MS Project With Project Management Basics

Published on June 2016 | Categories: Types, Presentations | Downloads: 36 | Comments: 0 | Views: 134
of 42
Download PDF   Embed   Report

MS Project With Project Management Basics

Comments

Content

Project Management Basic concepts
with
®
Microsoft Project 2010

By:
Abdul Ghaffar PMP
[email protected]
+923434017209

Objective
• Projects Management Basics





What is a Project
Project Constraints
Project Planning, Monitoring & control
WBS

• Getting started with MS Project
(General Schedule Settings and Currency)

• Creating Project in MS Project





10/06/2014

Project Calendar
Task List
Task Notes
Duration
Linking Tasks
By : Abdul Ghaffar, PMP

3

Objective …
– Lead & Lag
– MileStone
– Network Diagram
– Critical Path
– Adding Resource and its cost
– Creating Baseline
– Custom Fields

• Tracking Project
• Other Views and Reports
10/06/2014

By : Abdul Ghaffar, PMP

4

What is a Project?
A project is a temporary endeavor that helps to
accomplish some specific objective by utilizing definite
interconnected tasks and the effective utilization of
resources.








10/06/2014

To achieve an objective
One Time (Start and finish dates)
Constraints of time, cost and resources
Performed by People – Single or Group
Coordinated and controlled activities
Specific Deliverables
Progressive Elaboration

By : Abdul Ghaffar, PMP

5

Major Constraint on Project

10/06/2014

By : Abdul Ghaffar, PMP

6

Project Process Groups

10/06/2014

By : Abdul Ghaffar, PMP

7

PMBOK 5
10/06/2014

By : Abdul Ghaffar, PMP

8

WBS for MS Project Training
1. Soft ware
Development Plan

1.10
1.1
Scope

1.2
Analysis/Soft
ware
Requirements

1.3
Design

1.4
Developme
nt

1.5

1.6

Testing

Training

1.7
Documenta
tion

1.8
Pilot

1.9

Post
Deploymen Implement
ation
t
Review

1.5.1
Unit Testing
1.5.2
Integration Testing

10/06/2014

By : Abdul Ghaffar, PMP

9

Starting With MS Project 2010
File
->options
-> Display

10/06/2014

By : Abdul Ghaffar, PMP

10

Starting With MS Project 2010
File
->options
-> Schedule

10/06/2014

By : Abdul Ghaffar, PMP

11

MS Project 2010

10/06/2014

By : Abdul Ghaffar, PMP

12

Task List

10/06/2014

By : Abdul Ghaffar, PMP

13

Task Duration

10/06/2014

By : Abdul Ghaffar, PMP

14

WBS Code

10/06/2014

By : Abdul Ghaffar, PMP

15

Sub Task

10/06/2014

By : Abdul Ghaffar, PMP

16

Link Task..
where the first must be finished before
Finish to Start (FS),

Start to Start (SS),

Finish to Finish (FF),

the next begins.
where 2 tasks must start at the same
time.
where 2 tasks must end at the same time.

where the start of the first is linked to
Start to Finish (SF) ,

the completion of the second (with a lag
time specified as well.

10/06/2014

By : Abdul Ghaffar, PMP

17

Link Task

10/06/2014

By : Abdul Ghaffar, PMP

18

Predecessors

10/06/2014

By : Abdul Ghaffar, PMP

19

Lead & Lag Time
• Lead time causes a successor task to overlap
a predecessor even though they are linked
finish to start (FS).
• Lag time allows you to add a delay between
the start of the successor and the end of the
predecessor.
– Simply specify lead or lag time in the
Predecessor column.
• Lead time is represented with a minus sign (-)
• Lag time is represented with a plus sign (+).

10/06/2014

By : Abdul Ghaffar, PMP

20

Lead and Lag

10/06/2014

By : Abdul Ghaffar, PMP

21

Calendar

10/06/2014

By : Abdul Ghaffar, PMP

22

MileStone

Milestones let you gauge your progress through the project.
10/06/2014
By : Abdul
Ghaffar, PMP
It’s
good practice to include a Start and Finish
Milestone
for each division/part of your WBS.

23

Resource

10/06/2014

By : Abdul Ghaffar, PMP

24

Assign Resources to Tasks

10/06/2014

By : Abdul Ghaffar, PMP

25

The Critical Path
The Critical path is the flow of tasks, of which,
a delay in any one of these tasks will cause a
delay to the project.
It is the longest path through the project
network diagram and the shortest possible
time to complete the project

10/06/2014

By : Abdul Ghaffar, PMP

26

Critical Path

10/06/2014

By : Abdul Ghaffar, PMP

27

Critical Path..

10/06/2014

By : Abdul Ghaffar, PMP

28

Slack

Slack is the amount of time that a task can slip before it affects another task
or the project's finish date. By : Abdul Ghaffar, PMP
10/06/2014

29

Custom Field

10/06/2014

By : Abdul Ghaffar, PMP

30

Tracking Project
To control the variations from actual plan (baseline)
we need to track project and continuously check
the health of the project.
• EVM is a financial measurement tool that
combines the conflicting aspects of scope,
schedule and cost into a unified set of metrics.
• These metrics can be used for measuring,
monitoring, reporting and forecasting project
performance. It can be used through all the
phases of a project, from initiation to closure.
10/06/2014

By : Abdul Ghaffar, PMP

31

Earned Value …

10/06/2014

By : Abdul Ghaffar, PMP

32

Example
You have a project to build a new fence. the fence is
four sided as shown.
Each side is to take one day to build and is budgeted
for $1000 per side.
The sides are planed to be completed one after the
other.
Today is the end of day three.

• Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc.
10/06/2014

By : Abdul Ghaffar, PMP

33

Plan Tasks

10/06/2014

By : Abdul Ghaffar, PMP

34

Set Baseline

10/06/2014

By : Abdul Ghaffar, PMP

35

Actual Status

10/06/2014

By : Abdul Ghaffar, PMP

36

Check Status

10/06/2014

By : Abdul Ghaffar, PMP

37

Status Summary

10/06/2014

By : Abdul Ghaffar, PMP

38

Calendar View

10/06/2014

By : Abdul Ghaffar, PMP

39

Network Diagram

10/06/2014

By : Abdul Ghaffar, PMP

40

Other Reports

10/06/2014

By : Abdul Ghaffar, PMP

41

THANKS

10/06/2014

By : Abdul Ghaffar, PMP

42

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close