Project Finance Presentation for EDAMA
Eversheds LLP Thursday 16th March 2013
Limited Recourse and Non Recourse Financing – Terms used interchangeably
• What is it?
“The financing of the development or exploitation of a right, natural resource or other asset where the bulk of the financing is to be provided by way of debt and is to be repaid principally out of the asset being financed and its revenues.”
• Key features
Financing – Possible routes
• Limited/Non recourse debt for greenfield projects • • • • • What is limited recourse The “full scope “project finance version, allowing significantly lower equity commitments It is available, but requires to go through a specific discipline Subject to rating agencies perception
Limited/Non recourse refinancing of operational projects • • • Available now that more projects are actually operational and have good track records Simpler than greenfield as all construction contractual & management issues have been resolved May take the form at some point of portfolio refinancings (and allow for sale of minority stakes in these as well)
•
Sale of minority stakes in projects, pre- or post-completion • • • • Allows to recycle capital invested in existing projects into new ones without loss of operational control Recent transactions have shown there is appetite from many types of investors for these assets Most interested investors to date prefer to avoid construction risk, but that will change Allows capture of value through long term O&M arrangements or PPAs
Project Finance Structure
Shareholders
Landlord Leases
SPV
Security (Debenture) Limited Recourse Facility
Banks
Offtaker Direct Agreements and Assignments Subcontractors Subcontractors Subcontractors
Key elements of bankability of wind projects
Property and planning
• • • • • • • • Option for lease and lease Term of lease Certainty of rental and other costs - RPI Termination rights Direct Agreement Grid Connection - wayleaves Site access roads Adjacent rights - restrictions
Energy Yield
• Wind/Solar Data • Correlation • P50/P90 – debt sizing
Debt to Equity
• • • • • History of developer Site Funding shortfalls Contingent equity Change of control
Grid Connection
• • • • Date of connection Capacity Land rights Remedies
Technology
• • • • Turbine supplier/Panel Supplier Warranties O&M Currency risk
PPA
• • • • • • Term Contract Price Price adjustments Change in law Counterparty risk Security arrangements
Construction
• • • • • • Longstop date Assumed completion date Liquidated damages Collateral warranties Interface issues – multi-contracting Insurance and title transfer
Operational
• • • • • • O&M agreement Project management agreement Availability guarantees (95%-97%) Debt service reserve Maintenance reserve Monitoring
Bank Protections
• • • • • • • Security structure Intercreditor issues Distributions and distribution conditions Reporting requirements Accounts and project revenue control Insurance Hedging agreements
Lender – Sponsor Friction points
• How intrusive is the due diligence? • • • Review of interfaces, sub-contracts, logistics and project management – irrespective of contractual structure Review of technology, supply chain, quality control processes, key personnel, sub-contractor creditworthiness Requirement for a number of PF-standard clauses More explicit warranty and interface language Decision on number of contracts Responsibility for vessels Parent company guarantees or performance bonds Detailed information – and at times, validation of decisions Share retention clauses Debt: Equity 70:30 Equity Upfront Consecutive O&M assumptions Tenor, scope, liability, fixed price, counterparty Options to exit after a few years
How involved are the banks (or relevant advisors) in contract negotiation? • • • • •
•
How strict are the financial covenants? • • • • •
•
What are the terms and conditions for long term O&M? • •
PF or not to PF (1)
• It helps improve risk discipline for the project
• • • • More external eyes on contracts, interfaces and detailed project structure Specific focus by banks and their advisors on potential downside scenarios Project can “work” on a stand-alone basis (which makes it easier to sell)
It can help investors – and contractors!
•
• •
Blame the Bank
Less zero-sum negotiations
It’s really limited/non-recourse • • Banks take construction risk on the basis of the contracts and committed contingency mechanisms While sponsor involvement is valued, banks evaluate deals with no expectation of additional cash in
•
Pricing will come down
PF or not to PF (2)
• It needs to be an early decision by investors • • A lot of the value from project finance discipline comes at an early stage, when choosing the contractual structure and negotiating the relevant contracts The good news is that a lot of that work can be done without involving large banking groups, by using a small number of specialised advisors
•
It requires experienced advisors
•
• • •
Bring in at your side entities which have credibility as lenders’ advisors and ask them to look at the project from the perspective of lenders
Good, legal, financial and technical advisors are indispensable Pre-packaging a deal that banks will accept
Investors and contractors need to be committed to it • • Counterparties will accept to incorporate banks’ requirements in their commercial offers only if they really believe that the project will not happen without external financing Take into account the feedback from specialised advisors
Any Questions....
Indraj Mangat, Partner, Banking
Eversheds T. E. +44 776 741 1508
[email protected]
...Thank you!
© EVERSHEDS LLP 2013. Eversheds LLP is a limited liability partnership.