4. Answer the following questions for the following network. Times shown are in days.
a. What is the length of the critical path?
b. What are the earliest start and latest start for E?
c. What is the latest start for B?
d. If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?
Comments
Content
GSCM 530 DeVry Week 5 Homework Assignment
GSCM530
GSCM 530 DeVry Week 5 Homework Assignment
GSCM 530 DeVry Week 5 Homework Assignment
4. Answer the following questions for the following network. Times shown are in days.
a. What is the length of the critical path?
b. What are the earliest start and latest start for E?
c. What is the latest start for B?
d. If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes five days instead of the expected three?