Project Management Basic concepts
with
®
Microsoft Project 2010
By:
Abdul Ghaffar PMP
[email protected]
+923434017209
Objective
• Projects Management Basics
–
–
–
–
What is a Project
Project Constraints
Project Planning, Monitoring & control
WBS
• Getting started with MS Project
(General Schedule Settings and Currency)
• Creating Project in MS Project
–
–
–
–
–
10/06/2014
Project Calendar
Task List
Task Notes
Duration
Linking Tasks
By : Abdul Ghaffar, PMP
3
Objective …
– Lead & Lag
– MileStone
– Network Diagram
– Critical Path
– Adding Resource and its cost
– Creating Baseline
– Custom Fields
• Tracking Project
• Other Views and Reports
10/06/2014
By : Abdul Ghaffar, PMP
4
What is a Project?
A project is a temporary endeavor that helps to
accomplish some specific objective by utilizing definite
interconnected tasks and the effective utilization of
resources.
•
•
•
•
•
•
•
10/06/2014
To achieve an objective
One Time (Start and finish dates)
Constraints of time, cost and resources
Performed by People – Single or Group
Coordinated and controlled activities
Specific Deliverables
Progressive Elaboration
By : Abdul Ghaffar, PMP
5
Major Constraint on Project
10/06/2014
By : Abdul Ghaffar, PMP
6
Project Process Groups
10/06/2014
By : Abdul Ghaffar, PMP
7
PMBOK 5
10/06/2014
By : Abdul Ghaffar, PMP
8
WBS for MS Project Training
1. Soft ware
Development Plan
1.10
1.1
Scope
1.2
Analysis/Soft
ware
Requirements
1.3
Design
1.4
Developme
nt
1.5
1.6
Testing
Training
1.7
Documenta
tion
1.8
Pilot
1.9
Post
Deploymen Implement
ation
t
Review
1.5.1
Unit Testing
1.5.2
Integration Testing
10/06/2014
By : Abdul Ghaffar, PMP
9
Starting With MS Project 2010
File
->options
-> Display
10/06/2014
By : Abdul Ghaffar, PMP
10
Starting With MS Project 2010
File
->options
-> Schedule
10/06/2014
By : Abdul Ghaffar, PMP
11
MS Project 2010
10/06/2014
By : Abdul Ghaffar, PMP
12
Task List
10/06/2014
By : Abdul Ghaffar, PMP
13
Task Duration
10/06/2014
By : Abdul Ghaffar, PMP
14
WBS Code
10/06/2014
By : Abdul Ghaffar, PMP
15
Sub Task
10/06/2014
By : Abdul Ghaffar, PMP
16
Link Task..
where the first must be finished before
Finish to Start (FS),
Start to Start (SS),
Finish to Finish (FF),
the next begins.
where 2 tasks must start at the same
time.
where 2 tasks must end at the same time.
where the start of the first is linked to
Start to Finish (SF) ,
the completion of the second (with a lag
time specified as well.
10/06/2014
By : Abdul Ghaffar, PMP
17
Link Task
10/06/2014
By : Abdul Ghaffar, PMP
18
Predecessors
10/06/2014
By : Abdul Ghaffar, PMP
19
Lead & Lag Time
• Lead time causes a successor task to overlap
a predecessor even though they are linked
finish to start (FS).
• Lag time allows you to add a delay between
the start of the successor and the end of the
predecessor.
– Simply specify lead or lag time in the
Predecessor column.
• Lead time is represented with a minus sign (-)
• Lag time is represented with a plus sign (+).
10/06/2014
By : Abdul Ghaffar, PMP
20
Lead and Lag
10/06/2014
By : Abdul Ghaffar, PMP
21
Calendar
10/06/2014
By : Abdul Ghaffar, PMP
22
MileStone
Milestones let you gauge your progress through the project.
10/06/2014
By : Abdul
Ghaffar, PMP
It’s
good practice to include a Start and Finish
Milestone
for each division/part of your WBS.
23
Resource
10/06/2014
By : Abdul Ghaffar, PMP
24
Assign Resources to Tasks
10/06/2014
By : Abdul Ghaffar, PMP
25
The Critical Path
The Critical path is the flow of tasks, of which,
a delay in any one of these tasks will cause a
delay to the project.
It is the longest path through the project
network diagram and the shortest possible
time to complete the project
10/06/2014
By : Abdul Ghaffar, PMP
26
Critical Path
10/06/2014
By : Abdul Ghaffar, PMP
27
Critical Path..
10/06/2014
By : Abdul Ghaffar, PMP
28
Slack
Slack is the amount of time that a task can slip before it affects another task
or the project's finish date. By : Abdul Ghaffar, PMP
10/06/2014
29
Custom Field
10/06/2014
By : Abdul Ghaffar, PMP
30
Tracking Project
To control the variations from actual plan (baseline)
we need to track project and continuously check
the health of the project.
• EVM is a financial measurement tool that
combines the conflicting aspects of scope,
schedule and cost into a unified set of metrics.
• These metrics can be used for measuring,
monitoring, reporting and forecasting project
performance. It can be used through all the
phases of a project, from initiation to closure.
10/06/2014
By : Abdul Ghaffar, PMP
31
Earned Value …
10/06/2014
By : Abdul Ghaffar, PMP
32
Example
You have a project to build a new fence. the fence is
four sided as shown.
Each side is to take one day to build and is budgeted
for $1000 per side.
The sides are planed to be completed one after the
other.
Today is the end of day three.
• Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc.
10/06/2014
By : Abdul Ghaffar, PMP
33
Plan Tasks
10/06/2014
By : Abdul Ghaffar, PMP
34
Set Baseline
10/06/2014
By : Abdul Ghaffar, PMP
35
Actual Status
10/06/2014
By : Abdul Ghaffar, PMP
36
Check Status
10/06/2014
By : Abdul Ghaffar, PMP
37
Status Summary
10/06/2014
By : Abdul Ghaffar, PMP
38
Calendar View
10/06/2014
By : Abdul Ghaffar, PMP
39
Network Diagram
10/06/2014
By : Abdul Ghaffar, PMP
40
Other Reports
10/06/2014
By : Abdul Ghaffar, PMP
41
THANKS
10/06/2014
By : Abdul Ghaffar, PMP
42