04 MAY 07

EDGE 2007
BSCs

25 20 15 10 5 0 10 24 11

7 Karachi Alcatel Pending Planned Done

Islamabad

Lahore

Karachi Motorola

Total
Islamabad Lahore Karachi Motorola Karachi Alcatel TOTAL 10 24 11 7 52

Done
10 24 11 7 52

Planned
0 0 0 0 0

Pending
0 0 0 0 0

HIGH LIGHTS - BSCs
Islamabad
All BSCs succesfully processed for EDGE cutovers.

Lahore
All BSCs succesfully processed for EDGE cutovers.

Karachi
All BSCs succesfully processed for EDGE cutovers.

CELL SITES - Expansion & Activation
100 80 60 40 20 2 0 Islamabad 1 Lahore 0 16 0 Karachi Motorola 1 0 Karachi Alcatel 0 61 61 43 43 43 43 Expansions Done EDGE Activated Expansion Planned Expansion Pending 99 99

TOTAL

Expansion done
61 99 43 43 246

EDGE activation
61 99 43 43 246

Planned Expansions
2 0 0 0 2

Pending for misc reasons
1 16 1 0 18

Islamabad 64 Lahore 115 Karachi Motorola 44 Karachi Alcatel 43 TOTAL 266 Note: in Karachi - Count is for the sites having EDGE cells only.

HIGH LIGHTS - Cell sites
Islamabad
2 planned and to be completed before next week end and 1 pending at Egyptian Embassy because of access issue for which the authorities have declined.

Lahore
16 PENDING ACTIVITIES BREAKDOWN 12 for hardware shortages at deployments end i.e. OD cabinets 3 are pending for Acquisition related issues - For two NOC from HQ 4 Core is required and third is expected to be cleared by Monday. 1 site is pending at TXN's end.

Karachi - Motorola
Last activity is at SHERATON, under process for Access permissions

Karachi - Alcatel
All done

PM - TEHCNICAL

Confidential & Proprietary

1/1

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close