QUALITY CONTROL CHECKLIST
JOB NO:-

SITE LOCATION:-

CLIENT;-

INSPECTION DATE:-

PROJECT:FABRICATION AND ERECTION OF 10,000 LTRS WATER TANK ON 10M TOWER
1. CIVIL WORKS:
1
2
3
4
5

Is the dimension of the foundation according to specification?
Is the foundation surface level? Both squarely and diagonally?
Are the positions of holding down bolts according to specification

Drwg Reference
DRG 01
DRG 01
DRG 01

II. FABRICATION
1
2
3
4
5
6
7
8
9
10
11
12
13
14

N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A

15
16

Are the floor plates cut according to specification?
Are the thicknees of the floor plates conform with specification?
Are shell plates corrugation conform with specification?
Are the thicknees of the shell plates conform with specification?
Are the thicknees of the roof plates conform with specification?
Is the right size and thickness used for safety hand rail?
Is the right size and thickness used for curb ring?
Is the right size and thickness used for safety hand rail?
Is the right size and thickness used for Stanchion?
Is the right size and thickness used for Horizontal Bracing?
Is the right size and thickness used for Diagonal Bracing?
Is the right size and thickness used for Main Beam ana Tank Beam?
Is the right size and thickness used for Diagonal Bracing?
Are the holes on the Hand rail post conform with specification?
Are the holes on the Horizontal Bracing and Diagonal Bracing conform with
specification?
Are the holes on the Stanchion and Gusset plate conform with specification?

1
2
3
4
5
6
7
8
9
10
11
12
13

Are the floor plates properly laid on the Tank Beam?
Is the welding joint of floor plates according to specification ?
Is the welding joint of shell to floor plates according to specification ?
Is the outside dimension of tank shell conform with specification?
Are the roof plates properly laid on the Tank?
Are the Stanchion properly bolted onto the Foundation Bolt?
Are the Stanchion properly Plumb?
Is the dimension of the Stanchion conform with specification?
Are all the Bolts on Stanchion, D/Horizontal bracing properly tightened?
Are all the Bolts on Main Beam and Tank Beam properly tightened?
Is the position of inlet, outlet and wash out pipe conform with specification?
Is the position of Air vent conform with specification?
Is the position of Air vent conform with specification?

N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A

1
2
3
4
5
6
7
8
9
10

Has the tank been cleaned - of
Is the require paints used
Is the painting process in line with painting procedure
Is the paint film thickness conform with the specification

N/A
N/A
N/A
N/A

III. TANK ERECTION

IV. FINISHING

N/A
N/A

YES

NO

INSPECTED BY:
PQE

APPROVED BY
HQA/QC

REMARK

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close