC  Snow melting • Size Availability:  Straight lengths: ¼’’ to 12’’- 20 ft  No coils

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 30 of 75

DMV (Yellow) • Uses:



– Drain – Waste – Vent – Solar – HVAC Size Availability: – Straight lengths: 1¼’’ to 8’’- 20 ft. – No coils

3. MALLEABLE IRON PIPE  Characteristics: – strong – susceptible to rust and corrosion – difficult to install Uses: – drain pipes – hot and cold supply Size Availability: – 1/2” to 12” diameter – 21’ lengths- cut pipe available

 

4. CASTE IRON SOIL PIPE • CHARACTERISTICS – Versatile – Adaptable for use in all types of building – Low-Cost Installation. – Cast iron soil pipe can be preassembled – Product readily available • USES – sanitary and storm drain – waste and vent piping applications • SIZE AVAILABILITY – 11/2” to 12” diameter – 5’ AND 10’ lengths
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 31 of 75

5. VITRIFIED CLAY PIPE • CHARACTERISTICS: – Life expectancy: over 100 years – Chemically inert: resistant to attack from solvents, acids, alkalis, gases, etc. – Low friction coefficient. – Structural integrity: inherent load bearing – Resistant to root penetration and leakage. – Abrasion resistance: – Handling: easy to handle and install. – Economical • USES – sanitary and storm drain – waste and vent piping applications • SIZE AVAILABILITY: – 11/2” to 12” diameter – 5’ AND 10’ lengths

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 32 of 75

Self Check No. 1.1-2a IDENTIFICATION: Identify the following the different types of pipe. Image of Pipe: Name:

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 33 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 34 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 35 of 75

Answer Key No. 1.1-2a Image of Pipe: Name: ABS (Acrylonitrite-ButedieneStyrene) PIPE

PVC (Polyvinyl Chloride) PIPE

CPVC (Chlorinated Polyvinyl) PIPE

PE ( Polyethelyne) PIPE

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 36 of 75

TYPE K (GREEN) Copper Pipe

TYPE L (Blue) Copper Pipe

TYPE M (Red) Copper Pipe

DMV (Yellow) Copper Pipe

MALLEABLE IRON PIPE

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 37 of 75

CASTE IRON SOIL PIPE

VITRIFIED CLAY PIPE

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 38 of 75

Task Sheet No. 1.1-1a Identify Plumbing materials Title: Identifying Plumbing Materials

Performance Objectives: At a given presentation the trainee should be able to correctly identify standard plumbing materials, their characteristics and uses. Supplies and Materials: Slide Presentation or Video presentation on plumbing materials Performance Criteria Check List Steps: 1. View slide or Video presentation on plumbing materials. 2. Make a list of standard plumbing material use in plumbing. 3. List down the uses and characteristics of plumbing materials. 4. Check your work against the Performance Criteria Checklist with your trainer. 5. Submit your output to your trainer for evaluation.

Assessment Method: Evaluation of finished output, Performance Criteria Checklist, Oral Questioning

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 39 of 75

Performance Criteria Checklist Task Sheet 1.1-1 Trainees Name ______________________________ Date: _________ CRITERIA Did the trainee … 1. View slide or Video presentation on plumbing materials? 2. Make a list of standard plumbing material use in plumbing? 3. List down the uses and characteristics of plumbing materials? 4. Check the work against the Performance Criteria Checklist with your trainer? 5. Submit output for evaluation? YES NO

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 40 of 75

Information Sheet No. 1.1-2b
Plumbing Fittings LEARNING OBJECTIVES: After reading this INFORMATION SHEET, YOU MUST be able to identify and select plumbing fittings needed in a specific job. INTRODUCTION: This information sheet contains standard plumbing fittings, their uses and descriptions. These fittings are essential materials in plumbing installation, without fittings it is merely impossible to connect pipes for installation. COMMON PIPE FITTINGS Plumbing installation process utilizes fittings to connect pipes. Plumbing fittings comes in different materials such as PVC, galvanize iron, cast iron, UPVC, copper and etc. Fittings have different function or purpose and uses for plumbing installation either for water supply or waste drainage system. Plumbing fittings have different shapes which allow rigid straight pipe to change both direction and diameter. Figure 2.1 Show the plumbing fitting name, description, uses and image. NAME DISCRIPTION USES IMAGE 1. ELBOW The most Used to common elbows change the come in 90 angle or degree and 45 direction of the degree turns. pipe run The sweep of the fitting describes how fast a transition or change in direction is made

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 41 of 75

2. STREET ELBOW

One end of the fitting has male threads and the other end has female threads.

Used to change short angle /direction and omit the use of nipple.

3. TEE

Shaped like the Allow for letter T. branch lines DWV tees are known as waste or sanitary T’s. PVC or G.I fitting that is inside threaded with same end size PVC or G.I fitting that is inside threaded with different end size Abrupt changes in diameter and take very little space. made in three parts consisting of a nut, a female end, and a male end Used to join two straight pieces of pipe of the same diameter Used to join pipe of different diameters Used to make the diameter of a pipe fitting smaller Used to join pieces of pipe where pipes cannot be turned or when a piece of equipment may have to be removed for maintenance or replacement.

4. COUPLING

5. REDUCER

6. BUSHING

7. UNION

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 42 of 75

8. CAPS

9. PLUG

Industrial caps can be round, square, rectangular, Ushaped, Ishaped and have a round hand grip or a flat hand grip. Have male threads. It is similar to a cap but it fits inside the fitting

Used to close the end of a dead end pipe.

Close an opening on a pipefitting normally used for inspection and cleanout Used primarily to gain inside access to DWV systems.

10. WYE

Pronounced like the letter Y and looks like letter Y

Note: View Slide Presentation on Pipe fitting or visit www.plumbinghelp.ca for other references of pipe fitting not included in this information sheet.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 43 of 75

Self Check No. 1.1-2b A. TRUE OR FALSE: Write T if the sentence is correct and F if the sentence is false. 1. 2. 3. 4. 5. Plug is used to close the opening of a pipe fitting. Union is used to join pieces of pipe where pipes cannot be turned. The fitting to be used to change short angle is coupling. Reducer is used to join pipe of different diameters. Wye is a fitting which allow for a branch, it is shape like a tee.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 44 of 75

Answer Key No. 1.1-2b A. TRUE or FALSE 1. 2. 3. 4. 5. T T F T F

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 45 of 75

Information Sheet No. 1.1-3
Plumbing Tools and Equipment’s for installation.

Learning Objectives: After reading this INFORMATION SHEET, YOU MUST be able to identify and describe plumbing tools and equipment for plumbing installation. INTRODUCTION Include in this information sheet are the different plumbing tools and equipment’s in plumbing installation. Tools are categorized in to two, the hand and power tools. Tools are also fall into different classification such as Cutting, Measuring, Holding, Driving Tools and etc. It is a must for the plumber to select properly what tools and equipment needed according to job specification. Plumbing Tools Plumbing tools fall under one of two categories: 1. Hand tools  Manually operated.  Not as expensive as power tools.  Equally important in completing a task or project.  Most employers expect a plumber to have basic hand tools when being considered for employment. See Figure 3.1 for the plumbing tools and their corresponding uses.

Name
Levels

Uses
A level has tubes partially filled with colored liquid leaving a trapped air bubble. Used to lever pipe
Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Image

PTC MALILIPOT

Prepare Pipe for Installation

Document No. Issued By: Revision #______

Page 46 of 75

Pull-Push Rule

horizontally or even finding its plumbness They vary in blade width and length. The retractable type with a pocket clip is the most common. Use to measure pipe for installation The framing square is a tool for laying out angles. It has two edges that form a 90 angle. Adjustable wrenches are available in various sizes. Some have a cushioned grip. Their jaw opening is adjustable and smooth. Use to hold pipe and fittings have grooved jaws designed to provide grip for working with metal piping systems.
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

Squares

Adjustable Wrenches

Pipe Wrenches

PTC MALILIPOT

Prepare Pipe for Installation

Page 47 of 75

Hammer

Used for driving clams and piping support in plumbing installation and use also for roughing work use to cut both ABS and PVC pipe.

Plastic pipe Saw

Hack Saw with Blade

designed to cut through metal.

Wall Board Saw

designed to cut circular holes

Chalk line or chalk box

Used to mark a straight line for layout or to cut plywood boards.

Figure 1.1-3 Shows the plumbing tools and its uses.

Note: View slide presentation or visit www. Plumbinghelp.com for additional references regarding plumbing tools and uses.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 48 of 75

Self Check No. 1.1-3 A. MATCHING TYPE Match column A with column B. A 1.

B A. Adjustable wrench

2. B. Hack Saw

3. C. Pull-Push Rule

4. D. Levels

5. E. Pipe wrench

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 49 of 75

Answer Key 1.1-3 A. MATCHING TYPE: 1. 2. 3. 4. 5. C A B E D

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 50 of 75

Task Sheet 1.1-3
Title: IDENTIFICATION OF SHOP HAND AND POWER TOOLS Performance Objectives: After completing this activity the trainee will be able correctly identify the different types of tools needed in carrying out the activity Supplies and Materials: Blank paper, ball pen Equipment: Shop hand tools Tool Identification: 1. On the table are set of different shop tools. Identify the classification of plumbing tools 2. Make a list of plumbing tools according to its classification or category. 3. Innumerate the uses of plumbing tools. 4. Get a partner and compare your list with your partner and discuss its function, operation and proper use. Use the performance checklist given to you by your trainer as your guide. 5. After completing the activity, submit the list and if ready for an assessment approach your trainer for your institutional evaluation. Assessment Method: Evaluation in correctly identifying the tools, Performance Criteria Checklist

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 51 of 75

Performance Criteria Checklist 1.1-3 SHOP HAND TOOLS IDENTIFICATION

Trainees Name ______________________________ Date: _________
CRITERIA 1. Did the trainee identify plumbing tools? 1. Hand Tools a. Striking tools 1. Rubber Mallet 2. Ballpeen Hammer 3. Sledge hammer 4. Claw Hammer b. Gripping tools /turning tools 1. wrenches a. adjustable wrench b. pipe wrench c. spud wrench d. adjustable basin wrench e. monkey wrench f. strap wrench 2. Pliers a. Diagonal Cutting Plier b. Pipe wrench c. long nose plier c. Turning tools 1. Slotted Screwdriver 2. Phillips Screwdriver 3. Wrench a. box b. Open c. Combination d. Socket d. Cutting tools 1. Hacksaw 2. Cutter 3. Tin snip 4. Cold Chisel 5. File 6. Pipe cutter 7. PVC pipe cutter 8. Cooper tubing cutter 9. Pipe burring reamer
PTC MALILIPOT

YES

NO

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 52 of 75

e. Threading tools 1. Pipe threader 2. Pipe Tap 3. Flaring tools 4. Pipe die set f. leveling/marking tools/ aligning tools 1. level bar/ spirit level 2. chalk line 3.pencil 4.plumb bob g. Measuring tools 1. Pull push rule 2. Did the trainee innumerate the uses of tools? 3. Did the trainee compare and discuss the list and uses of tools with his/ her classmate? 4. Submit the list? Submit and pass the evaluation?

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 53 of 75

Information Sheet No. 1.1-4
Hand and Power Tools safety Learning Objectives: After reading this INFORMATION SHEET, YOU MUST be able to explain, identify and perform safety handling of hand tools. INTRODUCTION: In this information sheet contains OH& S on handling both hand and power tools. One’s a plumber practice safe handling of tools he/ she can avoid accident, injury which may result into death or damage to property. On the other hand if the plumber did not practice such safety handling of tools it may have a reverse result. HAND AND POWER TOOL SAFETY Plumbing tools are classified into two; the HAND TOOLS and the POWER TOOLS. Differences between hand and power tools: – Hand tools have no power source, other than the physical force applied by the user. Hand tools include anything from axes to hammers, and screwdrivers to wrenches Power Tools require a non-human power source to function properly--e.g. External (electricity, compressed air, etc.) or Internal (battery pack, internal combustion engine, etc.).



Both kinds of tools require specific safety precautions or rules to be followed; yet some rules will apply to both.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 54 of 75

There are five basic rules that apply to all tools used either hand or power and general safety rules that govern with the use of hand tools 5 Basic Rules  Keep all tools in good working order  Use the tool only for what it is designed to do  Examine the tool for damage before each use  Always follow the manufacturer’s instructions when operating any tool  Always wear the appropriate PPE when operating any tool GENERAL “Hand Tool” SAFETY RULES  Carry all sharp tools in a holster or sheath  Tag worn, damaged or defective tools and do not use them  Do not perform “makeshift” repairs to tools  Do not use cheater bars The Greatest Hazards of Hand Tools: Misuse/Improper Maintenance  Using a screwdriver as a chisel  Could cause the tip to break and fly, hitting either the operator or bystanders  A wooden handle on tool such as a hammer or an axe is loose, splintered or cracked  The tool head could fly off and strike the operator or bystanders  Impact tools, e.g. chisels and wedges, are unsafe if their heads are “mushroomed”  The heads might shatter on impact sending sharp fragments flying  Wrenches must not be used if the jaws are sprung, cracked or twisted  The wrench could slip off

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 55 of 75

SAFETY RULES for SPECIFIC Hand Tools HAMMERS  Use a claw hammer for pulling nails  Do not strike a hardened steel surface with a claw hammer  Do not strike one hammer against another hammer  Do not use a hammer as a wedge or pry-bar

CHISELS  Use only chisels that are sharp  Do not use chisels with a mushroom head  Use only hammers that are designed for use with chisels

SAWS
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 56 of 75

 Do not carry the saw by the blade  Do not use any saw that has a dull saw blade  Keep control of the saw by releasing downward pressure at the end of each stroke

SCREWDRIVERS       Always ensure the screwdriver fits the head of the screw Do not hold the work piece against your body while using the screwdriver Do not use a screwdriver as a punch, chisel, pry bar or nail puller Do not use a screwdriver to test the charge of a battery Use blue handled screwdrivers when working on electrical Do not use a screwdriver to make a starting hole for screws

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 57 of 75

WRENCHES  Do not use wrenches that are bent, cracked, or that have loose handles  A hammer may be used for striking “face wrenches” ONLY  If at all possible use socket or box wrenches  Do not use a cheater bar

SNIPS     Wear safety glasses or goggles when using snips Wear work gloves when cutting material with snips Do not use snips as a hammer, screwdriver, wrench or pry bar Use the correct type of snips for the job

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 58 of 75

GENERAL “Power Tool” SAFETY     Do not use power tools you are not trained on Do not lift or carry power tools by their power cord Keep power cords out of the paths of the power tool Do not leave tools unattended

 Do not stand in water or wet surfaces when running a power tool  Hold all power tools by the plastic hand grips or other nonconductive areas.  Do not plug multiple electrical cords into a single outlet  Do not use power tools or extension cords with a missing prong  Ground all tools unless double insulated

Note: View slide presentation and video for safety handling of tools or visit www.plumbinghelp.ca for more references.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 59 of 75

Self Check No. 1.1-4 Safety Handling of Plumbing Tools A. Innumerate the five basic safety rules that apply both hand tools and power tools. B. Explain what will happen if the hand tools are misused or improper maintenance. Give at least one. C. TRUE or FALSE. Write TRUE if the sentence is correct and write FALSE if it is not. 1. Hand tools require a non-human power source to function properly. 2. Tagging worn, damaged or defective tools and not using them is one of the general safety rules in handling tools. 3. It is proper to strike one hammer against another hammer. 4. Use only hammers that are designed for use with chisels. 5. It is safe to use wrenches that are bent, cracked, or that have loose handles.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 60 of 75

Answer Key 1.1-4 Safe Handling of Tools 1. 5 Basic Rules  Keep all tools in good working order  Use the tool only for what it is designed to do  Examine the tool for damage before each use  Always follow the manufacturer’s instructions when operating any tool  Always wear the appropriate PPE when operating any tool 2. Explain…possible answer  Using a screwdriver as a chisel  Could cause the tip to break and fly, hitting either the operator or bystanders  A wooden handle on tool such as a hammer or an axe is loose, splintered or cracked  The tool head could fly off and strike the operator or bystanders  Impact tools, e.g. chisels and wedges, are unsafe if their heads are “mushroomed”  The heads might shatter on impact sending sharp fragments flying  Wrenches must not be used if the jaws are sprung, cracked or twisted  The wrench could slip off 3. TRUE or FALSE 1. FALSE 2. TRUE 3. FALSE 4. TRUE 5. FALSE
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 61 of 75

EVIDENCE PLAN Qualification: Unit of Competency: PLUMBING NC II Prepare Pipe for Installation

Observation & oral Questioning

Third party Report

Demonstration & Questioning

Ways in which evidence will be collected: ( tick the column)

Portfolio

The evidence must show that the trainee…  Read and interpreted work instructions according to job requirements*  Selected and used appropriate processes, tools and equipment to carry out tasks*  Selected materials in accordance with specifications and job requirements* Demonstrated compliance with safety regulations applicable to work site operations*

X

Written X X X X
Page 62 of 75

X

X



NOTE: * Critical aspects of competency Prepared By: Check By:
Prepare Pipe for Installation
Date Developed: Jan.2012 Developed by: Efren G. Gayanes

EFREN G. GAYANES TRAINER

Date: Date:

Document No. Issued By: Revision #______

PTC MALILIPOT

ASSESSMENT TOOLS Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency: LO 1: Task: Your task is to:  Select the letter that best answer to the questions. Question to prove the candidate’s underpinning knowledge. 1. What would you do if the plan given to you does not fit with the actual site situation? A. Ask the supervisor or foreman for further revision B. Implement the plan regardless of discrepancy of the plan. C. Revise the plan without consulting the supervisor. D. All of the above. 2. What would you do in case the structural portion of the building is to be affected by your piping lay out? A. Revise the piping lay out. B. Coordinate your work with the structural designer or engineer and secure approval before going work. C. Implement the plan. D. Ask approval from the owner. 3. What are the tools and equipment needed in preparing pipe for installation? A. Hack Saw, Pull-Push ,Pipe Threader B. Try, Square, C. Welding Machine, plier D. Tester, heater 4. What are the materials needed in preparing pipe for installation. A. PVC,GI, Cast Iron pipe B. Wire, gloves C. Welding rod, angle bar
PTC MALILIPOT

EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION IDENTIFY AND SELECT MATERIALS,TOOLS AND EQUIPMENT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 63 of 75

D. None of the above 5. What would you do if the tools or equipment being used suddenly broke down? A. Stop the task and check the tools or equipment and report it to your immediate supervisor. B. Stop the task and go home C. Ask for replacement D. All of the above

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 64 of 75

Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency: LO 1:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION IDENTIFY AND SELECT MATERIALS,TOOLS AND EQUIPMENT

Task to prove the candidate’s underpinning knowledge and skills. A. Interpreting Plumbing Layout Plan Performance Objectives: Given the plumbing layout plan the trainee should be able to interpret the plan and a make list of the standard plumbing symbols and abbreviation indicated on the plan and make a simple plumbing layout or sketch plan. Supplies and Materials: Plumbing Layout Plan, Performance Criteria Check List Steps: 1. Secure Plumbing layout plan at the learning resource area. 2. Make a list of different plumbing symbols and abbreviation indicated. 3. Interpret the plumbing layout plan. 4. Make a simple plumbing lay out plan or sketch plan. 5. Check your work against the Performance Criteria Checklist with your trainer. 6. Present your work to your Trainer for evaluation. Assessment Method:
Date Developed: Jan.2012 Developed by: Efren G. Gayanes Document No. Issued By: Revision #______

PTC MALILIPOT

Prepare Pipe for Installation

Page 65 of 75

Evaluation of finished output, Oral Questioning

Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency: LO 1:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION IDENTIFY AND SELECT MATERIALS,TOOLS AND EQUIPMENT

Task to prove the candidate’s underpinning knowledge and skills. B. Identifying Plumbing Materials Performance Objectives: At a given presentation the trainee should be able to correctly identify standard plumbing materials, their characteristics and uses. Supplies and Materials: Slide Presentation or Video presentation on plumbing materials Performance Criteria Check List Steps: 1. View slide or Video presentation on plumbing materials. 2. Make a list of standard plumbing material use in plumbing. 3. List down the uses and characteristics of plumbing materials. 4. Check your work against the Performance Criteria Checklist with your trainer. 5. Submit your output to your trainer for evaluation.

Assessment Method:
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 66 of 75

Evaluation of finished output, Oral Questioning

Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency: LO 1:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION IDENTIFY AND SELECT MATERIALS,TOOLS AND EQUIPMENT

Task to prove the candidate’s underpinning knowledge and skills. C. IDENTIFICATION OF SHOP HAND AND POWER TOOLS Performance Objectives: After completing this activity the trainee will be able correctly identify the different types of tools needed in carrying out the activity Supplies and Materials: Blank paper, ball pen Equipment: Shop hand tools Tool Identification: 1. On the table are set of different shop tools. Identify the classification of plumbing tools 2. Make a list of plumbing tools according to its classification or category. 3. Innumerate the uses of plumbing tools. 4. Get a partner and compare your list with your partner and discuss its function, operation and proper use. Use the performance checklist given to you by your trainer as your guide. 5. After completing the activity, submit the list and if ready for an assessment approach your trainer for your institutional evaluation. Assessment Method: Evaluation in correctly identifying the tools, Oral Questioning.
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 67 of 75

Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency: LO 1:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION IDENTIFY AND SELECT MATERIALS,TOOLS AND EQUIPMENT

Oral question to prove the candidate’s underpinning knowledge and skills.

1. What would you do if you cannot read and interpret complex blue print plan? 2. What would happen if you did not use the plan for your piping installation work? 3. What if you used PVC pipes instead of steel pipe passing thru the structural portion of the building? 4. What would you do if the tools needed for the task is not available or not functional. 5. Why you should not let the tools merge with the other tools?

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 68 of 75

COMPETENCY ASSESSMENT TOOL ANSWER KEY A. Question to prove the candidate’s underpinning knowledge. 1. What would you do if the plan given to you does not fit with the actual site situation? A. Ask the supervisor or foreman for further revision B. Implement the plan regardless of discrepancy of the plan. C. Revise the plan without consulting the supervisor. D. All of the above. 2. What would you do in case the structural portion of the building is to be affected by your piping lay out? Revise the piping lay out. A. Coordinate your work with the structural designer or engineer and secure approval before going work. B. Implement the plan. C. Ask approval from the owner. 3. What are the tools and equipment needed in preparing pipe for installation? A. Hack Saw, Pull-Push ,Pipe Threader B. Try, Square, C. Welding Machine, plier D. Tester, heater 4. What are the materials needed in preparing pipe for installation. A. PVC,GI, Cast Iron pipe B. Wire, gloves C. Welding rod, angle bar D. None of the above 5. What would you do if the tools or equipment being used suddenly broke down? A. Stop the task and check the tools or equipment and report it to your immediate supervisor. B. Stop the task and go home C. Ask for replacement D. All of the above

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 69 of 75

Observation and Questioning Checklist Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION

Instructions for the teacher:
1. Observe the student how to prepare pipe for installation. 2. Describe the assessment activity and the date on which it was undertaken. 3. Place a tick in the box to show that the student completed each aspect of the activity to the standard expected in the enterprise. 4. Ask the student a selection of the questions from the attached list to confirm his/her underpinning knowledge 5. Place a tick in the box to show that the student answered the questions correctly. 6. Complete the feedback sections of the form. Date of observation Description of assessment activity Location of assessment activity The student….  Secured and interpret plumbing layout plan* If yes, tick the box After the activity the trainee will rate either




Make a list of different plumbing symbols and abbreviation indicated* Make a simple plumbing lay out plan or sketch plan* Identify and select plumbing materials in line with job requirements and according to safety practices.* Identify and select plumbing tools and equipment.* Innumerate uses of plumbing tools. Use PPE in line with job requirements*
Yes No

   

Did the student’s overall performance meet the standard?
Date Developed: Jan.2012 Developed by: Efren G. Gayanes

PTC MALILIPOT

Prepare Pipe for Installation

Document No. Issued By: Revision #______

Page 70 of 75

Student’s name: Teacher’s name: Name of School: Qualification: Unit of competency:
EFREN G. GAYANES TESDA-PTC MALILIPOT PLUMBING NC II PREPARE PIPE FOR INSTALLATION

Instructions for the teacher: Oral question to prove the candidate’s underpinning knowledge and skills. Answer: 1. What would you do if you cannot read and interpret complex blue print plan? Answer: (a) I will ask my immediate superior to guide and assist me. (b) I will honestly tell my superior that I could only understand and interpret simple drawing. 2. What would happen if you did not use the plan for your piping installation work? Answer: The output may not be standard and not in accordance with owners specification. It may cause great loss of material and back job. 3. What if you used PVC pipes instead of steel pipe passing thru the structural portion of the building? Answer: Knowing the situation, inform your immediate superior and ask him to request for an approval of materials to be used for that particular location. 4. What would you do if the tools needed for the task is not available or not functional. Answer: Report to your superior about the situation and request for the needed tools required for the specific task or job. 5. Why you should not let the tools merge with the other tools? Answer: It may result to damage of tools. It is difficult to secure needed tools within given time. It may cause accident while searching for the tools needed.
PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 71 of 75

INENTORY OF TOOLS, MATERIALS, EQUIPMENT AND FACILITIES SECTOR: CONSTRUCTION QUALIFICATION: PLUMBING NC II NOMINAL DURATION: 258hrs COMPETENCY BASIC COMMON CORE 1. PREPARE PIPE FOR INSTALLATION 1.1 Prepare 1.CBLM 1.PPT on materials, tools 2.Handout on plumbing and equipment. plumbing blue print materials reading ( 2) 3.Handouts pcs on plumbing 2. PPT on tools Plumbing 4.Handouts Materials on 3.PPT on 5.Handouts Plumbing on Safety tools and handling of equipment tools 4. PPT on 6. PPE Plumbing pictures Safety 7.Tarpualin handling of on plumbing Tools and fittings, Equipment materials, 6. Video file and tools on Safety 8. Plumbing handling of Design and Tools and estimate by Equipment Max Fajardo 7. Video on PPE PRINT MATERIALS NON-PRINT MATERIALS TOOLS EQUIPMENT

1.Cutting Tools(10 pcs) 2.Threading tools (5pcs) 3. Reaming Tools (2pcs) 4.Measuring tools (15pcs) 5. Marking Tools ( 10 pcs)

1. Pipe cutter 2.Grinder 3.Threading Machine (to be purchase) 4.Working Table ( 5pcs) 5. Training Mock up (7pcs) 6. Portable Foldable Pipe vise Tri pod(1pc)

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 72 of 75

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 73 of 75

Definition of Terms
Conveying It refers to flow or movement and the process of supplying water to the building. Fittings Device fastened to the end of pipes to make connections between individual pipes. Drainage System System include, all piping within the public or private premises that conveys sewage, rainwater or other liquid waste, to a legal point of disposal. Plumbing Fixtures Are installed receptacles, devices, or appliances which are supplied with water, or which receives or discharge liquid waste to a drainage system. Plumbing System System includes the water supply distribution pipes, plumbing fixtures and traps; soil, waste, and vent pipes. Waste pipe Is a pipe that conveys liquid waste from fixture that is free of fecal matter. Water Service Pipe Is the pipe from the water main or other source of water supply to the building served. Water supply system The water supply of a building or premises consist of the water service pipes, the water distributing pipes, and all necessary connecting pipes, fittings, control valves and all appurtenances in or adjacent to the building or premise.

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 74 of 75

REFERENCES AND FURTHER READING

1. Max B. Fajardo Jr. Plumbing Design and Estimate second edition. 2001 2. L.V. Ripka.Plumbing Design and Installation. Third Edition.atp publication, INC, Homewood, Illinois 60430-4600 3. Revised Plumbing Code of the Philippines

PTC MALILIPOT

Prepare Pipe for Installation

Date Developed: Jan.2012 Developed by: Efren G. Gayanes

Document No. Issued By: Revision #______

Page 75 of 75

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close