PROGRESS REPORT (1st Week March 2015)
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Outstanding Work (In Progress)
Section
Activity
Building
Architectural
Works
Brickwall-in-Position
Plastering Work
Ceiling Works
M&E Works
Percent
age
97%
Man
Power
Pre-Successor
Activity
FF-Sprinkler
Pump
Successor Activity
Remark
Bricklayering
->Plastering
Level Lower Ground- 85%
89%
22%
Level Lower Ground- 40%
Framing Works - 50%
Piping & Conduiting Works
- Cold+Hot Water & Plumbing Works
- Fire Fighting Services
- Electrical Services
- ELV Services
- HVAC Services
Cabling & Wiring Works
- Cold+Hot Water & Plumbing Works
- Fire Fighting Services
- Electrical Services
- ELV Services
- HVAC Services
PROGRESS REPORT (1st Week March 2015)
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Ceiling frame
Third Floor- 3017,3018,3021
Fourth floor -left ac storage room 4007
Request for information
1. Advice from id designer on the finishing near
window
Skim Coat
Electric Wiring
ELV
Housekeeping /
Demobilization
2nd Floor
12/27
room
complet
ed
3rd floor
Main
cabling
on
corridor
Install
busbar
ground
floor
3rd floor
typical
room
6
Two days render Demonstration on supplier 2223/1/2015
Ideal Thickness: 5-7mm
Bad weather caused delay
6
Main progress still on typical room
Busduct TPN already install for riser staircase 3.
#Ensure the electrical room out of water.
Request for information
1. Any isolator for submersible pump and standby
pump for sump pit_lower ground ?
4
Request for information
1. Need of cctv installation along fencing?
2.
Banyan start to remove their rebar wastage by
26/1/2015.
Expect Manager briefing on Site preparation on
receiving scheduled incoming material and setting out
site storage with protected security {URGENT}
3
Excavation on
Retaining Wall,
New Store Room
(12mx16m)
PROGRESS REPORT (1st Week March 2015)
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Plumbing
2
Internal Plumbing 4th
Floor
Dewatering on
Basement
1
Wall plastering,
Crack repair
Lift Core
Repairing crack
Water tightness on
internal Building
Crack Sprinkler Tank
Fencing
Main Drainage
aircond
Window subframe
Lift installation
Sealing some
windows with
plywood+silicon
(Location: Lift motor
Room, lift lobby,
switchboard room),
Lift Installation,
Switchboard Room
7
2
4
Bricklayering
ID Drawing
Bricklayering
5017 on toilet
Expect sub-contractor start housekeeping on all
wastage.
Hydrostatic test will redo again after ID finalized.
Request for information
1. Insufficient detail on laundry room
=source of hot water? Need water heater?
= the cw and hw pipe are concealed or
exposed?
2. Request catalogue for all plumbing fixture etc.
New kerb on preventing water entering lift entrance
lower ground
Improving external drainage to prevent inflow water into
building
*Mud Flow on entrance after storm rain 16/1/2015
*Structural Repair claimed insufficient thickness of
reinforced concrete (1inch) on the edge lead to
dampness on the lift core.
*They reported waterstop failure on Passenger lift along
the certain perimeter of lift core.
Some rooms were flooded due to incoming of heavily
rain through window opening.
Q: Necessary to temporarily seal some windows?
High risk zone: Busbar riser, render storage, ac storage
room, lift
Pending Structural Repair for investigation report
Main activities on retaining wall
Pending arrival of precast drain (estimation 3 weeks)
Drainage problem (sitting lounge)
Rectification on 5 windows due to wrong positioning
(>1 inch).
Inspection on squareness of window and alignment will
PROGRESS REPORT (1st Week March 2015)
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Handrail roof garden
Plastering on Hose
Reel Room
Internal plastering 5th
floor
Sealing gap on fixed
glass near meeting
room
Screeding on pump
room
Hacking the
problematic wall due to
plumbing pipe on
cafeteria.
Cement Skim Coat RC
Plinth
Lintel /stiffener on
3021/3022
Bricklayering on 4th
floor corridor in replace
hitching waterproofing
Toilet screeding and
wall plastering
Painting
2024, 3023, 4018,
5018)
Start marking and
Plastering on rc wall
for handrail (24-12015)
Plastering->Wall
Painting -> Hose Reel
Piping -> Hose Reel
Drum (critical on 5th
floor)
Floor screeding
2
15%
40%
be completed on Thursday 29/1/2015.
Wrapping protection on Handrail completed.
Plastering on fire hose reel compartment 1st / 4 /5 floor
completed.
Expectation on completing plastering on Wed 28/1/2015
Ceiling frame
Bricklayering
->Plastering
Remove loading
bay
Housekeeping
wastage
Rendering ->
Mock Up
Sample
-After CNY
-For ground floor, current external wall (without
rendering) is ideal for painting(commented by TBS
Tang).
PROGRESS REPORT (1st Week March 2015)
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Mark level on flooring
(GF-meeting Room)
Concreting on toilet
floor 3011
Additional beam or
lintel support for FG
15/16/17/18
Coring 5th floor Soil
Pipe
And sitting lounge
Ceiling Gypsum Board
on first floor
Opening for exhaust
fan for switch board
room + toilet Roof
Garden + lift motor
room
Inspection on Staircase
2
Hacking parapet wall
Roof Garden
Ceiling Evenness
Basement
Screeding on AC Room
each floor
Screeding RC ledge
first floor + fourth floor
Discrepancy between old and new drawing
Seek CHT
Consultant
advice, EOT
drawing
Request for information
1. Dimension on fg 15/16/17/18 from EOT
2. Structural design on lintel for fg 15/16/17/18
from CHT consultant
Request for information
1. Latest id drawing
Final ID
Drawing, M&E
Inspection, M&E
As built drawing
Checklist completed and will be distributed to contractor.
Request for information
1. Enquiry model of exhaust fan.
2. Need of any subframe for the exhaust fan.
Staircase work report will completed 28/1/2015
WEDNESDAY.
Pending final
EOT design
Planned mock up painting on ceiling lower ground for
review the finishing work_cement skim coat on Monday
26/1/2015. Check the work of cement skim coat.
External
Plastering