PROGRESS REPORT
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
Schedule

Activity

On-going
Progress

Plastering

PreSuccessor
Activity

Successor Activity

Left Side70%
Front- 90%
Back-80%
Right- 65%
Unconfirmed

Skim Coat

2nd Floor
3rd floor

Electric Wiring
ELV
Housekeeping /
Demobilization
Plumbing

Dewatering on
Basement
Lift Core
Water tightness on
internal Building

Crack Sprinkler Tank
Fencing
Main Drainage
aircond
Window

Percentage

Excavation on Retaining Wall,
New Store Room (12mx16m)
Internal Plumbing 4th Floor

Repairing
crack
Housekee
ping on
waste pipe
(avoid
blockage)

Remark

Ideal Thickness: 5-7mm in single coat
Onsite thickness: 2-3mm with removed small particles
Render Supplier responded the chalkiness of render due to
insufficient thickness. With current 2-3mm with removed
small particles, there would be potential crack defect after
exposure to sun.
Main progress on typical room

Wall plastering, Crack repair

-insufficient detail on laundry room (Refer to Ruth)
-Request catalogue for all plumbing fixture etc.
-completed temporary divert RWDP and waste pipe to
external surrounding
-warning Plastering worker on damage incident on pipe
plug)
Mud Flow on entrance after storm rain 16/1/2015

Lift installation

*leaks another place after first PU injection

Sealing some windows with
plywood+silicon (Location: Lift
motor Room, lift lobby,
switchboard room), Lift
Installation, Switchboard Room

Pending thin plywood from Hardware

Bricklayering
ID Drawing
Bricklayeri
ng 5017

Critical

5017, 4014, 3021,3022, sitting
lounge toilet (1025, 2024, 3023,

Pending Structural Repair for investigation report
level
Pending arrival of precast drain (estimation a month)
Drainage problem (sitting lounge)

PROGRESS REPORT
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
on toilet

Planned

Wrapping handrail roof
garden
Plastering on Hose Reel
Room
Screeding on pump
room
Cement Skim Coat RC
Plinth
Internal plastering 5th
floor
Lintel /stiffener on
3021/3022
Bricklayering on 4th floor
corridor in replace
hitching waterproofing
Toilet screeding and wall
plastering
Painting

Mark level on flooring
(GF-meeting Room)
Concreting on toilet floor
3011
Additional beam or lintel
support for FG
15/16/17/18

Coring 5th floor Soil Pipe
Coring switch board
room opening

Opening for exhaust fan
for switch board room +

4018, 5018)

Plastering->Wall Painting -> Hose
Reel Piping -> Hose Reel Drum

15%

Yes

Pending contractor action
No further action from both contractors since memo on
1/1/2015

Bricklayering
->Plastering

Floor screeding
Remove
loading
bay
Housekee
ping
wastage

Rendering
-> Mock
Up Sample

-After CNY
-For ground floor, current external wall (without rendering)
is ideal for painting(commented by TBS Tang).

Discrepancy between old and new drawing
Seek CHT
Consultant
advice,
EOT
drawing
Exchange
6’’ Coring
bit at Hua
Chang

PROGRESS REPORT
PROJECT:
Proposed One Block of 6-Storey Executive Suites with Commercial Space on Lot 3493, BTD, Jalan Tun Razak, Bintulu
toilet Roof Garden
Inspection on Staircase
2

#Fadzil

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close